Resource allocation
Fichas del conjunto (3)
- 1What method is used for allocating resources to a schedule?A resource histogram
Each resource is charted showing the amount that each of them is planned to be used across the life of the project. - 2How is a resource histogram created?At the bottom of the Gantt chart.
The timescale follows the x-axis of the Gantt chart & the y-axis is the resources user per time period.
The histogram is shaded to reflect the value of resources planned week by week. - 3What are the benefits of using a resource histogram?See at a glance where resources are planned to be used.
Can confirm resource availability in accordance with the plan.
Can take steps to deal with resource issues.