GoConqr has a new look! Let us know what you think.

Flashcards

T022 Design Economics & Cost Planning - Cost Estimates & Cost Plans

Robert Binks English 4.0Average rating 4.0 out of 5 (1 rating) 53 cards

Cards in this deck (53)

  1. 1What types of estimate are there?Budget / feasibility
    Cost estimate
    Cost plan
  2. 2What is a feasibility estimate?A high level exercise to assess whether a project is financially viable and to set an outline budget for the scheme
  3. 3What is the format of a feasibility / budget estimate?Rate per m2 or per functional unit
    May be presented as a range
  4. 4What is a functional unit?The ‘factors which express the intended use of the building better than any other’
    E.g. number of bedrooms in a hotel, number of beds in a hospital
  5. 5What information do you need to be able to carry out a feasibility estimate?Type of building (function)
    New build or extension
    Location
    Size
    Indication of quality
    Site visit
  6. 6What is the % error on a feasibility estimate?10%
  7. 7What is a cost estimate?A forecast of the possible cost of a building based on historical data
  8. 8When would you do one?Stage C/D
  9. 9What are the principal components of a cost estimate?Construction costs
    Preliminaries
    Contractor’s OH&P
    Contingency
    Inflation
    Assumptions - programme
    Exclusions
    Area Schedule
    Basis of Estimate – drawings / specifications list
  10. 10Name the main elements of an elemental estimateSubstructure – excavation and substructure
    Superstructure – frame, upper floors, external walls, roof, internal finishes
    Services
    External works
  11. 11What is usually excluded from a cost estimate?Professional fees
    VAT
    Client decant costs
    Loose fixtures and fittings
    Inflation
    Site acquisition costs
    Section 106s
    Removal of asbestos
  12. 12Why is VAT excluded?Because different clients will incur different levels of VAT, might not be applicable
    We would not be in a position to know the correct rate unless informed of it
  13. 13What is the % error on a cost plan?5%
  14. 14What is contingency?A sum included in the estimate to cover unknown expenses or unmitigated risks during the project
  15. 15How is contingency assessed?The amount included should reflect the risks and unknowns specific to the project. During early estimates when little information is available it is common to include a %. At the end of stage C it is usually 10%. This should reduce as more information becomes available and the unknowns decrease
    At the end of Stage E it is usually 5% (2.5% design and 2.5% construction contingency). It is common to have a higher % for refurbishment work due to the higher level of unknowns and therefore risks
  16. 16What are preliminaries?They define the scope of works
    Include the project particulars, lists of drawings, desciprtion of the site, scope of work, details of management arrangements. Often contain items for pricing which are general items needed by the contractor to carry out the work that cannot be attributed to specific items of work
  17. 17Where do you find the guidelines to prepare preliminaries?SMM7
  18. 18Name some preliminaries sectionsA10 – project particulars
    A54 – provisional sums
  19. 19What should be considered when assessing preliminaries levels?Length of contract
    Location – accessibility, space restrictions, accommodation etc
    Type of project – new build / refurb, tower / one story etc
    Size of project
    Need for temporary works
    Need for security
    Limitations on method and sequencing of works, working hours – supervision requirements
    Sectional completion
    Availability of services
    Level of contractor’s designed works
  20. 20How do you take account of inflation when benchmarking / cost estimating?Through the use of TPIs
  21. 21What does TPI stand for? What do TPIs show?Tender Price Index, reflects changes in the level of pricing contained in the lowest accepted tenders for new work to take account of market conditions – compares against base rates
  22. 22Where can you get this information from?BCIS
    TPI forecasts – published in Building
    In house forecasts
  23. 23How do you take account of location? Why do you need to take account of location?Through the application of location indices
    Different market conditions in different locations
    Different cost of materials, different wage rates etc – impact on tender levels
  24. 24What is BCIS?Building Cost Information Service
    Provides construction cost and price information through publications, online services and price books
  25. 25What is a cost plan?Presents the estimated cost into a structural elemental or functional format
    It shows how the design team proposes to distribute the funds available on the elements of the proposed building.
  26. 26What is the purpose of a cost plan?It is used by the cost consultant to control the development of the design
    It identifies the client’s agreed cost limit and how the money is to be allocated to the different parts of the building.
  27. 27What is the difference between a cost estimate and a cost plan?Cost plan is a plan of costs for the works in preparation for turning into a cost report to check against.
    Estimate is a forecast of construction cost
  28. 28What is buildability? What are the advantages of buildability?Harnessing the contractor’s expertise and knowledge during the design stage.
    Better programming, sequencing and construction methods – a quicker construction time
    Lower capital and life cycle costs
    Improved quality in the finished building’s performance and maintenance characteristics
  29. 29What is a wall to floor ratio?This shows the relationship between wall area and floor area
    It is used to show the cost efficiency of the building
    The lower the ratio the cheaper the building as there is less external wall area per m2 of floor area
  30. 30What is the most efficient shape?A circle
    BUT this is not the most efficient shape as it has a poor lettable floor area – difficult to fit out
    THEREFORE a square is the best
  31. 31What is the difference between cost and price?Cost is the total of labour, plant, materials and management deployed for a specific activity
    Price is the amount a purchaser / client will pay for an item or product – it is cost plus profit
  32. 32What information would you expect the design team to provide at stage D?Detailed design information approaching that of tender documentation.
  33. 33How would you prepare an estimate for M&E works?I would ask an M&E specialist surveyor to undertake the estimate
    For feasibility estimates the M&E amount would be included in the m2/functional unit rate
  34. 34What is GEA?Gross External Area
    This is the area of the building measured externally at each floor level
  35. 35What is GIA?Gross Internal Area
    This is the area of the building measured to the internal face of the perimeter wall at each floor level
    Excludes external open sided balconies, fire escapes, canopies, external walls, fuel stores
  36. 36What is NIA?Net Internal Area
    This is the area of usable space measured to the internal face of the perimeter wall at each floor level
    Excludes the above and internal structural walls and columns, spaces with headroom less than 1.5m, corridors and circulation space used in common, permanent lift lobbies, toilets, cleaners cupboards, plant rooms
  37. 37Where are all of these defined?The Code of Measuring Practice, 6th Edition, published by the RICS
  38. 38What is the purpose of the Code of Measuring Practice?Provides precise definitions to permit the accurate and consistent measurement of buildings
  39. 39What would you expect the percentage of NIA to GIA / GEA to be?It depends on the type of project being undertaken (school, hospital, office etc…)
    If it were an office build I would expect the NIA to GIA to be in the region of 70-85%, where 70% is not good and 85% is excellent.
  40. 40Where do you get cost information from?In house historic data
    Benchmarks
    BCIS
    Building cost models
    SPONS and other price books (Laxtons etc)
    Sub contractors and suppliers
  41. 41What do you measure in accordance with?SMM7 or NRM2
  42. 42What does SMM7 stand for? What does it do?Standard Method of Measurement, Edition 7
    SMM7 identifies the unit to which the work is measured and the requirements of measuring the works.
    SMM7 is authorised by agreement between the Royal Institution of Chartered Surveyors and the Construction Confederation.
  43. 43How do you measure steel under SMM7 – and what other items would you measure in association?Under SMM7 steel is measured in Tonnes.
    Other items to measure in association with steelwork include framing erection, permanent formwork, cold rolled purlins and cladding rails, isolated structural member, filing hollow sections, surface preparation, surface treatment and localised protective coating. (G)
  44. 44How do you measure brickwork walls under SMM7 – and what other items would you measure in association?Under SMM7 brickwork walls are measured in m2. Other items to measure in association with brickwork include:
    Isolated piers,
    Isolated casings,
    Chimney stacks,
    Projections,
    Arches,
    Brick reinforcement,
    Sundry items,
    Forming cavity,
    Closing cavities
  45. 45What is a Section 106 agreement?They are also referred to as planning obligations
    They are typically agreements between local authorities and developers negotiated in the context of granting planning consent
  46. 46What sort of things is the Section 106 agreement money spent on?Affordable housing
    New open space or environmental improvements
    New roads and transport capacity
    Health and education facilities
  47. 47What is construction to ‘shell and core’?The basic structure, services and envelope of the building AND the fit out of landlord / common areas
    E.g. reception, toilets, lifts, cores, base services are terminated at breakout points to floors, life safety services infrastructure
  48. 48What is a CAT A fit out?Also known as a ‘developer’s fit out’
    Provides the generic requirements to suit most developers
    E.g. life safety elements and basic fittings - suspended ceiling tiles, raised floors, carpet, lighting, power distributed to floor plates
  49. 49What is a CAT B fit out?Overlays the CAT A provision with bespoke elements particular to the needs of the building user to enable the tenant to occupy and use the space
    E.g. partitions, power distributed to floor boxes, data cabling, artwork and branding, upgrading CAT A finishes and toilet finishes etc
  50. 50Where could you find the definitions for these?British Council of Offices (BCO) fit out guide
  51. 51What is BWIC?BWIC stands for Builders Work In Connection and is usually set as a percentage of the services cost.
    Depending on the size of the job and complexity will determine the percentage of BWIC.
    BWIC accounts for any drilling, fixing, cutting etc… that the builders do whilst undertaking the services.
    BWIC can be measured in accordance with SMM7 when doing a BOQ’s.
  52. 52What cost would you expect for a new build city centre office tower in London? What cost would you expect for a CAT A fit out to that office? What about a CAT B fit out? What cost would you expect for a retail shopping centre?Know what your own schemes have cost
  53. 53What cost would you expect for a warehouse? What cost would you expect for a hotel? What cost would you expect for city centre residential tower?Know what your own schemes have cost.

Information

Description
Flashcards on T022 Design Economics & Cost Planning - Cost Estimates & Cost Plans, created by Robert Binks on 06/09/2014.
Created by
Robert Binks
Views
397
Rating
Average rating 4.0 out of 5 (1 rating)

Feedback

What is it about?

What do you think of the new look?

How do you like it?