Production lecture 5

Elisa Vink English 12 cards

Cards in this deck (12)

  1. 1(machine) scheduling-scheduling is the final stage of production planning
    - scheduling can be defined as: prescribing of when and where each operation necessary to produce a product is to performed, fixing up starting and finishing times of each operation comprising a procedure
  2. 2Goal- making a feasible production schedule
    - making an optimal production schedule
  3. 3scheduling = optimisation problem- given: machine(s), operations/jobs
    - decisions: for every operation/job: on what machine, start times of the operations
    - objective: several choices, depending on the production strategy
    - constraints: capacity constraints of the machines, operations cannot overlap, operations cannot be interrupted
  4. 4Input scheduling processFor job j:
    - Pj (processing time)
    - Rj (release date): time at which job j is available for processing
    - Dj (due date): time at which the processing of job j is due to be completed
  5. 5output scheduling process- Wj (waiting of job j): time that job j has to wait in the system before its processing starts
    - Cj (completion time of job j): time at which job j finishes
    - Fj (flow time of job j): time time that job j spends in the system
    - Lj (lateness of job j) = Cj - Dj
    - Tj (tardiness of job j): Tj = Lj if Lj > 0, 0 otherwise
    M (makespan): moment at which the last job is finished
  6. 6Objectives- minimize total time to run the entire set of jobs (sequence does not matter); makespan = sum of setup and run times for any sequence jobs
    - minimize the average time each job spend at the machine (sequencing jobs in ascending order according to their total processing time, setup + run time)
    - shortest processing time SPT: average time in the system will always be minimized by selecting the next job processing that has the shortest processing time at the current operation.
  7. 7Priority rules (sequencing rules)use of logic rules that guide the prioritizing of job at a work station:
    - random: often used as a benchmark for other rules
    - FIFO/FCFS: 'fair' in that jobs are processed in the order they arrive at the work center
    SPT: shortest processing time first: reduce work in process inventory, average job completion time, average job lateness
    - LPT: longest processing time first
    - EDD: earliest due date: work well for criteria associated with job lateness
  8. 8SPTfor the basic single-machine scheduling problem, the SPT-priority rule minimizes the;
    - average flow time
    - average number of jobs in system
    - average waiting time
    - average lateness
    - Max. waiting time
  9. 9EDD- for the basic single-machine scheduling problem the EDD-priority rule minimizes; maximum lateness Lmax and maximum tardiness Tmax
    - if the objective is to minimize the number of tardy jobs: if EDD leads to a schedule with no tardy jobs, the schedule is an optimal schedule otherwise, you can use (Moore-)Hodgson's algorithm to make an optimal schedule
  10. 10(Moore-)Hodgson's algorithmminimizes the number of tardy jobs in the single machines environment with ready time equal to zero
  11. 112 machine flow shop; johnson's ruleJohnson's rule minimizes the makespan
  12. 12complexity of scheduling problems- for some scheduling problems simple methods exist to calculate an optimal schedule, but many scheduling problems are very complex
    - for a lot of scheduling problems no simple method exists to determine an optimal schedule
    - these problems are frequently modeled as (mixed) integer linear program (M)ILP
    - often binary variables are used that indicate; wether a job is assigned to a machine, wether an employee is assignment to a machine

Information

Description
Flashcards on Production lecture 5, created by Elisa Vink on 11/10/2020.