- 1What is Standard Costing?Standard Costing establishes in detail the standard cost of each component of a product, so that a total cost can be calculated for that product.
- 2Advantages of Standard Costing- To help with decision making, e.g. as a basis for pricing decisions.
- To assist in planning, e.g. plan amount of materials needed.
- For monitoring and controlling costs. - 3What is an 'Ideal Standard'?An ideal standard makes no allowances for inefficiency or wastage of labour or materials, and therefore assumes perfect conditions.
- 4What is 'Attainable Standard'?Attainable Standard allows for a small amount of normal wastage and inefficiency, but it is set at a level that is considered to be a challenging target based on current operating conditions.
- 5What is 'Basic Standard'?Basic Standard is a historical (out-of-date) standard that allows comparisons to be carried out over long periods of time.
- 6What is 'Strategic Management'?Strategic Management is concerned with long-term planning and decision making. This usually fits in with 'Ideal' and 'Attainable' Standards.
- 7What is 'Operational Management'?Operational Management centers around the day-to-day activities taking place within an organisation. This usually fits in with 'Attainable'and 'Basic' Standards.
- 8What is the formula for Total direct material variances?Standard Cost of materials for the actual production level - Actual Cost of materials for the actual productions level
- 9What is the formula for direct material price variances?Standard Cost of the actual quantity of materials used - Actual Cost of the actual quantity of materials used
- 10What is the formula for direct material usage variances?Standard Quantity of materials for actual production at a standard price - Actual Quantity of materials used at a standard price
- 11What is the formula for Total direct labour variances?Standard Cost of labour for the actual production level - Actual Cost of labour for the actual production level
- 12What is the formula for direct labour rate variances?Standard Cost of the actual labour hours used - Actual Cost of the actual labour hours used
- 13What is the formula for direct labour efficiency variances?Standard labour hours of actual production at standard cost - Actual labour hours of actual production at standard cost
- 14What is the idle time variance?Actual productive labour hours used at standard cost - Total actual labour hours used at standard cost.
- 15What does PAUS stand for?P - Price Variances use
A- Actual Quantities.
U - Usage Variances use
S - Standard Costing. - 16What are the Causes of Variances?- Poor Standards
- Different Suppliers
- Exchange Rates
- Poor Training
- Higher grade staff
- Inflation
- Better production machinery - 17What is tolerance level?The range around the standard within which performance is considered to be acceptable and action does not need to be taken
- 18What is exception reporting?The practice of reporting only the information which is significant. In terms of variances, it could involve only reporting variances outside of the agreed tolerance level.
- 19What is a Cost Reconciliation Statement/Operating Statement?A statement reconciling the standard cost of the actual production with the actual cost by using relevant variances.
Information
- Description
- Accounting Flashcards on Chapter 2 Revision - Decision and Control, created by Josh McMahon on 26/04/2022.
- Created by
- Josh McMahon
- Views
- 0
- Rating
More on Standard Costing and Variance Analysis