Estimate cost
- Involded all the efrorts needed to complete the projet
- Costo of quality effort
- Costo of Risk effort
- Costo of project manager time
- Cost of Project manager activities
- Cost directly associated with the Project: labor, material, training, et.
- Expenses of physical office space
- profit
- Overhead cost: management salaries, general offices
- Types
- Fixed
- No change_ set up, rent etc.
- Variable
- Depende of amount of work or amount of production
- Direct
- Attributable to the work of project
- indirect
- overhead ítems or costs incurred for the benefit of more that one project
- Fixed
- Cost Management Plan
- Scope base line
- Project Schedule
- Human Resource Management Plan
- Risk Register
- OPAs
- Policies and historical records related to stimating: templates,process, procedures, lessons learned, and historical information
- EEFs
- Company culture or Systems that the Project will be have to deal or can use
- Project Management Cost
- Buttom up
- PMBOK
- Knowledge Area: Cost Management
- Process Group: Planning
- Process: Estimate Cost
- one point
- Analogous
- Parametric
- three point
- Using ...
- Project Management Software
- Resource cost rate
- Reserve Analysis
- Reserve
- For unknown risks
- Contingence
- for knows risks
- Reserve
- Cost of quality
- Group desition Making
- most likely to understand what`s involved in the efforts
- Accuracy to Estimates
- Ranges ***
- Rough Order of Mafnitude (ROM)
- On Project Initiating
- -25% to 75%
- Budget Estimate
- During project planing
- -10% to 25%
- Definitive Estimate
- +/-10% or -5 +10%
- Rough Order of Mafnitude (ROM)
- Plan Management Cost
- Cost estimates
- Delivery cost plan
- Involded all the efrorts needed to complete the projet
Determinate budget
- PMBOK
- Knowledge Area: Cost Management
- Process Group: Planning
- Process: Detrminate budget
- Cost Managment Plan
- Is total of cost needed to complete the project
- Cost Base line
- budget portion that the PM will have control over Include de funding requirements
- Scope base line
- Project Schedule
- Risk Register
- Cost Estimates
- Basis of estimates
- prerequisites ***
- perform Risk Management activities
- include reserves
- include managment reserve
- Additional funds to unforeseen risk
- rollup cost package cost = Cost aggregation
- 1. Totalize Cost Activity by Work Packagen= Work Package Estimate
- 2. Totalize Work Package Cost by Control Account = Cotrol Account Estimate
- 3. Totalize Control Accounts = Project Estimate
- 4. Add Contingency Reserves = Cost Base line
- 5. Add mangement reserves = Cost Budget
- 6. Comparate to Parametric Estimate, Espert Judgment, historica record, etc. to sanity check
- 7. Check constraint of project.
- PMBOK