Site Possession Meeting
Map content
Site Possession Meeting
Timing
- - Date of commencement of contract corresponding with the date of site possession, e.g. Clause 21.1 PAM 1998 form (With quantities edition)
- - The date of site possession stipulated [Clause 38(b) JKR 203A (REV 10/83)]
Purpose
- For employers to officially hand over possession of the site to the contractor.
- For the contractors in reciprocation to officially take over possession of the site from the employer for the purpose of the contract.
- To introduce team members.
- Explanation of contractor requirements.
Participants
- Architects - Surveyors (Quantity Surveyors, Land Surveyors, Building Surveyors) - Engineers (C&S) - Contractors - Consultants - Clients - Local Authorities
Minutes Taker
- Superintending Officer (SO)
Documents
- From Employer to Contractor
- 1. Copy of project procedures manual.
- 2. Letters of delegation power.
- 3. Copy of formal contract documents (if ready)
- 4. Priced BQ and construction drawing sets (For contracts based on BQ)
- 5. Priced summary of prices, specifications and construction drawings (For contracts based on drawing and specs)
- From Contractor to Employer
- 1. Insurance policies or cover notes and receipts of premium paid.
- 2. Performance bond, advance payment bond, etc.
- 3. Copy of proposed work programme.
- 4. List of documents required from employer/contract administrator.
- 7. Project & site organisation chart, details and CV’s of personnel.
- 5. List of proposed sub-contractors & Details of address for service of notice.
- 6. Miscellaneous documents required under contract.
- From Employer to Contractor
Information
- Description
- Mind Map on Site Possession Meeting, created by Patrick Stitch on 18/09/2017.
- Created by
- Patrick Stitch
- Views
- 1
- History
-
- Created by Jo Yen Tan · Sep 18, 2017
- Copied by Patrick Stitch · Sep 18, 2017
- Rating