For larger works where most of the works
have already been designed.
Contractors design portion
available
Detailed contract provisions
payment
extentions of time
employer to provide either
drawings and bill or quantites
drawings and
sepecification/work
schedule
Building has already been designed and builder just builds the scheme
various forms of pricing mechanismn
at lease 3 versions of the contract
With bills of quantites
without bills of quantities
contractor is given a set of
drawings and a specification
with approximate quantities
not acurate
quantities will change but
the rates will remain
structure
reticals
the agreement
works required
drawings and specification
articles
scope of works
contract sum
contract admin, qs
form of dispute resolution
contract partoculars
attesation
deed
12 years liability
Underhand
6 years liability
There are specific provisions in JTC SBC which the
employer may defer the date for possession by up to 6
weeks, if the relevant entry is made in the contract
particulars.
Intermediate
Form
used when
proposed works are simple
involving basic trades and skills
project does not
involve complex
services
project does not involve
complex specialist works
when fairly detailed contract
provisions are required
Design & Build
used where employer has
defined his requirements
where the contractor
is to carry out the
design and
construction
employers requirement documents
contractor to provide priced
contractors proposals
provisions are as detailed as
standard form contract
Minor Works
up to half a million
used when works are simple in nature
employer provides
drawings and / or a
specification.
it has less detailed provisons
not very good for extentions of
time, payment provisons etc.
standard building contract is the
template upon which all the other forms
are based upon.
The clauses for the other forms are
either added or deducted from the
clauses in the SBC
Performance bond
A mean of insuring a client against the risk of the
contractor failing to fufil contractural obligations to
the client.
usually set at 10% of the contract value
can help a client to
overcome difficulties
that have been caused
by non performance of
the contractor.
can be used to help find a new
contractor to complete the works.
JTC have 3rd party rights but dont usually
get used as colleteral warranties brings in
3rd party rights
Payment Provisions
if you put an application
for payment in. the
employer does not put in
his own notice or pay less
notice than the contractor
is entitled to the amount
of money he has asked for.
Extension of time
Notice of delay by contractor to say:
materials (circumstances)
Cause or cause of delay
identify relevant events
expected date to complete
Contract Administrator to make
their own assessment
within 12 weeks after PC
irrespective of any notice given by the contractor
loss and expense applications
Contractor to make
application as soon
as it becomes
apparent that
regular progress has
been affected
identify relevant matters
details of actual loss and expense may follow
usually includes
heads of claim
prolongation costs
head office overhead cost
disruption
Relevant events
variations
advise weather
delay on the party of a nominated subcontractor
delay in giving the
contractor possession of the
site
A delay notice is required to
be served by the contractor
inline with the contract
provisions
construction claims fall
into two main categories
common law damages
where there is a breach of a contract
to put the injured party in the
same position as they would be in
if the contract has been
performed
3 main elements of
common law damages
causation
must be a direct link
between the breach of
contract & damage suffered
remoteness
can only claim losses which have
arised naturally from the breaches
duty to mitigate loss
claimant is not
permitted to allow their
loss to mount up
must show that there is a breach of a contract term.
Proof of claim
burden of proof (criminal)
standard of proof beyond reasonable doubt on balance of proabability (civil)
claims under the contract
Liquidated Damages
must be a realistic
estimate of damages
suffered
cannot be a penalty
tendering
Single stage selective tendering
Restricts the number
of tenders being
invited to submit bids.
Pre-selecting a limited number
of contractors to tender for the
work
Two stage selective tendering
negotiated tendering
The purpose is not to involve the
contractor with responsibility for design.
lt is to get the main contractor involved,
in an advisory capacity, before the
scheme has been fully designed.
forming a contract price at the end of
stage one, based on the tendered
preliminaires, overheads allowance and
provisional sums for all other elements
of the work.
used when
the building works are of very
complicated nature;
the magnitude of the work may be
unknown at the time for selection of
the contractor
an early completion date is paramount
the professional team wish to make use
of the cotractors expertise when
finalizing the design
negotiation
the employer has
worked with the
contractor before.
bills of quantities
define the whole of the contractor’s
obligation for quality and quantity
of work.
certificates
two catogries
certify the quantity of works done to date on
which payment is calculated
certify that an event has taken place (interim
certificates)consist of those that record an event
or non event
Cerificate of practicle completion
Certifcate of final completion
certifcate of non completion
All main standard forms of contracts
give power to the CA to order the
exclusion from the works of specified
persojns. This extends beyond the
contractors own emplyees to include
the employees of subcontractors.
materials on site
The value of unfixed materials and goods intended
for works, whether they are on or off site, may be
included in an interim certificate. If this is done, then
the ownership of these materials and goods will pas
to the employer as soon as the amount is duly paid.
liquadated damages
If possession is not then given on the date
specified, the employer will lose the right to
recover liquidated damages from the contractor
in the event of late completion.