Commencement, Delays and Suspension

  1. Commencement of Works

    • The Engineer shall give the Contractor not less than 7 days’ notice of the Commencement Date
    • the Commencement Date shall be within 42 days after the Contractor receives the Letter of Acceptance
    • The Contractor shall commence the execution of the Works as soon as is reasonably practicable after the Commencement Date
  2. Programme

    • The Contractor shall submit a detailed time programme to the Engineer within 28 days after receiving the notice of Commencement of Works
  3. Extension of Time for Completion

    • The Contractor shall be entitled to an extension of the Time for Completion by any of the following causes:
      • a Variation or other substantial change in the quantity of an item of work included in the Contract
      • exceptionally adverse climatic conditions
      • Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions
  4. Delay Damages

    • If the Contractor fails to comply with Time for Completion, then he shall pay delay damages to the Employer for this default
  5. Suspension of Work

    • The Engineer may at any time instruct the Contractor to suspend progress of part or all of the Works. During such suspension, the Contractor shall protect, store and secure such part or the Works against any deterioration, loss or damage.
  6. Consequences of Suspension

    • If the Contractor suffers delay and/or incurs Cost from complying with the Engineer’s instructions Suspension of Work and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled to Claims: (a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and (b) payment of any such Cost,
  7. Prolonged Suspension

    • If the suspension of Work has continued for more than 84 days, the Contractor may request the Engineer’s permission to proceed. If the Engineer does not give permission within 28 days after being requested to do so, the Contractor may, by giving notice to the Engineer, treat the suspension as an omission of the affected part of the Works. If the suspension affects the whole of the Works, the Contractor may give notice of termination .

Information

Description
Mind Map on Commencement, Delays and Suspension, created by Mohamed Omar on 24/04/2019.
Created by
Mohamed Omar
Views
0
History
  • Created by Mohamed Omar · Apr 24, 2019
  • Copied by Mohamed Omar · Apr 24, 2019
Rating

More on Construction Variations, Delays and Claims

Feedback

What is it about?

What should we add next?