Chapter 10: Budget Planning
Map content
Chapter 10: Budget Planning
Budget Management
- Importance budget planning
- Cost is one of the three project constraints
- A budget is a plan or forecast
- Cost management also includes tracking and managing variances from the planned expenditures
- Estimating costs to compare and select
- Methods of estimating
- Managing the budget
- Budget timeline
- Budget variances
- Importance budget planning
Project Cost Management
- The processes involved in planning, estimating, budgeting, and controlling costs so that the budget can be completed within the approved budget
Tools & techniques in estimating cost
- Analogous estimate
- Parametric estimate
- Bottom-up estimating
- Resource cost rates
- Vendor bid analysis
- Reserve analysis
- Cost of quality
Cost Management
- PV: Planned Value, estimated value of the planned work
- EV: Earned Value, estimated value of work done
- AC: Actual Cost, what you paid
- BAC: Budget at Completion, the budget for the total job
- EAC: Estimate at Completion, what is the total job expected to cost?
- EAC: Estimate to Complete, forecasted costs to complete job
- ETC: Estimate to Complete, forecasted costs to complete job
- VAC: Variance at Completion, how much over/under budget do we expect to be?
Manage Cost:
- Estimate Costs
- Determine Budget
- Control Costs
Managing the Budget
- Cash flow
- Contingency reserves
- For unexpected expenses that arise during the project
- There are almost always some surprises, but can’t predict at the start what it will be
- Can be spent and still be within the original project budget
- Management Reserves
- Contingency reserves
- Cash flow
Budget Baseline & Project Cost Chart
- Project budget is usually shown graphically, illustrating the cumulative planned spending.
- Typical shape for the budget curve is s-shaped, with less spending at the beginning and end of the project.
- Add the periodic expenditures on a regular basis to create the Project Cost Chart.
Earned Value Formulas
- EV-AC : Negative = Over budget & Positive = Under budget
- EV-PV : Negative = Behind Schedule & Positive = Ahead of Schedule
- EV/AC : How much are we getting for every dollar we spend?
- EV/PV : Progress as % against plan
- EAC-AC: How much more do we have to spend?
Earned Value guide
- EV is always first
- Variance = EV minus something
- If the formula relates to cost use AC
- If the formula relates to schedule use PV
- Interpreting results: negative is bad and positive is good
- Interpreting results: greater than one is good, less than one is bad
Cost Variance: CV
- The difference between the earned value and the actual cost is the cost variance:
- CV=EV-AC
- If positive, you are achieving more than you predicted for the money
- If zero, you are right on the plan
- If negative, you are achieving less than you predicted for the money
Schedule Variance: SV
- Difference between planned and actual progress
- SV=EV-PV
- Positive value: project is ahead of schedule
- Zero: project is on-time
- Negative: project is behind schedule
Cost Performance Index: CPI
- Cost Performance Index: CPI
- CPI=EV/AC
- A value greater than one: under budget
- Equal to one: on budget
- Less than one: overspending the budget
Schedule Performance Index: SPI
- Compares progress on the scope to spending
- SPI = EV/PV
- SPI less than one indicates the project is behind schedule
- SPI of one is right on schedule
- SPI greater than one the project is ahead of schedule
Information
- Description
- Mind Map on Chapter 10: Budget Planning, created by Syuhada Asmaa on 25/06/2021.
- Created by
- Syuhada Asmaa · Jun 2021
- Updated
- Jun 25, 2021
- Views
- 12
- Rating