SAB8# 169 TCPI
Map content
SAB8# 169 TCPI
TCPI = (BAC - EV) / (EAC - AC)
- TCPI BAC INVALIDO
- safe bet that there will be a few more cost overruns
- TCPI = (100k-68k) / (107k-70k)
- 0.86
- Good, keep the performance
- 0.86
- Cambia en la parte de abajo BAC por EAC
- TCPI BAC INVALIDO
TCPI = (BAC - EV )/ (BAC - AC)
- TCPI BAC VALIDO
- Project going on budget
- To-Complete Performance Index
- How well your project must perform to stay on budget
- TCPI = (40k-17k) / (40k-15k)
- 0.92
- Greater than one is bad; less than 1 is good.
- Good, keep the performance
- 0.92
- TCPI BAC VALIDO
BAC = 40000 EAC = 30000 EV = 17000 AC=15000
BAC=100000 EAC=107000 EV=68000 AC=70000