SAB9#70_Control Costs

Description

Mind Map on SAB9#70_Control Costs, created by Salvador Rueda on 25/02/2016.
Salvador Rueda
Mind Map by Salvador Rueda, updated more than 1 year ago
Salvador Rueda
Created by Salvador Rueda over 8 years ago
19
0

Resource summary

SAB9#70_Control Costs

Annotations:

  • In the exam, assume that the project manager is measuring, measuring, measuring on the project 
  1. It is all about knowing how you are doing compared to your plan and making adjustments when necessary
    1. Project funding requirements
      1. Project Management Plan
        1. Work Performance Data
          1. Orginizational Process Assets
            1. Earned value management
              1. Project Management Software
                1. Reserve Analysis
                  1. To-complete performance index (TCPI)
                    1. Performance Reviews
                      1. Earned Value Management
                        1. Integrates COST, TIME and the WORK DONE
                          1. PV - Planned Value
                            1. EV - Erned Value
                              1. AC - Actual Cost (total cost)
                                1. BAC - Budget at Completion
                                  1. EAC - Estimate at Completion
                                    1. ETC - Estimate to Complete
                                      1. VAC - Variance at Completion
                                        1. Formulas
                                          1. CV -Cost Variance EV - AC
                                            1. SV - Schedule Variance EV - PV
                                              1. CPI - Cost Performance Index EV/AC

                                                Annotations:

                                                • The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
                                                1. SPI - Schedule Performance Index EV/PV
                                                  1. EAC Estimate at Completion
                                                    1. AC + Bottom-up ETC
                                                      1. BAC/CPI
                                                        1. AC+(BAC-EV)
                                                          1. AC+(bac-EV)/CPI(c)XSPI(c))
                                                          2. TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
                                                            1. ETC - Estimate to Complete EAC-AC
                                                              1. VAC - Variance al Complietion BAC-EAC
                                                          3. Forecasting
                                                            1. Work Performance Information
                                                              1. CV - Cost Variance
                                                                1. SV - Schedule Variance
                                                                  1. CPI - Cost Performance Index
                                                                    1. SPI - Schedule Performance Index
                                                                      1. TCPI - To-Complete Performance Index
                                                                        1. EAC - Estimate to Complete
                                                                          1. VAC - Variance al Complietion
                                                                          2. Cost Forecast
                                                                            1. Change request
                                                                              1. Update Management Plan
                                                                                1. Update Project Documents
                                                                                  1. Update OPA´s
                                                                                    1. Progess Reporting
                                                                                      Show full summary Hide full summary

                                                                                      Similar

                                                                                      HSC Economics
                                                                                      lydia le
                                                                                      GCSE Maths Notes: Averages
                                                                                      Andrea Leyden
                                                                                      Chemistry Edexcel C2 topic 1+topic 2 notes
                                                                                      isabellaoliver
                                                                                      Othello content knowledge quiz
                                                                                      rubyduggan
                                                                                      B2, C2, P2
                                                                                      George Moores
                                                                                      AQA Biology B2 Questions
                                                                                      Bella Statham
                                                                                      Unit 1 flashcards
                                                                                      C R
                                                                                      GCSE AQA Physics Unit 2 Flashcards
                                                                                      Gabi Germain
                                                                                      Teaching Using GoConqr's Tools
                                                                                      Micheal Heffernan
                                                                                      English spelling rules
                                                                                      Sarah Holmes
                                                                                      2PR101 1.test - 3. část
                                                                                      Nikola Truong