Sub-Contracts
Reasons for their use
- SMM in 1922 contained 16 different trades
- 1988 edition contains over 300
- Affords flexibility for the main contractors
- Main Contractor still wholly liable to Employer
- No privity of contract between Employer and SC
- Note that some Employers may influence or insist on a SC
- SMM in 1922 contained 16 different trades
Liability of SC to Emploers
- Collateral warranty
- Shanklin Pier v. Detel Products
- No claim in pure economic loss
- this is no longer very clear
- Junior Books v. Veitchi
- sufficiently close relationship
- The same could occur in negligent misstatement if the relationship were sufficiently proximate
- Hedley Byrne v Heller
- Junior Books v. Veitchi
- this is no longer very clear
- The main contractor can discharge his liability if he is careful in the selection of the SC
- D&F Estates v. Church commissioners
- Collateral warranty
Relationship
- Nominated selected by the Employer
- Domestic selected by the Contractor
- Named SC - species of the JCT form
- Avoids the disadvantages associated with nomination
- Named SC - species of the JCT form
Incorporation of contract terms
- Not uncommon for their to be no Contract
- Modern Building v. Limmer & Trinidad
- Held that the expression on the acceptance letter meant the 'green book'
- Although this should be contrasted where the Arbitration clause was deemed not to be included
- T.W. Thomas v Portsea Steamship
- Modern Building v. Limmer & Trinidad
- Not uncommon for their to be no Contract
Incorporation of main terms
- Can be ambiguous if referring to the main contract
- Geary, Walker v. Lawrence & Son
- Delay
- Martin Grant v. Sir Lindsay Parkinson
- Argued that work of the SC should be free to arrange in an efficient and profitable manner
- Martin Grant v. Sir Lindsay Parkinson
- Can be ambiguous if referring to the main contract
Dispute resolution
- A probable inclusion although a dispute with the SC could be passed up to the Employer. These would both be heard separately
- Tripartite arbitration
- A probable inclusion although a dispute with the SC could be passed up to the Employer. These would both be heard separately
Name borrowing
- Northern Regional Health Authority v. Derek Crouch Construction
- Concerned with whether the court could open up an appeal from an Adjudicator. Held not to.
- Although Beaufort Development v. Gilbert Ash - they can
- Concerned with whether the court could open up an appeal from an Adjudicator. Held not to.
- Northern Regional Health Authority v. Derek Crouch Construction
Witholding payment, set off and abatement
- Only if very cleaar
- Beaufort Development v. Gilbert Ash
- HGCRA
- Section 111 notice is required
- SL Timber systems v. Carillion Construction
- The wide rule of the notice is held to promote cashflow
- Pay no argue later - this has risks associated with liquidation
- Section 111 notice is required
- HGCRA
- Beaufort Development v. Gilbert Ash
- Pay when paid
- Section 111 prohibits this
- Midland expressway v. Carillion Construction - CAMBBA
- Section 111 prohibits this
- Employer has control mechanisms in the JCT to prohibit the amount of works sub-let.
- Only if very cleaar
Assignment
- Can freely assign rights unless prohibited
- Linden Gardens v. Lanesta Sludge
- Can freely assign rights unless prohibited
Employer liability to SC
- No implied right of payment for nominated SC
- Has to be incorporated
- JA Milestone v. Yates Castle Brewery
- Has to be incorporated
- No right to direct SC
- No implied right of payment for nominated SC
Information