Settlement
All ground settles in the first 5 years.
Some structures settle 20-30+ years later.
Amount of settlement depends on type of soil & imposed loads.
Types of Settlement
Uniform Settlement
Differential Settlement
Soil Types & Problems
Clay: heave & shrink
Sandy Soils: frost heave, washed away by water
Organic Soils: compressible & hold water
Fills: unknown problems can occur...
Problems with Vegetation
Extract water form soils to cause shrinkage & subsidence.
Felled trees can cause heave.
Particular problem in southeast where soil is mostly clay.
Buildings with foundations in the 'root zone' can be affected.
Minimum distances between trees & buildings are required.
Preventing Settlement
Desk Study (Always)
Walkover Survey (Always)
Soil Analysis (If Concerns Found From Above)
"Pay for a Site Investigation if You Have One or Not"
Types of Foundations
Strip
Piles
Raft
Reasons for Inadequate Foundations
No/missing foundations
Design faults
Incorrect spec. of concrete reinforcement
Alteration of building loads causing localised weaknesses
Reasons for Foundation Problems
Settlement - occurs when soil consolidates under load & removes excess water (if uniform, cracking should not occur)
Subsidence
Heave
Mining & vibrations through earthquakes.
Reasons for Failure of Pile Foundations
Lack of adequate boring.
Inaccurate soil classification.
Insufficient penetration.
Soft strata under tip of pile.
Inadequate data.
Misinterpretation of loads.
Damaged, buckled or broken piles.
Vibrations causing movement.
Flowing strata.
Tension failure of pile due to lack of reinforcement.
Eccentricity due to bowing.
Decay due to lower ground water level.
Insect and marine borer attack & corrosion.
Poor quality concrete or reactive aggregate.
Collapse of thin shell of the piles.
Overweight due to earth fill.
Methods of Investigating Foundation Movement
Trial Pits
Desk study
Boreholes
Soil & Root Sampling
Drain testing
Crack monitoring
Methods to Prevent Pile Foundation Failure
Early repair (encasement or replacement)
Removal of partial load
Underpinning
Other Reasons for Cracking
Sulphate attack
Wall tie failure
Thermal/moisture movement
Lateral pressure from poorly tied roofs
Defective arches and lintels
Crack Identification
The following suggests foundation movement:
Wide cracks running along wall.
Cracks extending down to ground level.
Tapered cracks.
Distorted window & door openings.
Tilting external walls.
Sloping floors.
Crack Classification (BRE Digest 251 - Table 1)
Category 1 - hairline cracks of less than 0.1mm - classified as negligible - No Action Required.
Category 2 - fine cracks with widths up to 1mm which can be treated easily with decoration - damage generally restricted to internal wall finishes & barely visible on external brickwork.
Category 3 - cracks with widths up to 5mm that are easily filled & not necessarily visible externally with some re-pointing possibly required.
Category 4 - cracks with widths between 5-15mm which required opening up & patching by a mason. Re-pointing required, bricks replaced, water-tightness impaired and possibly fracturing of service pipes.
Category 5 - extensive damage with crack widths of 15-25mm requiring breaking out and replacing of sections of walls. Doors & windows are distorted, floor sloping, loss of bearing in beams and services pipes disrupted.
Category 6 - structural damage caused by cracks with widths exceeding 25mm which requires a major repair job involving partial or complete rebuilding. Beams lose bearing, walls lean & require shoring, windows broken with distortion & danger of instability.
Remedial Measures for Cracking
Depends on severity of cracking:
Decoration
Repointing and alteration
Replacement of components
Removal of structure (partial or total) and rebuilding
New Page
Information
- Description
- Undergraduate MIS & MRR (Summary of MRR Revision Topics) Note on Sites & Foundations - Summary, created by d.moran-10 on 19/05/2014.
- Created by
- d.moran-10
- Views
- 33
- Rating