  1. 1describe relationship between the defects liability period and final certificatePrior to the completion of the defects liability period, the architect will undertake a 'final certificate inspection' and any unsatisfactory work can be listed to the contractor for rectification.
    Once the defects are completed, the architect will issue the 'final certificate' which formally completes the contract and all final monetary adjustments will be scheduled in this certificate including the returns of any cash retention.
  2. 2final certificatethe successful completion of the defects liability period, shows the amount of the final payment due to the contractor and certifies that the works have been completed in accordance with the contract
  3. 3practical completionrefers to the stage of a construction contract when the works become reasonably fit for use and occupation
  4. 4practical completion (7 things happen)1 - commissioning tests for plant and equipment are completed successfully
    2 - approvals for occupation have been obtained from authorities
    3 - defects liability period begins
    4 - 50% of the security held is released back to the contractor
    5 -
    6 -
    7 -
  5. 5floatthe measure of free time in a program between non-critical activities not affecting the finishing time for a project.
    float is the additional time available befor e a non-critical activity becomes a critical activity
  6. 6who has the benefit of the float?both parties benefit
    EOT should only be given to critical path items
    Owner has benefit of float in a CP item until it becomes zero
    Contractor has float in non-CP items which are subject to EOT that would be granted for delays to critical activities
  7. 7ex. of contractual floatprovisional delays like weather
  8. 8security of paymentsUnder legislation, an owner in receipt of a claim for payment from a contractor has a set time limit in which they must either pay the amount claimed, reject the claim entirely, or dispute the amount claimed and pay the portion of the claim which is not disputed. If the owner does not respond, the claim must be paid in full
  9. 9progress paymenta payment under a contract or client-architect agreement for work partly completed. a progress payment is made by the principal/client to the contractor on the presentation by the contractor of a progress certificate prepared by the architect
  10. 10set-offthe process whereby a contractor's progress claim is reduced by the contract administrator by an amount owed by the contractor to the owner
  11. 11who provides the securitythe contractor!
    it is an assurance that the contractor will meet its obligations under the contract
  12. 12types of securitycash retention or bank guarantee
  13. 13what is a cash retentionan amount retained progressively from each payment until a nominated limit is reached
  14. 14unconditional bank guaranteecash equivalent provided by a financial institution
    usually (2) are provided for a project, each valued at half the total security required
  15. 15how much security is suggested by ABIC-SW5% of contract price and remains 5% of original contract price if it is varied during construction
  16. 16what is a prime cost iteman allowance in the contract for the supply of necessary items not yet finally selected
    ex. door furniture
  17. 17what is a provisional suman allowance in the contract for the cost of foreseeable necessary work, including the supply of materials not fully described or detailed at the time that the contract commenced
    ex. service connections
  18. 18contingency suma sum of money included in a construction contract sum for expenditure if necessary on matters unforeseen at the time of calculating the contract sum
  19. 19what are liquidated damagesa pre-estimate of the 'loss' a client is likely to suffer if the practical completion is delayed beyond the contract date of PC.
  20. 20when are liquidated damages payableif the works have not reached PC, the architect must notify the contractor and owner that the owner is entitled to liquidated damages
  21. 21how are liquidated damages deductedthey are deducted from the next and subsequent progress certificates

Informações

Descrição
NEP Architecture FlashCards sobre NEP - Contract Admin, criado por kristin koslowski em 10-08-2018.
Visualizações
0
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?