Phase 1
2007
Involved building rock armour on eastern end of the sea front
Phase 2
2007
Protecting the main town
- shingle and sand beaches replenished and stabilised
-rock armour extended (Beacon rocks) and realigned
( north wall rockery)
- drainage systems improved ( prevent landslides
reduce water build up
£26 million
Phase 3
Meant to protect the west of Lyme Regis from lanslides
never carried out- couldn't justify the high cost
19.5 million pounds
390 m of sea wall and rock armour
protects roads going into the towm
2015