Mapa mental
Chapter 6: Developing a Project Plan
Conteúdo do mapa
Chapter 6: Developing a Project Plan
Free Slack vs. Total Slack
- Free Slack is the number of days that an activity can have before it starts delaying the next (successor) activity
- Total Slack is the number of days that activity can have before it starts delaying the whole project.
Importance of Managing the Critical Path
- helps you keep your project on track and on budget, providing visibility into your project
- Dependencies
- people
- tasks
Early vs. Late Slack
- Start Slack is (Late Start - Early Start)
- Finish Slack is (Late Finish - Early Finish)
Level of Detail
- Activities must be clearly defined, and should be measurable
- activity at the lowest level should be clearly identifiable and measurable
Informações
- Descrição
- Mapa Mental sobre Chapter 6: Developing a Project Plan, criado por John Sullivan em 19-11-2018.
- Criado por
- John Sullivan
- Visualizações
- 0
- Avaliação
Mais sobre Project Management Plan