Chapter 6: Developing a Project Plan

John Sullivan Inglês

Conteúdo do mapa

Chapter 6: Developing a Project Plan

  1. Free Slack vs. Total Slack

    • Free Slack is the number of days that an activity can have before it starts delaying the next (successor) activity
    • Total Slack is the number of days that activity can have before it starts delaying the whole project.
  2. Importance of Managing the Critical Path

    • helps you keep your project on track and on budget, providing visibility into your project
    • Dependencies
    • people
    • tasks
  3. Early vs. Late Slack

    • Start Slack is (Late Start - Early Start)
    • Finish Slack is (Late Finish - Early Finish)
  4. Level of Detail

    • Activities must be clearly defined, and should be measurable
    • activity at the lowest level should be clearly identifiable and measurable

Informações

Descrição
Mapa Mental sobre Chapter 6: Developing a Project Plan, criado por John Sullivan em 19-11-2018.
Criado por
John Sullivan
Visualizações
0
Avaliação

Mais sobre Project Management Plan

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?