Chapter 6: Developing a Project Plan

  1. Free Slack vs. Total Slack

    • Free Slack is the number of days that an activity can have before it starts delaying the next (successor) activity
    • Total Slack is the number of days that activity can have before it starts delaying the whole project.
  2. Importance of Managing the Critical Path

    • helps you keep your project on track and on budget, providing visibility into your project
    • Dependencies
    • people
    • tasks
  3. Early vs. Late Slack

    • Start Slack is (Late Start - Early Start)
    • Finish Slack is (Late Finish - Early Finish)
  4. Level of Detail

    • Activities must be clearly defined, and should be measurable
    • activity at the lowest level should be clearly identifiable and measurable

Information

Description
Mind Map on Chapter 6: Developing a Project Plan, created by John Sullivan on 19/11/2018.
Created by
John Sullivan
Views
0
Rating

More on Project Management Plan

Feedback

What is it about?

What do you think of the new look?

How do you like it?