SAB9#137_Documentos_Contingencia
Risk Register Updates
- Residual Risk
- Risk that remain after risk response planning
- After you have avoided ,exploited, mitigated ,enhanced, transferred , shared and actively accepted risks , there will still be some risk that remain
- Contingency Plan
- plans describing the specific actions that will be taken if the opportunity or threat occurs
- Fallback Plan
- specific action if contingency plan are not efffective
- Risk Owners
- Each Risk must be assigned to someone who may help develop the risk response and who will be assigned to carry out the risk response
- The Risk Owner can be a stakeholder other than a team member
- The Risk occurs , the risk owner takes the preapproved action determined in a project planning and inform to PM
- The Risk Owner can be a stakeholder other than a team member
- Each Risk must be assigned to someone who may help develop the risk response and who will be assigned to carry out the risk response
- Secondary Risk
- Any new Risk created by the implementation of selected risk response should also be analyzed as part of risk response planning
- a response to one risk will create the possibility of new risk that would otherwise not have occurred
- The discovery of secondary risk may require additional risk response planning
- a response to one risk will create the possibility of new risk that would otherwise not have occurred
- Any new Risk created by the implementation of selected risk response should also be analyzed as part of risk response planning
- Risk Triggers
- These are events that trigger the contingency response
- Early warning signs for each risk can help to know when take the action
- These are events that trigger the contingency response
- Contracts
- include terms and conditions required in a project
- PM must be involved before a contract is signed
- PM should have a complete risk analysis and include terms and conditions requiered to mitigate or allocate threats and to enhance opportunity
- PM must be involved before a contract is signed
- include terms and conditions required in a project
- Reserves (contingency)
- Having reserves for time and cost is a requiered part of a project management
- Should include in the Cost Management
- Contingency reserves
- Account for "known unknowns" that you identify in risk Management
- are calculated and become part of the cost baseline
- Management reserves
- Account for "known unknowns" these are items you did not or could not identify in the risk management
- are estimated and then these reserves are added to the cost baseline to get the project budget
- PM has control of the cost baseline and can approve use the contingency reserves , but management approval is needed to use management reserves
- Make sure you realize that reserves are not an additional cost to a project
- Having reserves for time and cost is a requiered part of a project management
- Residual Risk
Project Documents Update
- Other Documents a PM has created to help manage the project may also change
- How Risk Response planning might affect the roles and responsabilites on a project , your stakeholder management strategy , or your Quality metric ?
Project Management Plans Updates
- Efforts spent in risk management can result in updates to the ...
- Planning is interative or go Back iterations
- After careful consideration and evaluation , planning risk response may require changes to ....
- Critical for understanding the impact risk management has on a project , especially if you don't currently do risk management in your real work
Imagens e arquivos do mapa
Informações
- Descrição
- PMP Taller de Certificación PMI Mapa Mental sobre SAB9#137_Documentos_Contingencia, criado por Roman Velasquez em 02-02-2017.
- Criado por
- Roman Velasquez
- Visualizações
- 0
- Histórico
-
- Criado por Roman Velasquez · 10 mar 2016
- Copiado por Roman Velasquez · 2 fev 2017
- Avaliação