  1. Resource Optimization

    • find the ways to adjust the use of resoure
    • Resource Leveling
      • Produce a resource-limited schedule
        • lengthens the schedule
        • Increases cost
        • Limited by
          • Amount of resource
          • Resource availability
          • Others constraints
    • Resoure Smooting
      • Similar to Resource Leveling
      • Within the limits of the float
      • The activity is not delayed
  2. Develop the Schedule

    • Knowledge Area: Time Managament
    • Process Group: Planning
    • Process: Develop Schedule
    • Create the Schedule model
    • Is calendar -based
    • is Approved
    • is realistyc
    • Historical Records
    • Project scope stament
    • Defined activities
    • Network diagram
    • Activity duration estimates
    • Activity resource requirements
    • Resource calendar
    • Resource breakdown structure
    • Identify working and not working days
    • Risk that could impact de schedule
    • The process include:
      • Work with the stakeholders priorities
      • look for alternative ways to complete the work
      • look for the impact on others projects
      • Negotiate resource
      • apply leads and lags
      • Compress the schedule: crashing, fast track, reestimate
      • Adjust the component of project management plan
        • example: risk plan or WBS
      • scheduling tool
      • optimize resource
      • Approve final schedule
      • Formal management approval
    • Schedule Network Analysis
      • Critical Phat Method
        • Critical phat
          • Is the longest path through the Network Diagram
            • Is necesary determinate all paths to determinte the critical ptah
          • Is the shortes time it could take to complete the project
        • Allow focus the project management efforts
        • helps to determinate if and issue need inmediat attención
        • Allow the compress schedule
        • show the float
        • Near-Critical Path
          • Is close, in duration, to critical path
          • Increases the Risk
          • There can be more that one
          • Focus the time and effort monitoring and controlling activities on btoh the critical and near-critical paths
        • Float or(=) slack
          • Total float
            • Amount of time an activity can be delayed without delaying the project end date or intermediary millestone.
          • Free Float
            • Amount of time an activity can be delayed without delaying the early start date of the its successor
          • Project Float
            • Amount of time a project can be delayed without delaying the externally imposed project competation date.
          • Activities of Critical Path have 0 Slack
          • IS an asset of the project
          • Allow resource optimizing
          • Allow share resource
          • Float = Late Start - Aerly Start = Late Finish - Early Finish=Slack
        • Using CPM
          • Fordware pass
            • in convergence select the late aerly finish
            • pass the EF to the successor
            • pass from beginning to end project following the dependecies.
          • Backware pass
            • pass the ES to the predecessor
            • In convergence select the aerly Late Start
            • moving the end to benning of project following the dependencies.
          • Activities with float=0 are in the critical path
      • Schedule compression
        • Fast Tracking
          • aTaking a critical path that were originally planning in a series and doing them instead in parallel
          • Rework as a result
          • increase the risk
          • Requires more attention to comunication
        • Crashing
          • Adding or adjust resource
          • Increase the cost
          • Increase the risk
      • Modeling
        • What if scenaries
      • Resource Optimization
        • Resource leveling
          • Resource-Limited schedule
            • availability and others constraint
          • lengthens the schedule
          • Increase the cost
          • Is a function of software
        • Resource Smootihng
          • The resource is leveling only within the limits of floats of activities
      • Critical Chain Method
      • Monte Carlo Analysis
        • Computer Software
          • Base: Optimistic, pessimistic and most likely
          • Result
            • The probabllly of completing the project on any specific day
            • The probabllly of completing for a any specific cost
            • The probabllly of any activity actually being on the Critical Path
            • the overall project risk
    • Approved Schedule Base line

Imagens e arquivos do mapa

  • TC#62#63_Optimization_Resource_Analysis_Diagram_Red
  • TC#62#63_Optimization_Resource_Analysis_Diagram_Red
  • TC#62#63_Optimization_Resource_Analysis_Diagram_Red

Informações

Descrição
Mapa Mental sobre TC#62#63_Optimization_Resource_Analysis_Diagram_Red, criado por Paulino Valladar em 03-02-2016.
Visualizações
3
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?