1f Gantt Chart and CPA
Gantt Chart
- Chart showing tasks as blocks with the length of the block representing the duration of the task
- Dependencies (tasks with must take place before another can be started) are represented by arrows
Critical Path Analysis
- Critical Path: The tasks depending on each other that determine the shortest time the project can be completed.
- A delay in any task on the critical path creates a delay in the overall project time
- CPA diagrams have labelled arrows representing tasks with the numbers representing duration.
- Each task goes to and from a milestone, (multiple tasks can go to and from the same milestone)
- Note: When drawing CPA diagrams it is best to work from the final task and add dependencies.
- Critical Path: The tasks depending on each other that determine the shortest time the project can be completed.
Used to help plan and manage a project
Focus on timescales as well as dependencies of tasks
Informações
- Descrição
- A level, A2 IT (Chapter 1) Mapa Mental sobre 1f Gantt Chart and CPA, criado por Gladys Mba em 02-05-2017.
- Criado por
- Gladys Mba
- Visualizações
- 4
- Avaliação
Mais sobre Project Scheduling and Network Analysis