O GoConqr está de visual novo! Conte para nós o que você achou.

Quiz

Project Management Tools Quiz

Niamh Ryan 10 perguntas 5,0 (1 avaliação)

Fazer o quiz

Este quiz tem tipos de pergunta que abrem no player de sempre.

Perguntas do quiz (10)

  1. 1A critical activity has...
    1. ANegative slack time
    2. BZero slack time
    3. CPositive slack time
  2. 2Critical path: The path of activities which represent the [blank_start]longest[blank_end] total time required to complete the project. A delay in an activity on the critical path causes a delay in the [blank_start]entire project[blank_end].
    1. Alongest
    2. Bshortest
    3. Centire project
    4. Dpreceding activity
    5. Eparallel activities
  3. 3Finish to start lag: The minimum amount of time that must pass between the [blank_start]finish[blank_end] of one activity and the [blank_start]start[blank_end] of its successor(s)
    1. Afinish
    2. Bstart
    3. Cfinish
    4. Dstart
  4. 4The variance in the project completion time can be calculated by [blank_start]summing[blank_end] the variances in the completion times of the activities in the critical path
    1. Asubtracting
    2. Bsumming
    3. Cmultiplying
  5. 5The normal distribution assumption holds if the number of activities in the path is large enough for the [blank_start]central limit theorem[blank_end] to be applied.
    1. Acentral limit theorem
  6. 6The following times for completion an activity have been estimated.
    Optimistic time: 4 days
    Most likely time: 7 days
    Pessimistic time: 10 days.
    The variance in the expected time is [blank_start]1[blank_end] days.
    1. A1
  7. 7When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between [blank_start]8[blank_end] and [blank_start]80[blank_end] hours of work.
    1. A8
    2. B80
  8. 8When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as [blank_start]work packages[blank_end].
    1. Awork packages
  9. 9High level elements in the WBS should match, word for word, nouns used to describe outcomes in the [blank_start]scope statement[blank_end].
    1. Ascope statement
  10. 10The current activity has an Early Start of March 1st and a duration of 3 days.
    The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is [blank_start]3[blank_end] days.
    1. A3

Informações

Descrição
Quiz on project management
Idioma
English
Visualizações
112
Avaliação
5,0 de 5 · 1 avaliação
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?