  1. 1 Which of the following about projects, programs and portfolios is NOT correct?
    1. AInterrelating projects can be groups under a program for better coordination.
    2. BAll projects and programs under a portfolio must be related to each other.
    3. CPrograms and projects serving to same business goal can be grouped under a portfolio
    4. DUnrelated projects cannot be grouped under same program
  2. 2Project Management Office (PMO) in an organization may do all of the following in an organization except:
    1. ATest the functional requirements of products developed.
    2. BProvide guidance
    3. CManage interdependencies between projects
    4. DGather lessons learned document
  3. 3 Which of the following is NOT required to exist in a Project Manager?
    1. AKnowledge about project management
    2. BPerformance on applying project management methodologies
    3. CPersonal skills to manage communication
    4. DSubject matter expertise on the technology used in project
  4. 4Which of the following is NOT true about lessons learned documentation?
    1. AMust be collected and updated throughout the project
    2. BOnly best practices of the project should be mentioned
    3. CLessons learned documentation will be used in future in organization
    4. DOnce finished, lessons learned documentation is stored in organizational process assets library of the company.
  5. 5All of the following are processes of Stakeholder Management knowledge area EXCEPT:
    1. ADetermine Stakeholders
    2. BIdentify Stakeholders
    3. CManage Stakeholder Engagement
    4. DControl Stakeholder Engagement
  6. 6All of the following about stakeholders are true EXCEPT:
    1. AStakeholders are affected by project
    2. BStakeholders might affect the project
    3. CStakeholders can be only individuals
    4. DStakeholders need to be managed
  7. 7During Monitor Stakeholder Engagement process, you noticed that a stakeholder is involved in the project at neutral level although he should have involved as supportive. What is the NEXT action you should do?
    1. ATake actions to increase his engagement level to supportive
    2. BReevaluate the Stakeholder Register document
    3. CIgnore the stakeholder and put maximum effort on other supportive stakeholders’ management
    4. DWait for him for another 1-2 months to see whether he will be supportive
  8. 8 You are working in a smart phone development project. You are in the Collect Requirements Process of your project. Which of the following is NOT a valid requirement?
    1. AMust have a good quality
    2. BMust have a 8 Mega Pixel camera
    3. CMust have a Li-on battery
    4. DMust be delivered in 6 months
  9. 9During your project, you are aiming to track the requirements over the life of project to ensure they are accomplished. You should use:
    1. ADefect List
    2. BRequirements Traceability Matrix
    3. CTest Report
    4. DProject Plan
  10. 10Using WBS brings several benefits in a project. Which of the following is NOT a benefit of using WBS?
    1. AHelps prevent work from slipping through cracks
    2. BPrevents procurement of certain items
    3. CHelps prevent changes
    4. DProvides a basis for estimating cost and time

Informações

Descrição
Quiz sobre project management, criado por KAYVAN BAHRAMI em 23-02-2019.
Idioma
English
Visualizações
134
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?