Quiz
Managing - Chapter 9
Crie uma conta grátis para terminar este quiz
Salve seu progresso e veja sua nota final.
Já tem uma conta? Inicie sessão
Perguntas do quiz (44)
11. In CPM, __________ are specified.
- Aa) exact levels of uncertainty associated with activities
- Bb) an expected time, a crash time, and the standard deviation time
- Cc) three costs
- Dd) two activity times and two costs
22. The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.
- Aa) probabilistic
- Bb) crashed
- Cc) normal
- Dd) dynamic
33. If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.
- Aa) not be necessary to crash any activities in projects
- Bb) be necessary to crash the last few activities of most projects
- Cc) be completed on time and within budget
- Dd) be completed as per schedule
44. The formula for computing the cost/time slope for each activity that can be crashed is __________.
- Aa) (crash cost + normal cost) / (crash time + normal time)
- Bb) (crash cost - normal cost) / (crash time - normal time)
- Cc) (normal cost + crash cost) / (normal time + crash time)
- Dd) (normal cost - crash cost) / (normal time - crash time)
55. Economically speaking, crashing a project creates a technology change in the __________ for an activity.
- Aa) deliverable demand function
- Bb) production function
- Cc) audit function
- Dd) deliverable supply function
66. The __________ technique overlaps the design and builds phases of a project to expedite its completion.
- Aa) crashing
- Bb) fast-tracking
- Cc) leading
- Dd) blitzing
77. The points between the extreme points of the relationship between time use and resource use represent __________.
- Aa) time constrained projects
- Bb) resource constrained projects
- Cc) alternative trade-offs between time and resources
- Dd) a non-feasible solution space of trade-off alternatives related to time and resource use
88. The two fundamental approaches to constrained allocation problems are __________.
- Aa) heuristic approaches and rules of thumb
- Bb) linear programming approaches and optimization models
- Cc) heuristic approaches and optimization models
- Dd) goal programming and trial and error
99. The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.
- Aa) goal programming
- Bb) heuristic
- Cc) optimization modeling
- Dd) linear programming
1010. Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.
- Aa) GERT schedule
- Bb) Gantt chart
- Cc) PERT/CPM schedule
- Dd) Master schedule
1111. If a contradiction or conflict between constraints is detected, __________ should always take precedence.
- Aa) technological necessities
- Bb) time constraints
- Cc) resource constraints
- Dd) managerial preferences
1212. The __________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.
- Aa) as soon as possible
- Bb) as late as possible
- Cc) minimum slack first
- Dd) shortest task first
1313. The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.
- Aa) minimum slack first
- Bb) shortest task first
- Cc) most successors
- Dd) as late as possible
1414. Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the “as late as possible” heuristic?
- Aa) Each activity will make use of all the slack available to it.
- Bb) The network will not have any critical activities.
- Cc) It would never be possible to override the “as late as possible” heuristic with a “must start no later than” date constraint.
- Dd) Many of the activities will be scheduled prior to the start date of the project.
1515. The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are __________.
- Aa) mathematical programming and linear programming
- Bb) mathematical programming and enumeration
- Cc) statistical analysis and simulation
- Dd) quantified heuristics and gaming
1616. The principal reason why a project manager is surprised by resource constraints on a project is the failure to include __________ in risk identification activities.
- Aa) resource availability
- Bb) resource cost
- Cc) resource mobility
- Dd) resource skill
1717. The tasks that logically precede a particular task in time are referred to as __________.
- Aa) successors
- Bb) followers
- Cc) predecessors
- Dd) priorities
1818. One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as __________.
- Aa) Goldratt’s Law
- Bb) Murphy’s Law
- Cc) the delay game
- Dd) the student syndrome
1919. When crashing a project, our first task is to develop __________.
- Aa) a table or graph of the cost of a project as a function of the project’s possible completion dates
- Bb) a schedule that shows the risks associated with each activity in the project
- Cc) a list that shows the activities and the events of a project without referring to the costs
- Dd) a table showing the noncritical activities and the cost associated with each of those activities
2020. Using the __________ heuristic method, the project team should be able to complete the maximum number of tasks during a given period of time.
- Aa) as soon as possible
- Bb) as late as possible
- Cc) shortest task first
- Dd) minimum slack first
2121. Studies have shown that the __________ scheduling heuristic method usually results in the minimum amount of project schedule slippage, best utilization of facilities, and minimum total system occupancy time.
- Aa) as soon as possible
- Bb) as late as possible
- Cc) shortest task first
- Dd) minimum slack first
2222. Thoughtless optimism, the “student syndrome,” and multitasking to reduce idle time can each contribute to __________.
- Aa) slack
- Bb) pessimistic bias
- Cc) optimistic bias
- Dd) feeder buffer
2323. In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity’s path but not its actual __________.
- Aa) duration
- Bb) slack
- Cc) float
- Dd) buffer
2424. One cannot save __________, rather one can only spend more or less of it.
- Aa) time
- Bb) money
- Cc) scope
- Dd) risk
2525. The use of __________ activity time estimates may reduce the chance that crashing the project will be needed.
- Aa) one probabilistic
- Bb) two probabilistic
- Cc) three probabilistic
- Dd) four probabilistic
2626. When we change technology, we may also be changing the level of __________ in carrying out the activity.
- Aa) risk
- Bb) money
- Cc) time
- Dd) all of the above
2727. The two principles to follow when crashing a project focuses on the __________.
- Aa) critical path and selects the least expensive alternative
- Bb) critical path and selects the most expensive alternative
- Cc) shortest path and selects the least expensive alternative
- Dd) critical path and selects the most expensive alternative
2828. A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources.
- Aa) scope constrained
- Bb) time constrained
- Cc) resource constrained
- Dd) system constrained
2929. __________ describes the amounts of individual resources an existing schedule requires during specific time periods.
- Aa) Resource loading
- Bb) Resource leveling
- Cc) Scope loading
- Dd) Resource succeeding
3030. __________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
- Aa) Resource loading
- Bb) Resource leveling
- Cc) Scope loading
- Dd) Resource succeeding
3131. __________ refers to the amount of time past a project’s due or delivery date.
- Aa) Schedule slippage
- Bb) Scope slippage
- Cc) Quality slippage
- Dd) Time constraint
3232. Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and __________.
- Aa) resource utilization
- Bb) time utilization
- Cc) management delay
- Dd) schedule utilization
3333. With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.
- Aa) in-process inventory
- Bb) schedule slippage
- Cc) resource utilization
- Dd) management delay
3434. Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.
- Aa) 9
- Bb) 12
- Cc) 18
- Dd) 24
3535. If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
- Aa) D = 6w
- Bb) W = 6d
- Cc) D = 8d
- Dd) W = 6d
3636. Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity (where D is held constant when resources are changed), correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are __________.
- Aa) D = 25w
- Bb) W = 25d
- Cc) D = 80w
- Dd) W = 8d
3737. Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.
- Aa) 80
- Bb) 70
- Cc) 60
- Dd) 75
3838. Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam’s efficiency rate is 90%. If Sam is only 70% available, Sam will require __________ hours to complete task R.
- Aa) 63
- Bb) 40
- Cc) 53.2
- Dd) 50.8
3939. __________ times result from an attempt to expedite the activity by the application of additional resources.
- Aa) Leveling
- Bb) Crash
- Cc) Post
- Dd) Constraint
4040. __________ are tasks that logically follow a particular task in time.
- Aa) Successor
- Bb) Strays
- Cc) Predecessors
- Dd) Critical
4141. Using Goldratt’s meaning of the word “dependent,” the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the ______________.
- Aa) priority chain
- Bb) critical chain
- Cc) dependency path
- Dd) heuristic path
4242. Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.
- Aa) necessary
- Bb) early
- Cc) late
- Dd) time-neutral
4343. When doing multiproject scheduling, each individual project is represented by a network of tasks. We can form a single network of these projects by connecting them with dummy activities and/or ___________.
- Aa) pseudo activities
- Bb) small tasks
- Cc) pseudonyms
- Dd) subnetworks
4444. Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?
- Aa) student’s syndrome
- Bb) arbitrary
- Cc) most successors
- Dd) most resources
Informações
- Descrição
- Managing Managing Quiz sobre Managing - Chapter 9, criado por Emma Ghini em 11-01-2021.
- Autor
- Emma Ghini
- Idioma
- English
- Visualizações
- 2
- Etiquetas
- Avaliação
- Ainda sem avaliações Avalie este quiz