  1. 1Network DiagramsNetwork Diagrams
  2. 2AOA Vs. AON Activities on arc vr. Activities on nodeAOA Vs. AON Activities on arc vr. Activities on node
  3. 3Node LabelsNode Labels
  4. 4Duration Estimation Methods• Past experience
    • Expert opinion
    • Mathematical derivation – Beta distribution
    – Most likely (m)
    – Most pessimistic (b)
    – Most optimistic (a)
  5. 5Constructing the Critical Path• Forward pass – an additive move through the network from start to
    finish
    • Backward pass – a subtractive move through the network from finish to
    start
    • Critical path – the longest path from end to end which determines the
    shortest project length
  6. 6Rules for Forward passForward Pass Rules (ES & EF)
    – ES + Duration = EF
    – EF of predecessor = ES of successor
    – Largest preceding EF at a merge point becomes EF for successor
  7. 7Rules for Backward PassBackward Pass Rules (LS & LF)
    – LF – Duration = LS
    – LS of successor = LF of predecessor
    – Smallest succeeding LS at a burst point becomes LF for predecessor
  8. 8Reducing the Critical Path• Eliminate tasks on the CP
    • Convert serial paths to parallel when possible
    • Overlap sequential tasks
    • Shorten the duration on critical path tasks
    • Shorten
    – early tasks
    – longest tasks
    – easiest tasks
    – tasks that cost the least to speed up

Informações

Descrição
Projectmanagement
Criado por
Lukas Berger
Visualizações
14
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?