1Wheeled Coach insists all of the following tasks are key to successful MRP use except
- Astringent quality control.
- Bmaterials plan must meet both schedule requirements and facility capabilities.
- Cplan must be executed as designed.
- Dinventory investment must be minimized.
- Eexcellent record integrity must be maintained.
2Demand for a given item is said to be dependent if
- Athere is a clearly identifiable parent.
- Bthere is a deep bill of material.
- Cit originates from the external customer.
- Dthe finished products are mostly services (rather than goods).
- Ethe item has several children.
3The phrase "demand related to the demand for other products" describes
- Adependent demand.
- Ba dependent variable.
- Cindependent demand.
- Drecursive demand.
- Eregression analysis.
4Dependent demand and independent demand items differ in that
- AAll of the above are true.
- BNone of the above is true.
- Cthe need for dependent-demand items is calculated.
- Dfor any product, all components are dependent-demand items.
- Ethe need for independent-demand items is forecast.
5Which of the following is not a key benefit of MRP?
- Aquality increases
- Bfaster response to market changes
- Creduced inventory levels
- Dbetter response times to customer orders
- Eimproved utilization of facilities
6Effective use of MRP and other dependent demand models does not require which of the following?
- Acost of individual components
- Binventory availability
- Clead times
- Dbill of materials
- Emaster production schedule
7A master production schedule specifies
- Awhat product is to be made, and when.
- Bthe financial resources required for production.
- Cthe raw materials required to complete the product.
- Dwhat component is to be made, and when.
- Ethe labor hours required for production.
8The __________ is (are) the MRP input detailing which end items are to be produced, when they are needed, and in what quantities.
- Amaster production schedule
- Binventory records
- Cassembly time chart
- Dload report
- Ebill of material
9A master production schedule contains information about
- Aquantities and required delivery dates of final products.
- Bscheduled receipts for each final product.
- Cinventory on hand for each final product.
- Dquantities and required delivery dates of all subassemblies.
- Einventory on hand for each subassembly.
10The aggregate plan gets input or feedback from which of the following areas?
- AAll of the above.
- Bengineering
- Cfinance, marketing, and human resources
- Dprocurement, production, and general management
- Ethe master production schedule
11Which portion of the master production schedule is normally fixed, frozen, or firm?
- Aonly the near-term portion
- Bonly the middle of the schedule
- Conly the aggregate schedule
- Donly the far-term portion
- Ethe entire schedule
12In continuous (stock-to-forecast) operations, the master production schedule is usually expressed in terms of
- Aend items.
- Bcustomer orders.
- Ckits.
- Dwarehouse orders.
- Emodules.
13In job shop (make-to-order) operations, the master production schedule is usually expressed in
- Acustomer orders
- Bwarehouse orders.
- Cend items.
- Dmodules.
- Ekits.
14The table above is an example of a(n)
- Amaster production schedule.
- Binventory record.
- Caggregate plan.
- Dload report.
- Ecapacity plan.
15A document calls for the production of 50 small garden tractors in week 1; 50 small garden tractors and 100 riding mowers in week 2; 100 riding mowers and 200 garden utility carts in week 3; and 100 riding mowers in week 4.
- Amaster production schedule.
- Bnet requirements document.
- CWagner-Whitin finite capacity document.
- Daggregate plan.
- Eresource requirements profile.
16The __________ is the input to material requirements planning which lists the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product.
- Abill of material
- Bmaster production schedule
- Cinventory records
- Dnet requirements chart
- Eassembly time chart
17An engineering change notice is used to change a(n)
- ABOM.
- BNone of the above.
- CMRP.
- DERP.
- EMPS.
18Firms making many different final products use __________ to facilitate production scheduling.
- Amodular bills
- Bphantom bills
- Coverdue bills
- Dplanning bills
- ENone of the above.
19A bill of material must be updated with the corrected dimensions of a part. The document that details this change is a(n)
- Aengineering change notice.
- Bresource requirements profile.
- Cmodular bill.
- Dplanning bill.
- Elead time-offset product structure document.
20The bill of material contains information necessary to
- Aconvert (explode) net requirements at one level into gross requirements at the next level.
- Bconvert gross requirements into net requirements.
- Cplace an order to replenish the item.
- Dcalculate quantities on hand and on order.
- Econvert net requirements into higher level gross requirements.
21A grill assembly takes 20 washers. Instead of listing these washers separately they are grouped into a single kit for production. The bill of material for the washers is classified as
- ABoth "Pseudo" and Planning
- BLow-level.
- CModular.
- DPlanning.
- E"Pseudo."
22The minimum record accuracy required for successful MRP is approximately
- A99%.
- B90%.
- C97%.
- Dlower than 90%.
- E95%.
23If the demand for product A is 50 units, what will be the gross requirement for component E?
- A300
- B250
- C100
- D200
- E4
24If the demand for product A is 50 units, what will be the gross requirement for component E?
- A50
- B300
- C100
- D150
- E200
25Low level coding means that
- Aa component item is coded at the lowest level at which it appears in the BOM structure.
- Ba final item has only a few levels in the BOM structure.
- CNone of the above.
- Dthe top level of the BOM is below level zero and that BOMs are not organized around the finished product.
- Eit is the code for the lowest level in the BOM structure.
Information
- Description
- OM- Final Quiz on Om Ch 14- Final, created by Shelby Reitz on 22/04/2018.
- Author
- Shelby Reitz
- Language
- English
- Views
- 0
- Tags
- Rating
- No ratings yet Rate this quiz
More on Production Planning and Scheduling