1Which one is not a basic element of Project Management?
- ADefining the overall project
- BFormulating time estimates for each task
- CEstimating project costs
- DNone of the others
2A project organization consists of?
- AProject manager
- BAll of the others
- CProject team
- DProject management system
3Which project application best illustrates the need for multiple time estimates?
- AFinancial audit
- BCommercial building construction
- CRobotic vacuum cleaner development
- DRefinery maintenance
4Which one of the following statements regarding the Gantt chart is true?
- AEvolved from the PERT chart
- BShows a plot of budget versus time
- CDeveloped during World War II
- DShows the scheduling of individual project tasks over time
5Which graph shows the sequencing of tasks over time?
- ADecision tree
- BGantt chart
- CFlow chart
- DHistogram
6Typically, crash time is defined as the?
- ADifference between earliest and latest starting times
- BMinimum time a task can be completed
- CMaximum tine a task can be completed
- DAverage time a task can be completed
7Which analytical process is used to determine the optimal way to reduce overall project time?
- APERT
- BSlack Management
- CCrashing
- DPERT-Cost
8The distribution of a project task with the time estimates of 2, 6, 10 is?
- ASkewed right
- BSkewed left
- CUniformly distributed
- DNormally distributed
9In an AOA network diagram the nodes represent _____ and the arcs represent ______ ?
- ASlack, Tasks
- BCritical time, Slack
- CTasks, Events
- DEvents, Tasks
10The Critical path is?
- ASet of tasks with zero slack
- BBased on the most likely time a task will take to complete
- CSet of tasks with positive slack
- DSet of tasks with negative slack
11Typically, the crash cost function?
- AIncreases in a non-linear fashion as project time is reduced
- BIncreases in a linear fashion as project time is reduced
- CRemains constant as project time is reduced
- DDecreases in a non-linear fashion as project time is reduced
12Which one of the following is characteristic of a project task?
- AAll of the others
- BSome tasks can be performed simultaneously
- CEach task has a beginning and an end
- DEach task can be described using single or multiple time estimates
13An activity with a slack of zero is called a ________activity?
- AEarliest start
- BNone of the others
- C Critical
- DCompleted
14In a Project Management cost analysis the region of feasibility is defined by?
- ALatest start time curve and slack management curve
- BSlack management curve
- CCash flow curve and earliest start time curve
- DEarliest start time curve and lastest start time curve
15The earliest start time for a task is equal to the?
- AAmount of activity slack
- BAverage completion time of its immediate predecessors
- CLatest completion time of its immediate predecessors
- DEarliest completion time of its immediate predecesors
16Which one of the following is depected in a project network diagram?
- ADuration
- BDependency
- CAll of the others
- DTask
17Which modelling technique is used for project network analysis?
- ADecision trees
- BPERT
- CCNP
- DFactor analysis
18PERT and CPM analysis are used for assessing the?
- AShortest time in which a project can be completed
- BCritical project tasks
- CResources needed to complete a project
- DAll of the others
19In crashing which tasks are generally selected first?
- AHighest cost
- BAverage cost
- CNon-critical
- DLowest cost
20In a project with multiple time estimates the probability of completing the project within the expected time is?
- ABetween 25% to 50%
- BMore than 75%
- CLess than 25%
- D50%
21Which project management system was developed by Dupont in 1957?
- AGantt chart
- BDecision tree
- CPERT
- DCPM
22Which one of the following statements best describes the critical path?
- AThe sequence of tasks that takes the longest time to complete
- BThe sequence of tasks that takes the shortest time to complete
- CThe set of tasks that has the lowest total costs
- DThe set of tasks that have more than one predecessor
23Which DSS is used for determining the optimal minimum cost crashing schedule?
- AForecasting
- BDecision trees
- CNPV
- DNone of the others
24Which project management model is used for time reduction applications?
- ACrashing
- BRegression
- CSlack
- DPERT-Cost
25Which one of the following multiple time distributions are skewed left?
- A3, 4, 8
- B2, 2, 2
- C5, 8, 9
- D4, 6, 8
26The output distribution for a multiple time estimate project is assumed to be?
- ABeta
- BNormal
- CConstant
- DUniform
27In an AOA network the nodes represent?
- AEvents
- B Activities
- CDown time
- DSlack
28In a beta distribution the most likely time is?
- ACloser to the most pessimistic time
- BCloser to the most optimistic time
- CEqual to the expected time
- DNone of the above
29Which variance should be used with a project with multiple critical paths?
- AThe smallest variance
- BThe largest variance
- CThe sum of all variances
- DThe average variance
30In crashing analysis the crashing cost function is assumed to be?
- ANon-linear
- BUniform
- CLinear
- DNormal
31Which one of the following multiple time estimates is normally distributed?
- A1,5,9
- B3,3,3
- C2,3,11
- DNone of the above
32Slack is defined as?
- ALF – LS
- BNormal time – crash time
- CLS – ES
- DLS – EF
33Which one of the following is not a standard input in developing an AP plan?
- AWait-and-see policy
- BCosts
- CCapacity statement
- DDemand forecast
34What AP policy is best when inventorying and backordering costs are large?
- ALevel
- BConstant workforce
- CChase
- DConstant output
35If unlimited outsourcing is permited then which outsourcing levels should be used as inputs in developing an aggregate plan?
- AEqual to demand
- BEqual to regular capacity
- CEqual to regular capacity plus overtime
- DEqual to overtime and undertime
36Which one of the following best describes a chase policy?
- AInventorying
- BConstant workforce
- CHiring/layoff
- DConstant output
37A proactive AP strategy tends focus on?
- ASubcontracting
- BReacting to deamnd
- CUsing a chase policy
- DModifying demand
38The use of outsourcing tends to minimize?
- AInventorying
- BCustomer service
- CTotal costs
- DAll of the others
39Typically, the goal of which one of the following AP objectives is to minimize?
- ACustomer service
- BNone of the others
- CInventory investment
- DFacility utilization
40Which one of the following is a standard AP objective?
- AImprove facility layout
- BMinimize customer service
- CImprove supplier quality
- DMaximize facility utilization
41Which one of the following is a reactive AP strategy?
- AComplementary products
- BPricing
- CAdvertising
- DOvertime
42Which one of the following AP pairs are consistent?
- ALabor shortages and implement chase strategy
- BLow holding costs and build inventory
- CHigh supplier costs and increase outsourcing
- DLabor union outsourcing restrictions and increase subcontracting
43Typially, the AP planning horizon is?
- A4 to 8 weeks
- B6 months or less
- C3 to 18 months
- D1 to 3 years
44Which AP action is best when there is a labor shortage?
- AHire and layoff as open as possible
- BReduce prices
- CIncrease the backlog
- DDecrease the backlog
45The time horizon associated with aggregate planning is generally considered to be?
- AShort range
- BNone of the others
- CLong range
- DMedium range
46Which one of the following AP costs is the most difficult to estimate?
- AOvertime
- BHiring
- CBackordering
- DInventory
47In developing an AP plan which costs typically can be carried over for several periods?
- AOvertime
- BRegular time
- CInventory
- DOutsourcing
48A responsive supply chain is best associated with?
- AFrequent new product/service introduction
- BStable demand
- CInfrequent product new produc/service introduction
- DLow profit margins
49What is the number of inventory turns associated with a firm with annual cost of sales of $100 million and an inventory value of $5 million?
- ANone of the others?
- B5
- C20
- D10
50Which DSS used in supplier selection involves performance characteristics and weights?
- ABreak-even analysis
- BLnear programming
- CFactor analysis
- DNPV
51Which one of the following is not a major supply chain decision issue?
- ADistribtion
- BLocation
- CProduct/service features
- DInventory
52A firm with a responsive supply chain would best be characterized by?
- AProcess focus
- BProduct focus
- CLow capacity cushions
- DLong delivery times
53What is the standardized data transmittal format used for communicating information between organizations?
- AMIS
- BEDI
- CIT
- DIST
54Which one of the following is not a step in the acquisition process?
- AForecast requirements
- BSelect suppliers
- CNone of the others
- DTrack orders
55An efficient supply chain is best associated with?
- AStable products/services
- BHigh inventories
- CFrequent product/service design changes
- DHigh product/service costs
56EDI stands for?
- AEducational decision institute
- BElectronic decision interchange
- CElectronic data interchange
- DElectronic data institute
57Which one of the following is not a standard supply chain performance metric?
- AOn time shipments
- BProduct demand
- CWeeks of supply
- DInventory turns
58Which one of the following can be used to reduce the bullwhip effect?
- AAll of the others
- BEngage in strategic partnering and buying
- CAdopte modern information technology systems
- DReduce both order and information lead times
59What is the value of inventory for a firm with an inventory turn of 10 and annual cost of sales of $500 million?
- ANone of the others
- B$10 million
- C$100 million
- D$50 million
60Forward placing is defined as placing inventory closer to the?
- AManufacture
- BEnd customer
- CEDI provider
- DSupplier
61Which one of the following is not a standard inventory component?
- ARaw materials
- BShipped goods
- CFinished goods
- DWork-in-progress
62Which one of the following represents the most significant source of disruption in an external supply chain?
- AForecasting errors
- BLate deliveries
- CEngineering change orders
- DLarge inventories
63Which supply chain decision issue involves the placement of finished goods inventory and the mode of shipment?
- ADistribution
- BProduction
- CLocation
- DInventory
64A major limitation of the standard AP model is?
- ALinear cost function
- BTight labor market
- CNonlinear cost function
- DLimited forecasting horizon
65Which one of the following is not consistent with increasing internal capacity in the short term?
- AAdd shifts
- BAdditional hiring
- COutsourcing
- DIncrease overtime
66A mixed AP policy can involve?
- AAll of the others
- BHiring/layoff
- CInventorying
- DOvertime
67Overtime is defined as?
- ABeing paid extra for additional work
- BNot being paid while on vacation
- CBeing paid whle not working
- DNot being paid extra for extra work
68Typically, the goal of which one of the following AP objectives is to maximize?
- ATotal costs
- BWorkforce vairations
- CInventory investment
- DCustomer service
69Which one of the following is a standard input in developing an AP plan?
- AOvertime costs
- BProduct life cycle
- CCompetitior pricing
- DAll of the others
70Which one of the following is consistent with increasing internal capacity in the short term?
- AOutsourcing
- BOvertime
- CUndertime
- DPlant expansion
71Which one of the following conditions best describes a level policy?
- AVary output rate
- BHire/layoff workers
- CBuild inventory
- DEmploy price discounts to increase demand
72Which one of the following is a reactive AP strategy?
- AOvertime
- BAdvertising
- CComplementary products
- DPricing
73Typically, the goal of which one of the following AP objectives is to maximize?
- AWorkforce vairations
- BCustomer service
- CInventory investment
- DTotal costs
74Which one of the following is a not standard AP objective
- AMaximize price effectiveness
- BMaximize system utilization
- CMinimize total cost
- DMinimize inventorying and backordering
75Which one of the following is not a reason a buyer enters into a relationship with a supplier?
- AQuality
- BCost
- CDelivery
- DNone of the others
76What is the correct SCM sequence?
- ASupplier relationships-design-inventory
- BStrategy-design-operations
- COperations-supplier relationships-ECM
- DDesign-inventory-operations
77The primary purpose of supply chain management is to?
- AMaximize system efficiency and customer service
- BSynchronize operations throughout the system
- CIncrease the use of planning software throughout the system
- DReduce the number of suppliers
78Which one of the following represents the most significant source of disruption in an internal supply chain?
- ALarge inventories
- BCompetitor actions
- CStandardized products
- DForecasting errors
79Which one of the following is not a standard LP constraint type?
- A<>
- B=
- C=>
- D<=
80Typically, which one of the following is the first step in developing a LP model?
- AConstruct the objective function
- BPerform sensitivity analysis
- CIdentify constraint types
- DIdentify variables
81Sensitivity analysis indicates the range of the RHS coefficients over which the shadow prices are?
- AUnbounded
- BInfeasible
- CSuboptimal
- DViable
82The optimal values of the variables in a minimization problem with all of the constraints less-than-or-equal-to are?
- AZero
- BCan not be determined
- CEqual to the RHS
- DTen
83Which resource management application involves determining the optimal price structure for the entire system?
- ARefinery operations
- BYield management
- CInvestment portfolio
- DManpower scheduling
84The value of the objective function is determined by?
- ASumming the product of the OF coefficents times the variable values
- BSumming the variable values
- CMultiplying the OF coefficents times the variable values
- DSumming the slack values
85A maximization problem must contain at least one?
- AGreater-than-or-equal-to type constraint
- BLess-than-or-equal-to type constraint
- CCost coefficient
- DDummy variable
86Which one of the following is a special LP solution type?
- AUnbounded
- BMultiple optimal solutions
- CAll of the others
- DInfeasible
Information
- Description
- Quiz on Final Exam Review, created by lseyer436 on 07/04/2015.
- Author
- lseyer436
- Language
- English
- Views
- 8
- Rating
- No ratings yet Rate this quiz
More on Project Scheduling and Network Analysis