PMP exam 4
Create a free account to finish this quiz
Save your progress and see your final score.
Already have an account? Sign in
Questions in this quiz (100)
1During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement. What should the project manager do next?
- AEscalate the situation again to the project sponsor.
- BReview this obstacle during the daily standup meeting.
- CRequest a new resource to execute the activities.
- DProvide feedback to the resource at the sprint review.
2A retail company identifies that it is losing sales because customers are not promptly informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.
Considering the objective to deploy customer value, which project life cycle approach should be chosen?
- AĐáp án

- BĐáp án ở trên
- AĐáp án
3A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
- AEnsure the stakeholder engagement plan is accurate and properly documented.
- BReview the lessons learned from the previous project
- CIdentify the risk of implementing the new solution and evaluate the impact on the project.
- DCreate a lessons learned document for the initiation phase
4After a performance review, a team member approaches the project manager and asks for feedback. The project manager mentions anecdotal information about this team member being a positive team player and generally getting their work done on time, even though they have been late with work once or twice. The team member expresses frustration at not having better information included in the annual performance review.
What should the project manager do to prevent this frustration going forward?- ARequest the human resource (HR) department to provide the key performance indicators (KPIs) that were defined for this project.
- BSet team performance goals and explain how the team receives the same performance scores.
- CReview the key performance indicators (KPIs) for this team member and remind the team member how they are determined.
- DProvide the team member with velocity tracking tools and explain how the team member can see and track performance.
5A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.
What strategy should the project manager implement to deal with this situation?- AAsk the team.to accelerate the iterations and avoid interruptions.
- BDiscuss the problem with the team and decide how to do the work together.
- CVerify team performance and ask for improvement during daily standup meetings.
- DRecommend that the project sponsor increases the budget to bring new resources.
6A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
- ABe clear with directions and assignments so people stay focused and engaged with their work.
- BPromote an environment where everybody knows what their contribution means to the project as a whole.
- CDesign a reward system to get people motivated by recognizing significant individual contributions from the last sprint
- DEncourage continuous rotation of roles among team members to keep people motivated throughout project delivery.
7There is a problem with a project because some features are not in compliance with regulations. Some stakeholders do not believe compliance is a priority, while others disagree. What should the project manager do?
- AReview the stakeholder engagement assessment matrix to determine next steps.
- BSet up some time with the stakeholders to explain the importance of compliance.
- CMeet with the sponsor to discuss how to handle the stakeholders' differing opinions.
- DSend out documentation to align stakeholder expectations and project objectives.
8A project team is working on a product that is planned for multiple iterations. They are delivering incremental value.
When should the value be demonstrated?- AAfter full development is completed
- BWhen a major feature is completed
- CAt the end of each and every iteration
- DWhen the sponsor approves the increment
9A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process, What should the project manager do?
- ADescope low-priority features that were not explicitly requested and add this feature as a high priority.
- BInform the senior manager that they will need a new project management plan for this feature
- CComplete the most current feature and release the resources for the new feature.
- DAnalyze the impact of this change and present the options to the senior manager.
10As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
11The project manager is reviewing a project's progress and notices that one of the risks has become an issue.
What should the project manager do to address the situation?- ASchedule a high-priority meeting with the project stakeholders to discuss the issue.
- BInitiate a change request to obtain additional funds from the management reserve.
- CMeet with the project team and customer to brainstorm about potential solutions.
- DCollaborate with the relevant stakeholders on implementing the risk response plan.
12A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.
What should the project manager do?- APlan a training session for the new team members not familiar with the system.
- BCommunicate the rules and criteria to the team members through email.
- CWork only with the team members familiar with the system
- DDocument which rules and criteria the new team members are not familiar wit
13A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.
How can the project manager promote empowerment and accountability among the team?- AAssign the tasks individually based on the role of the team member to ensure expertise on the subject.
- BEncourage and assign the team to perform demos of their products or software with the customers
- CGive the team autonomy to make their own decisions on how to perform the tasks.
- DEncourage the team to keep the product owner involved when choosing ways to resolve the given task
14After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.
What should the project manager do in order to gather the information needed from stakeholders?- AEmail, call, or meet with each stakeholder separately to obtain their input
- BConduct a meeting to build the project management plan with the stakeholders who are available
- CEscalate to the project sponsor that not all stakeholders are available for a meeting
- DMeet with the project management team to build the project management plan before consulting stakeholders
15A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.
What approach should the project manager use?- AAn agile approach as this would provide working functionality earlier
- BA predictive approach as this would please the senior stakeholders
- CA hybrid project as this will mitigate stakeholders' concerns.
- DA predictive approach as this will show benefits for all stakeholders
16A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
- AInform the design team to ensure compliance during the product design phase
- BInform the quality team that they need to ensure that the product is in compliance
- CEnsure that compliance is explicitly mentioned in the relevant requirements
- DMeet with the team and remind them of the compliance requirements
17A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?- ASet up a training session for all project team members
- BReach out to the functional managers for support
- CSpeak individually with each project team member about making the needed updates
- DSend an email asking all project team members to complete updates at the end of the day
18We architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?- ADiscuss the issue with the team to resolve the disagreement.
- BEnsure that there is consensus among the project stakeholders.
- CDiscuss the issue during the next sprint planning meeting.
- DSupport the outcome of the architects' agreement.
19The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members What two actions should project manager take? (Choose two)
- AAsk the team members to work it out themselves
- BDiscuss this situation with other project managers and ask for advice
- CReiterate ground rules at the next meeting and ensure that all team members are clear about these rules.
- DAddress the behavioral issue with each team member
- EDiscuss the behavior directly with their managers and request them to correct the behavior.
20A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?- AAvoid conflict and let the team self-organize on how they want to work on the project tasks.
- BAsk the project sponsor to provide team members with a project direction regarding outcomes.
- CSet short-term goals in order to create a winning culture internally and praise team members for achieving them.
- DEscalate the situation to the steering committee and request that more time be allotted to the project.
21A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule What should the project manager do?
- AAdvise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively
- BEscalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training
- CMake sure all stakeholders have access to the system and know where to find project artifacts
- DSend the project schedule via email to the stakeholders who need that information
22A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time What should the project manager do next?
- ARecord the issue then refocus the team's efforts on delivering the next set of deliverables
- BGive the team member a formal warning for the negative impact due to failure to delivering and not meet deadlines
- CHold a team meeting to discuss team member commitments and communications
- DMeet with the team member and work on a development plan for them to avoid missed deliverables in the future
23During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts What should the project manager do?
- APresent brainstorming topics a day before the session so the team can reflect and contribute more fully during the session
- BAdjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere
- CEnsure the team understands that their input needs to be fully articulated and explained to all team members during daily standups
- DRequire everyone to share personal details at the start of each team meeting to allow learn members to get to know one another
24The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision. What should the project manager do?
- ASupport the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future
- BCoach the team on the decision-making process, assuming a risk-averse strategy towards product releasing
- CAssume the responsibility for product releases making the final call on when something is ready for customer launch
- DEscalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision
25A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?- ASend out daily emails with the project status and task lists to all team members.
- BMeet daily with the project team and include a monthly report on the risks and issues.
- CDistribute a project newsletter that includes any project changes and required project information.
- DEncourage collaboration on a daily basis, facilitating different communication channels.
26A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?- AUse interpersonal skills to expedite the issue.
- BSend a gentle reminder to the technical service team.
- CUpdate the issue log with the status and priority.
- DIssue a formal warning to the technical service team.
27During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager notices that some of the team members are communicating with their managers directly to fulfill their requests.
This will lead the project to go beyond the agreed baselines. How should the project manager handle this situation?- ASet up a proper governance structure to ensure functional managers' requests are processed correctly.
- BModify the communications management plan to enable functional managers to add changes to the project.
- CFollow the project constraints and move forward with the agreed schedule baseline and the cost baseline.
- DAsk the functional managers to communicate with their peers and emphasize the impact of their requirements.
28Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?- ASend evidence to the new stakeholder that the project's status was sent according to the schedule
- BSuggest that the new stakeholder review the project status before the next board meeting
- CShare the communications management plan with the new stakeholder
- DDiscuss project requirements with the new stakeholder, and update the communications management plan.
29One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager do to monitor compliance?
- AAssess the risk register.
- BConduct project reviews.
- CPerform retrospectives.
- DComplete sprint reviews
30During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1.500 rpm (rate-per-minute) -> warns of max rate allowed
1.400pm (rate-per-minute) -> reduces the power and brakes the engine Which of the following statements is correct?- A0 1,600 rpm is a project risk,
1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue. - B1,600 rpm is a project issue,
1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk - C1600 rpm is a project issue; 1,d rpm is a project risk; and
1,400 rpm is an event that triggers a response strategy - D1.600 rpm is an event that triggers a response strategy. 1,500 rpm is a project issue and 1,4DD rpm is a project risk.
- A0 1,600 rpm is a project risk,
31A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.
What should the project manager do?- AReview the requirements of the report with the team member to redefine its purpose.
- BEscalate to the team member's functional manager that the report was not submitted as requested.
- CInstruct the team member to provide the report and document this in the performance review.
- DReassign the report to another team member to prepare and submit it as requested.
32A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource's refusal?- ASpeak directly with the resource.
- BCommunicate with their supervisor.
- COrganize a team meeting.
- DSpeak with their colleague.
33A team has been working together for several months and has successfully delivered work. A new team member has joined the team but is having difficulty contributing.
What should the project manager do to help the new team member integrate effectively?- AGive the new team member time to contribute until they ask for help and support.
- BAssign the new team member tasks so that the team member knows on what to focus.
- CApproach the team member to identify any issues and then plan a resolution accordingly
- DReview the project with the team member to ensure the project scope is understood
34An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them. How does the project lead ensure adherence to agile practices?
- AEscalate to management that the agile process is not going to work and ask them to speak to the agile coach,
- BHave two separate daily standups, one for the agile coach and technical writer and one for the agile development team.
- CHave a discussion with the team on the approach and come to a decision on when the daily standups should be.
- DInform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.
35A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?- ABuilt a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer
- BContracted with a third-party test lab to outsource all testing processes and required that they produce all test reports
- CLed a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop
- DBuilt a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server
36A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder's concerns?- AReview the benefits realization plan with the stakeholder.
- BProvide the stakeholder with regular updates on project progress.
- CAdd the stakeholder to the stakeholder engagement plan.
- DReview the prior analysis results with the stakeholder.
37In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the project sponsor that they know very little about the project.
What should the project manager do?- ADiscuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.
- BEnsure that the stakeholders who are complaining are present for the next project update meetings.
- CRecord the regular project update meeting and share it with all stakeholders after the meeting is completed.
- DChange the meeting time to the working time zones of the stakeholders who are complaining.
38us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

- AReview project cost because the project is over budget and ahead of schedule
- BReview project schedule and cost because the project is over budget and behind schedule
- CReview project schedule because the project is under budget and behind schedule
- DReview project scope because the project is under budget and ahead of schedule
39A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.
Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)- AOrganizational process assets (OPAs)
- BLesson learned registers from past projects
- CHistorical issue logs
- DProject scope statement
- EProject management plan
40At the end of a project, one of the suppliers is facing financial difficulties and is pushing the project manager to obtain financial, legal, and administrative approval in order to communicate formal project closure and ensure the transfer of liability. What should the project manager do next?
- ACompare the achieved results to the contract requirements.
- BMake the final payment as the project is completed.
- CTransfer the remaining variances and close the project.
- DEscalate to higher management to expedite the approval.
41A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer What should the project manager do?
- ARegister starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve
- BDevelop the quality management plan, as quality is as equally important as cost and schedule management.
- CGet confirmation from management that the team member has enough experience to build software without quality control
- DAsk the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project
42The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?- AConduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control
- BInvite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.
- CAdvise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.
- DDetermine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.
43A project manager has been assigned to an important project that will help set the future of the company.
Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.
What should the project manager do?- AReview the adaptive tools' impact and obtain agreement from the functional manager.
- BFollow the functional manager's recommendation to implement only predictive tools in the project.
- CMake the decision on which project approach to use that would best fit the project.
- DFollow the project management office's (PMOs) request to implement the adaptive tools in the project.
44A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?- AOrganize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation.
- BAsk the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned.
- CAsk the more experienced team member privately to take the task and inform the other team members that work has been reassigned.
- DOrganize a team meeting to inform team members about a change in direction and work with them to change the task allocation.
45An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?- AHire the resource in order to achieve the project objectives.
- BAsk the client for a meeting and explain that the task will not be performed
- CEvaluate the consequences and meet with the client to explain the possible scenarios.
- DTry to accomplish the task internally by leveling resources from other projects
46In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.
What should the project manager do?- AOrganize a meeting with the team and update the work breakdown structure (WBS).
- BRaise this issue, and review and update the progress report for the next monthly project meeting
- CStart the organization's change control process via a change request.
- DCommunicate with an officer in the environmental protection department to check if it is necessary.
47A project requires testing of the final product to be done at another department's testing facility, which is known for having low availability. This situation could potentially impact the project schedule.
What should the project manager do next?- AUpdate the risk register.
- BUpdate the issue log.
- CUpdate the lessons learned register.
- DUpdate the project schedule.
48A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.
What should the project manager do?- ASchedule a meeting with the previous project manager
- BSubmit a change request to the change control board (CCB)
- CSchedule training for project team members
- DConduct an earned value analysis (EVA)
49In the planning phase, a project manager receives identified risks from the sponsors and subject matter experts (SMEs) and wants to develop a risk response strategy for them. What should the project manager do first?
- APerform a risk reserve analysis.
- BAssign allocated budget to cover key risks.
- CAgree on the criteria to prioritize risks.
- DAssign a risk responsibility to each team member.
50A new development project is about to start, and the project manager knows that a high- profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?- AFocus on the implementation of a software as a service (SaaS) solution for the customer.
- BSpecify the scope and features to be deployed in the contract clearly.
- CWork very closely with the customer and third parties to meet their needs.
- DChange the marketing and product management definitions to meet stakeholder needs.
51A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?
- ACheck the change management plan
- BDocument the issue in the scope management plan.
- CConduct a team brainstorming session to resolve the issue
- DCheck the quality management plan
52A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
- ACompany's historical organizational project artifacts
- BCompany's project responsibility assignment matrix (RAM)
- CCompany's resource management plan
- DCompany's resource calendars
53A project manager is working on a highly complex project. During the execution of the project, the local government changed certain environmental regulations, which could potentially delay the project.
What immediate action should the project manager take?- AUpdate the issue log.
- BUpdate the project baseline.
- CUpdate the risk management plan.
- DUpdate the change request log.
54A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.
What should the project manager do to support the team?- ACreate a change request to extend the project's duration and costs.
- BProvide feedback to the team using project performance evaluations.
- CEscalate the impact on the schedule to the project sponsor.
- DInclude buffer time in the schedule to absorb future delays.
55After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.
Which phase of the Tuckman ladder of team formation is occurring?- AForming
- BMourning
- CStorming
- DNorming
56A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
- ADetermine a leadership style that is suitable for that location.
- BCheck if resources from headquarters can also be assigned to the project.
- CMentor the team members to perform project management.
- DAssign a local resource to manage communication with the team.
57A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
- AAsk the product owner, who is the key stakeholder, to choose among the different ideas.
- BPropose ideas to the group, ask everyone to vote, and then choose the most popular idea
- CSchedule a session to give everyone the chance to express their opinions about each idea, then vote and decide
- DOffer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting
58A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant.
The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?- AEvaluate the project risk and try to replace the project with another one within the organization.
- BInform the project sponsor about the risk and try to convince them to withdraw the project.
- CStudy and apply the lessons learned from the failed project so that this project does not follow the same pattern
- DContinue executing the project using the project manager's usual methods as all projects are unique.
59A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using What should the project manager have done to avoid this issue?
- AReferred to the communications management plan
- BValidated the issue log
- CValidated the project artifacts
- DPerformed expert judgment
60A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.
What should the project manager do first?- AReschedule the project taking this new information into account.
- BRefer to the project's resource management plan.
- CAsk the project sponsor for external resources.
- DCreate a change request to be validated by the project sponsor.
61A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.
Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?- AHow the quality was managed
- BHow the acceptance criteria were met
- CHow the scope was managed
- DHow the stakeholders were managed
62When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?- ACome to the meeting with suggested ground rules
- BAsk all team members to send new ideas prior to the meeting
- CExtend the meeting to allow everyone to speak
- DSet expectations for contributions ahead of the meeting
63One of the service providers on a complex project has been facing resource availability problems over the last six months. However, the service provider has assured the project manager that the deliverables will be on time.
How should the project manager address this situation?- AUpdate the issue log.
- BPerform a qualitative risk analysis.
- CPerform a root cause analysis.
- DImplement a risk response plan.
64A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.
What should the project manager do next?- AEnsure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.
- BConsider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.
- CDocument the kick-off meeting and close out the planning phase after the meeting is held.
- DLimit to one kick-off meeting in the project's first phase in order to control the budget.
65A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
How should the project manager respond- ANegotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced
- BDiscuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework
- CRecord the issue in the issue log and escalate the conflict to the project sponsor for assistance
- DExplain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews
66A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
67An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.
What should the project manager recommend?- ARequest marketing to launch an advertising campaign for the product that is currently in stock.
- BUpdate the project management plan, factoring in furloughs of the assembly team to reduce expenses.
- CExplore if the materials could be supplied locally and obtained on time.
- DMeet with the engineering team to manufacture the materials in-house.
68A high-performing team member's performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member's contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.
What should the project manager do?- APromote the higher performing team member to a higher position
- BRequest the high-performing team member to mentor the other team members
- CRemind the high-performing team member to focus on shared rewards rather than individual rewards
- DReward the high-performing team member privately to avoid team disruption
69A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
- AHigh-level product backlog
- BKey performance indicators (KPIs)
- CProduct vision
- DSchedule performance indexes (SPIs)
- EProduct roadmap
70A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.
What should the project manager do?- AUpdate the issue log and review the lessons learned register for options
- BImplement conflict resolution to accommodate the team's needs
- CImplement decision-making techniques to advance the stones
- DEmpower the team to self-organize and make their own decisions
71A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
- AReview the stakeholder register and ensure that communications are being followed in line with the communications management plan.
- BIsolate the project team from external factors such as senior management and stakeholders so that decisions can be made more quickly
- CReview the remaining scope and rebaseline the project's schedule to take into account delays in decision making
- DReview the adequacy of the project's governance and ensure that an appropriate structure is in place
72A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?- AEstablish the team ground rules and share them with the team for strict adherence.
- BCopy the ground rules established by another project and provide them to the teams.
- CExtract the organization's policies and processes, customize them, and give them to the teams to adhere to.
- DHelp the teams in establishing and adhering to their ground rules and revisit after regular intervals.
73The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?- AMonitor the interactions between the vendor and infrastructure manager going forward.
- BHost a meeting with the vendor and infrastructure manager to help resolve their disagreement.
- CEscalate the issue to the sponsor so appropriate action can be taken.
- DInstruct the vendor to correct the problem without additional arguments.
74A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
- AThe project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),
- BThe project team members need to ensure they have supplied sufficient knowledge transfer.
- CThe project sponsor must ensure all knowledge transfer is completed before project closure.
- DThe stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.
75A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation What should the project manager do?
- ACommunicate the ground rules, principles and reporting methods to the project stakeholders
- BPenalize the project team lead for not updating the project documentation properly.
- CReview this issue with the team lead for possible ways to resolve this situation
- DIssue guidance to the team member about reporting directly to the project manager
76During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project. What should the project manager do?
- AAsk the human resources director to appoint a senior team leader
- BInform the project sponsor about the possible delay
- CDirectly manage the project team to avoid project delays
- DProvide mentoring to the newly appointed team leader
77A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts What should the project manager do next?
- ARaise the issues in the retrospective and propose solutions
- BInform management that commitments will not be met.
- CInvolve management to help resolve the conflicts
- DCoach the team both as a whole and individually
78Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to ensure the project is delivered successfully?
- AAsk the vendor to communicate via the established channels.
- BInvite the vendor to a meeting to discuss the concerns.
- CEscalate the vendor's lack of responsiveness to the project sponsor.
- DProceed with other tasks while awaiting a response from the vendor.
79During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
- AConduct an expert judgment evaluation.
- BReview the quality management plan
- CUpdate the lessons learned register
- DReview the risk management plan
80A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.
What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?- AReceive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.
- BOrganize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.
- CIssue the team lead a warning, and consider recommending the team lead for emotional
intelligence training. - DFind ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.
81A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required How should the project manager assist the product owner?
- ACoach the product owner on how to create a product backlog
- BEncourage the team to subdivide the project tasks
- CCreate a work breakdown structure (WBS) and explain the deliverables to the product owner
- DDiscuss the product owner's responsibilities within the project team
82A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.
What should the project manager have done to prevent this conflict?- AProvided copies of the stakeholder engagement plan to all team members.
- BDefined the roles and responsibilities of the team members.
- CUpdated the communications management plan.
- DEstablished ground rules for the team
83During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
- ARevisiting the project management plan to ensure deliverables are on time
- BIncreasing the frequency of project update meetings to keep stakeholders informed
- CRevisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders
- DReviewing the business case and identifying gaps within scope
84A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one member reported an impediment that requires collaboration from an expert who is assigned to another project.
What should the project manager do first in this situation?- AReview the project's key performance indicators (KPIs) to determine the impact of this assignment.
- BCheck the expert's availability within the organization on an as-needed basis.
- CDevelop the team member's capacities through mentoring and training.
- DAsk the project sponsor to assign a new resource with the necessary expertise to the team
85A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.
What should the project manager do?- ADiscuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.
- BMeet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.
- CRequest a meeting with the sponsor to change the scope to allow the development team to conduct testing.
- DMeet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.
86A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings What should the project manager do?
- AAsk the individual who is hosting the event to use private communication methods.
- BSet up a meeting with the distracted team member to discuss any issues
- CAdd a social events section to the charter to handle these situations
- DAsk the individual who is hosting the event to mark it as private
87An agile team is making infrastructure changes to the human resources (HR) application system. Conflicting requirements are being submitted by various stakeholders.
What should the project manager do to help move the project forward?- AReview documents provided by other teams, such as lessons learned and the risk matrix.
- BAttend the Scrum of Scrums to identify roadblocks and manage dependencies.
- CStudy the technology to assist the team in decision-making if progress slows.
- DEncourage the stakeholders to collaborate by facilitating meetings and sharing knowledge.
88At the end of a workshop to review project deliverables, a number of follow-up action items were generated.
What should the project manager do next?- ADefer all actions until the next workshop to keep the team focused on other higher priorities
- BFollow up on each item as soon as possible to ensure timely completion and report the status to management.
- CReview the critical path and update the project schedule with the newly identified tasks.
- DPrioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.
89During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could become unmanageable with time. What should the project manager do?
- AHelp the team create the definition of done (DoD) to improve delivery quality.
- BAdd testing items to the backlog to assess quality periodically.
- CExpand the team in order to improve the quality of the project.
- DCompare the cost of improving quality against the cost of failure and adjust the budget.
90Drag the communication event on the left to the main subject discussed during the event on
the right- AĐáp án

- BĐáp án ở trên
- AĐáp án
91During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team How should the project manager handle this situation?
- AImplement crashing to compress the schedule and improve the schedule performance index (SRI).
- BImplement fast-tracking to compress the schedule and improve the SPI
- CPerform conflict management using the project's resource management plan.
- DReview the risk management plan to evaluate the probability and impact of these delays
92During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?
- AAssess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.
- BInvite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.
- CConduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.
- DInclude the stakeholder on regular project communications so that decisions can be followed up closely.
93While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?- AEscalate the issue to the project sponsor.
- BAddress the issue during the next sprint planning meeting.
- CInitiate a change request to extend the project end date.
- DExtend the dates for future project milestones.
94During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
- AReevaluate the project schedule as the velocity will be impacted by the loss of resources
- BReevaluate the backlog priority with the product owner since the velocity has been impacted
- CReevaluate the scope of the current iteration to keep the same velocity and timeline
- DReevaluate the velocity as the iteration duration will be impacted by new requirements
95An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?- AEscalate this to the project director for a resolution.
- BEscalate this to the agile lead of the second team.
- CReview the process and remove the impediment.
- DRemove the certification need from the project scope.
96During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?- AAllow the agile team to decide what they are able to deliver in each iteration
- BAsk the team for additional feedback and add tasks to the task board
- CHold a brainstorming session to identify the root cause of the complaints.
- DDocument the customer's complaints and critical issues in the issue log.
97A team has been working on a project for several months„ but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?- ACreate a prioritized backlog and define iteration review sessions with stakeholders
- BCreate a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders
- CSchedule a daily meeting to review team performance and impediments
- DSchedule a kick-off meeting for every project phase to share the project management plan with all stakeholders
98A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)- AThe junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.
- BThe junior project manager can discuss certain problems with their mentor without fear of retribution.
- CThe mentor will be immediately available to take over the project if there are problems or project delays.
- DThe mentor will be involved in the decision-making processes implemented by the junior project manager.
- EThe mentor can provide past project documentation with early warning indicators that potential problems could occur.
99A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.
What should the project manager do?- AAllow the most senior team members to decide the time that works for the team.
- BReassess the team's hours collaboratively so that the team is not impeded by the issue.
- CDiscuss the lack of dedication with the team member and their functional manager.
- DRemove the team member from the project team to be fair to the other members.
100A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.
How should the project manager handle this issue?- ADisregard these stakeholders since the relevant documents have been secured to execute this project.
- BUpdate the stakeholder register and risk management plan.
- CUpdate the stakeholder register and revise the stakeholder engagement plan.
- DExplain to the community members why they were not included as stakeholders for the project.
Information
- Description