PMP - Full Exam 1

Description

User has deleted their subject information Quiz on PMP - Full Exam 1, created by Deleted user on 29/03/2017.
Deleted user
Quiz by Deleted user, updated more than 1 year ago More Less
Created by a deleted user over 7 years ago
Baruch Herrera
Copied by Baruch Herrera about 7 years ago
42
0

Resource summary

Question 1

Question
A business case, which helps to determine whether a project is worth the investment, is created on the basis of the following except for
Answer
  • Market Demand
  • Ecological Impacts
  • Social Need
  • Availability of Funds

Question 2

Question
You are in charge of developing a new product for an organization. Your quality metrics are based on the 80th percentile of each of the last three products developed. This is an example of:
Answer
  • Statistical sampling
  • Metrics
  • Benchmarking
  • Operational definitions

Question 3

Question
The two closing procedures are called:
Answer
  • Contract closure and scope verification
  • Close Procurements and Close Project
  • Project closure and product verification
  • Project closure and lessons learned

Question 4

Question
During the develop schedule process, the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
Answer
  • Critical Path Method, GERT, Resource Requirements
  • Resource Leveling Heuristics, Mathematical Analysis, Calendars
  • Schedule compression, Resource optimization techniques, Critical chain method
  • GERT, PERT, Leads and Lags

Question 5

Question
Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the issue in the long term?
Answer
  • Problem solving
  • Withdrawal
  • Forcing
  • Smoothing

Question 6

Question
In communication, the receiver decodes the messages based on all but the following:
Answer
  • Culture
  • Semantics
  • Language
  • Distance
  • Knowledge

Question 7

Question
How much time does the typical project manager spend communicating both formally and informally?
Answer
  • 40-60%
  • 50-70%
  • 60-80%
  • 75-90%

Question 8

Question
Group brainstorming encourages all of the following except:
Answer
  • Team building A project manager facilitates communication
  • Analysis of alternatives
  • Convergent thinking
  • Uninhibited verbalization

Question 9

Question
The critical element in a project's communication system is the:
Answer
  • Progress report
  • Project directive
  • Project manager
  • Customer

Question 10

Question
System integration consists of:
Answer
  • Assuring that the pieces of a project come together at the right time
  • Planning for contingencies that may occur throughout the life cycle of the project
  • The pieces of the project function as an integration unit
  • a and c

Question 11

Question
Performance reviews are held to:
Answer
  • Correct the project manager's mistakes.
  • Provide for answers for upper levels of management
  • To assess project status or progress
  • To apprise the project costs and cost trends of the project

Question 12

Question
A complex project will fit best in what type of organization?
Answer
  • Functional
  • Cross-functional
  • Matrix
  • Balanced

Question 13

Question
Which of the following could be an appropriate WBS code for a work package at the fourth level in a WBS where the top level code is 1.0?
Answer
  • 1.4
  • 1.1.1.1
  • 1.2.3.4
  • a and c
  • b and c

Question 14

Question
Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?
Answer
  • Plan Scope Management
  • Define Scope
  • Validate Scope
  • Control Scope
  • Create WBS

Question 15

Question
The review of key deliverables and project performance at the conclusion of a project phase is called:
Answer
  • phase exit
  • kill point
  • stage gate
  • a and c
  • a, b and c

Question 16

Question
Project scope is:
Answer
  • All the work that must be done in order to deliver a product according to the specified features and functions, only
  • The features and functions that are to be included in a product or service.
  • A narrative description of work to be performed under contract.
  • a and b
  • all of the above

Question 17

Question
The unique identifiers assigned to each item of a WBS are often known collectively as:
Answer
  • The work package codes
  • The project identifiers
  • The code of accounts
  • The element accounts

Question 18

Question
The sender of a message is responsible for:
Answer
  • Confirming the message is understood
  • Ensuring the receiver agrees with the message
  • Scheduling communication exchange
  • Presenting the message in the most agreeable manner

Question 19

Question
What are the best uses of PERT:
Answer
  • Used in the planning phase to do " what if for the project.
  • Assist in the controlling of changes to the project.
  • Is used in the process of preparing a WBS for the project.
  • To measure future consequences of activities.
  • a and d.

Question 20

Question
Change requests can occur due to:
Answer
  • An external event such as a change in government regulation.
  • An error or omission in defining the scope of the product.
  • An error or omission in defining the scope of the project.
  • a and c
  • all of the above

Question 21

Question
A project management plan is:
Answer
  • A formal, approved document used to guide project execution, monitoring, and control.
  • A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.
  • A narrative description of products or services to be supplied.
  • D.A document describing the organizational breakdown structure of the company.

Question 22

Question
Which of the following is NOT an example of a type of schedule report?
Answer
  • Gantt chart
  • Milestone chart
  • Fishbone diagram
  • Network diagram

Question 23

Question
The most important criteria in deciding to initiate a project selection method is:
Answer
  • Stakeholder's vision
  • Low cost opportunity
  • Environmental consideration
  • Capability

Question 24

Question
Which of the following is correct order for stages in Tuckman ladder?
Answer
  • Foaming, Steaming, Norming, Perfuming, Dispersing
  • Forming, Storming, Protecting, Norming, Adjourning
  • Forming, Storming, Norming, Performing, Adjourning
  • Framing, Storming, Norming, Protecting, Adjourning

Question 25

Question
Three major processes in Project Human Resource Management are:
Answer
  • Staff recruitment, project staff planning and team building
  • Plan HRM, Acquire Project Team and Develop Project Team
  • Rewarding, salary reviews and penalties
  • Staff acquisition, staff training, staff deployment

Question 26

Question
A project is defined as:
Answer
  • A process of considerable scope that implements a plan.
  • An endeavor, which is planned, executed, and controlled; performed by people; and constrained by limited resources.
  • A temporary endeavor undertaken to create a unique product or service
  • An objective based effort of temporary nature.

Question 27

Question
Which of the following is not a General management technique?
Answer
  • Make-or-buy analysis
  • Analysis of alternatives
  • Applying PMBOK concepts
  • Lateral thinking

Question 28

Question
According to PMBOK, project management processes are organized into following order of process groups:
Answer
  • Initiating, planning, executing, monitoring, and closing
  • Designing, developing, testing, and implementing
  • Initiating, designing, planning, executing, controlling, and closing
  • Initiating, planning, executing, monitoring and controlling, and closing

Question 29

Question
___________ must be measured regularly to identify variances from the plan.
Answer
  • Stakeholder requirements
  • Project performance
  • Schedule progress
  • Cost

Question 30

Question
A project kick off meeting is usually conducted to:
Answer
  • Setup project team and announce the PM assignment
  • To draft project charter
  • Build up team spirit
  • Define project scope and develop WBS

Question 31

Question
Which of the following is not an external-unpredictable risk?
Answer
  • Changes in government regulations
  • Natural hazards
  • Unexpected environmental side effects
  • Inflation

Question 32

Question
Maslow ranked Human needs from the highest to lowest:
Answer
  • Self actualization; self promotion; social; security and physiological needs
  • Self esteem; self actualization; social; security and physiological
  • Self actualization; self esteem; social; security and physiological
  • Self fulfillment; self esteem; social; security and physiological

Question 33

Question
Which of the following statements concerning contract type is correct?
Answer
  • A fixed price contract contains the most risk for the buyer.
  • Cost reimbursable contracts offer sellers the highest profit potential.
  • Time and materials contracts are hybrid of cost reimbursable and fixed-price contracts
  • Unit price contracts are illegal in many jurisdictions

Question 34

Question
Herzberg identified factors, which, if present, will lead to increased motivation. A typical factor would be:
Answer
  • Good supervision
  • Job security
  • Regular promotions
  • Good salary

Question 35

Question
Your customer ask for a small change in the project, which was not budgeted in the project. It is a small effort as compared to the total project and you need the goodwill for a multimillion dollar on the pipeline. You will
Answer
  • Refuse to do the work
  • Agree to do the work at no charge
  • Do the work and bill him later
  • Assess the cost and schedule impact and tell them you will formalize the change request

Question 36

Question
You are responsible for ensuring that your seller's performance meets contractual requirements. For effective contract administration, you should:
Answer
  • Hold a bidders conference
  • Establish the appropriate contract type
  • Implement the contract change control system
  • Develop a statement of work

Question 37

Question
The three major causes of change on a project are:
Answer
  • Replacement of the project manager or key project team members; changes in priorities by senior management; and contractual difficulties
  • Changes in the relative importance of time, resources, or cost ; new knowledge about the deliverable; and technological uncertainty
  • Errors in the initial assessment of how to achieve the goal of the project; new information about the project deliverable; and a new mandate
  • Unavailability of resources promised by the functional managers; cost overruns; and changes in customer requirements

Question 38

Question
The purpose of the review of deliverables and project performance at the conclusion of a project phase is to:
Answer
  • Determine how many resources are required to complete the project according to the project baseline
  • Adjust the schedule and cost baselines based on past performance
  • Obtain customer acceptance of project deliverables
  • Determine whether the project should continue to the next phase

Question 39

Question
Your project is in the final test stage, the user acceptance test. It meets all the product specs and is under planned costs. In term of schedule, this project is ahead. Your customer met you and requested that he will not accept the product unless you make several changes. What you should do is:
Answer
  • Get the list of the changes and estimate all of them. If the total cost is still within the baseline, you will do it
  • Estimate the costs and send this to your customer requesting contract modification
  • Ask the customer to file a change request
  • Sit with the customer to review the product specs and tell him/her that you have completed the project.

Question 40

Question
The Delphi Method is best suited for:
Answer
  • Decision-making
  • Cost Control
  • Overhead rate estimating
  • Team discussions

Question 41

Question
Which of the following methods is least likely to be used for explaining project planning guidelines to the team?
Answer
  • Project Office Memo
  • Project office directive
  • Project team meeting
  • Formal project report

Question 42

Question
Projects are initiated in response of:
Answer
  • Stakeholder's pressure
  • Business needs
  • Technological obsolescence
  • All of the above

Question 43

Question
The party that needs the change resulting from the project, and who will be its custodian on completion is the:
Answer
  • Owner
  • Sponsor
  • Customer
  • Client

Question 44

Question
A document or tool which describes when and how human resources will be brought onto and taken off the project team is called a:
Answer
  • Staffing Management Plan
  • Responsibility Assignment Matrix (RAM ).
  • Organizational Breakdown Structure (OBS).
  • Resource Assignment Chart

Question 45

Question
In which type of organization is team building likely to be most difficult?
Answer
  • Functional
  • Projectized
  • Matrix
  • Project expediter

Question 46

Question
A tool which links the project roles and responsibilities to the project scope definition is called:
Answer
  • Scope Definition Matrix
  • Responsibility Assignment Matrix
  • Roles Assignment Matrix
  • Project Scope and Roles Matrix

Question 47

Question
Which of the following are outputs from the Plan Communications Management process?
Answer
  • Project records
  • Communications management plan
  • Performance reports
  • Formal acceptance

Question 48

Question
Which of the following statement is correct?
Answer
  • Process Groups are same as Project Phases
  • Each Process Group has a mapped Project Phase
  • Process Groups are not Project Phases
  • Monitoring and Control Process Group applies only in monitoring and control phase

Question 49

Question
The sending or conveying of information from one place to another is the process of:
Answer
  • Networking
  • Transmitting
  • Encrypting
  • Promoting

Question 50

Question
The three major types of communication are:
Answer
  • Written and oral, and verbal and nonverbal
  • Verbal, formal documentation, informal documentation
  • Verbal, written, and graphic
  • Verbal, written, and electronic

Question 51

Question
All of the following are communication methods EXCEPT:
Answer
  • Memos
  • Grapevine
  • Videos
  • Instant messaging

Question 52

Question
Communication is the PRIME responsibility of a Project:
Answer
  • Manager in a weak matrix
  • Manager in a projectized environment
  • Coordinator
  • Expeditor

Question 53

Question
What are the four parts of the communications model?
Answer
  • Sending, Receiving, Decoding, and Comprehending
  • Sender, Message, Medium, Receiver
  • Communicator, Message, Receiver, Decoder
  • Communicating, Transmitting, Receiving, Comprehending

Question 54

Question
In negotiations between the functional department managers and the project managers, which conflict management approach must be aimed at?
Answer
  • Win-Lose
  • Win-Win
  • Lose-Lose
  • None of the above

Question 55

Question
A type of organization in which the project manager has little formal authority and basically acts as a staff assistant to an executive who is ultimately responsible for the project is called:
Answer
  • Balanced matrix
  • Weak matrix
  • Projectized
  • Strong matrix

Question 56

Question
A type of organization in which the project manager has little formal authority and basically acts as a staff assistant to an executive who is ultimately responsible for the project is called:
Answer
  • Balanced matrix
  • Weak matrix
  • Projectized
  • Strong matrix

Question 57

Question
Create WBS process belongs to:
Answer
  • Initiation Process Group
  • Planning Process Group
  • Executing Process Group
  • Monitoring & Controlling Process Group

Question 58

Question
In which of the following organizations is the project manager role likely to be that of staff assistant?
Answer
  • Weak matrix
  • Functional
  • Balanced matrix
  • a and b

Question 59

Question
Project Risk Management includes all of the following processes except:
Answer
  • Risk Quantification
  • Risk Response Control
  • Risk Analysis
  • Risk Identification

Question 60

Question
Using the PMBOK definition of contingency reserve, which of the following statements about contingency reserves is false?
Answer
  • A contingency reserve is a separately planned quantity used to allow for future situations which may be planned for only in part.
  • Contingency reserves may be set aside for known unknowns.
  • Contingency reserves may be set aside for unknown unknowns.
  • Contingency reserves are normally included in the project's cost and schedule baselines.

Question 61

Question
Which of the following is true about a risk?
Answer
  • A risk can be deflected or transferred to another party through a contract or insurance policy.
  • Risks involve the chance of both a profit and a loss.
  • No opportunities are associated with a risk, only losses.
  • a and b

Question 62

Question
A contingency plan is:
Answer
  • A planned response that defines the steps to be taken if an identified risk event should occur.
  • A workaround
  • A reserve used to allow for future situations which may be planned for only in part.
  • a and c

Question 63

Question
Deflection or transfer of a risk to another party is a type of?
Answer
  • Risk Mitigation
  • Risk Acceptance
  • Risk Avoidance
  • Strategy for negative risks

Question 64

Question
Management reserves are used to handle which type of risk?
Answer
  • Unknown unknowns
  • Known unknowns
  • business risks
  • pure risks

Question 65

Question
Which of the following is considered during the Procurement Planning Process?
Answer
  • Whether to procure
  • How to procure and how much to procure
  • What and when to procure
  • A, B, and C

Question 66

Question
From a buyer's standpoint, which of the following is true?
Answer
  • Procurement planning should include consideration of potential subcontracts
  • Procurement planning does not include consideration of potential subcontracts since this is the duty of the contractor.
  • Subcontractors are first considered during the Solicitation Process
  • none of the above

Question 67

Question
Which of the following is true about procurement documents?
Answer
  • Procurement documents are used to solicit proposals from prospective sellers.
  • Invitation for Bid and Request for Proposal are two examples of procurement documents.
  • Procurement documents should be structured to facilitate accurate and complete responses from prospective sellers.
  • A, B, and C

Question 68

Question
Which of the following is a method for quantifying qualitative data in order to minimize the effect of personal prejudice on source selection?
Answer
  • Weighting system
  • Screening system
  • Selecting system
  • none of the above

Question 69

Question
Which of the following are examples of indirect costs?
Answer
  • Salaries of corporate executives
  • Salaries of full-time project staff
  • Overhead costs
  • A and C

Question 70

Question
Which of the following contract types places the greatest risk on the seller?
Answer
  • Cost-plus-fixed-fee contract
  • Cost plus-incentive-fee contract
  • Fixed-price-incentive contract
  • Firm-fixed-price contract

Question 71

Question
In which of the following contract types is the seller's profit limited?
Answer
  • Cost-plus-percentage-cost contract
  • Cost-plus-fixed-fee contract
  • Fixed-price-plus-incentive
  • B and C

Question 72

Question
A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?
Answer
  • $143,000
  • $142,000
  • $140,000
  • $132,000

Question 73

Question
The outputs of the Monitor and Control project work are utilized as inputs for the Performance of Integrated Change Control to give the following outputs, excluding.
Answer
  • Approved Change Requests
  • Change Log
  • Change Requests
  • Project Management Plan Updates

Question 74

Question
Under what circumstances is it better for a contractor to subcontract?
Answer
  • The subcontractor possesses special technical and engineering skills that the contractor does not have.
  • The work to be subcontracted represents almost all of the overall work effort.
  • The subcontractor can perform the work at a lower cost than the contractor.
  • a and c

Question 75

Question
Ramcharan, the project manager for a logistics project successfully undertook all the project activities and reached the final Close Project or Phase process that used the following inputs except for.
Answer
  • Accepted Deliverables
  • Enterprise Environmental Factors
  • Project Management Plan
  • Organizational Process Assets

Question 76

Question
Which of the following demonstrates a good negotiation skill?
Answer
  • Be ready to get the deal at any cost
  • Ensure that you get the most out of it
  • Offer more for less
  • Ask high and offer low

Question 77

Question
A narrative account of products, services or results to be achieved under a project comes in the form of
Answer
  • Project Statement of Work
  • Strategic Plan
  • Product Scope Description
  • Project Management Plan

Question 78

Question
The "rule of seven" as applied to process control charts means that :
Answer
  • If there are seven points on one side of mean, then an assignable cause must be found.
  • Seven consecutive points are ascending, descending, or the same.
  • At least seven quality inspectors should be in place for every thousand employees
  • A process is not out of control when at least seven measurements fall outside the lower and upper control limits.

Question 79

Question
There is project with CPI of 0.81 and TCPI=1.00001 this project is:
Answer
  • Over budget and hard to complete
  • Under budget
  • Over budget and early in its evolution
  • No inference can be made

Question 80

Question
A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project, is called:
Answer
  • Project life cycle
  • Portfolio management
  • Product life cycle
  • Program management

Question 81

Question
Which of the following activities do not fall under the Closing Process Group?
Answer
  • Document lessons learned
  • Applying appropriate updates to OPA
  • Recommending preventive action
  • Performing team members assessment

Question 82

Question
Who is not responsible for risk identification or reporting?
Answer
  • Project manager
  • Project team member
  • Project stakeholder
  • Functional Manager

Question 83

Question
Three Point Statistical Estimating Formula Group. Expected Value =
Answer
  • (Optimistic + (4 X Most Likely) + Pessimistic ) x 6
  • (Optimistic + (4 X Most Likely) + Pessimistic ) divided by 6
  • (Optimistic + (4 X Most Likely) x Pessimistic ) divided by 6
  • (Optimistic + (4 + Most Likely) + Pessimistic ) divided by 6

Question 84

Question
Parametric estimating is a technique where
Answer
  • is less costly, less time consuming and less accurate.
  • an algorithm is used to calculate cost or duration based on historical data and project parameters.
  • uses an average of most likely, optimistic and pessimistic activity durations
  • A and B

Question 85

Question
Examples of Projects include:
Answer
  • Implementing a new business procedure or process
  • Constructing a building or facility
  • Designing a new transportation vehicle
  • All of the Above

Question 86

Question
Projects are undertaken at all levels of the organization?
Answer
  • True
  • False
  • They are not related to each other
  • Neither true nor false

Question 87

Question
What does TQM stand for?
Answer
  • Time Quality Managed
  • Target Quality Management
  • Total Quality Management
  • Time Quote Management

Question 88

Question
________ means that every project has a definite beginning and a definite end.
Answer
  • Overall
  • Project Chart
  • Temporary
  • Duration

Question 89

Question
In case of an external IT project, the project initiator or sponsor must have provided the following information excluding.
Answer
  • Project Statement of Work
  • Agreements
  • Business Case
  • Organizational Process Assets

Question 90

Question
Who should be involved in the project planning phase?
Answer
  • The Project Manager.
  • The customer.
  • The Sub-contractors/vendors.
  • All of the above.

Question 91

Question
Cost Plus Incentive Fee (CPIF) contracts provide:
Answer
  • A reimbursement of allowable cost of services performed plus an agreed upon percentage of the estimated cost as profit.
  • A reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contract progresses.
  • The supplier with a fixed price for a delivered performance plus a predetermined fee for superior performance.
  • None of the above.

Question 92

Question
The successful project managers spend most of their time:
Answer
  • Planning with their personnel.
  • Planning with top management.
  • Communicating with project team.
  • Studying project results.

Question 93

Question
Project success depends on a number of interrelated factors, including time, cost and scope control. The success of any project depends primarily on:
Answer
  • Customer acceptance of deliverables
  • Customer satisfaction irrespective of outcome
  • Customer compromise in defining its needs
  • Exceeding customer requirements through gold plating.

Question 94

Question
Which of the following is the most efficient means of product quality inspection:
Answer
  • Statistical sampling.
  • 100% inspection
  • user review
  • A and C

Question 95

Question
A complete set of concepts, terms and activities that make up a professional field, project management field or an area of specialization is known as:
Answer
  • Knowledge Area
  • Domain Knowledge
  • Project Management Process
  • Project Management Group

Question 96

Question
Pareto Analysis, cause and effect diagrams and flow charts are used in quality.
Answer
  • Control.
  • Assurances.
  • Planning.
  • Verification.

Question 97

Question
In a multi-cultural environment, it is critical to establish a corporate culture that facilitates:
Answer
  • Problem-solving through different approaches.
  • Learning and communication
  • Partnerships, strong alliances and joint ventures
  • Negotiations.

Question 98

Question
A condition which will lead an organization towards conflict is:
Answer
  • Conflict of interest
  • Favoritism
  • Resolved prior conflicts
  • Both A and B

Question 99

Question
The contemporary view of conflict is that:
Answer
  • Conflict is bad.
  • Conflict is caused by trouble makers.
  • Conflict should be avoided.
  • Conflict is often beneficial

Question 100

Question
In general a project charter covers:
Answer
  • Project justification, background, scope, objectives, available resources, organizational responsibilities, a project schedule, estimates, procurement schedule, and any imitations that top management wants to apply.
  • Project justification, background, scope, objectives, available resources, organizational responsibilities, detailed project schedules, estimates, and detailed procurement schedules responsibilities, a project schedule, and any limitations that top management wants to apply.
  • Project justification, description, details of sponsor and project manager,, budget, assumptions and constraints, boundaries to apply.
  • Project scope, objectives, available resources, responsibilities, a project schedule, estimates, procurement schedules, and any limitations that top management wants to apply.

Question 101

Question
A project manager has increased project costs by US $75,000, but completed the project six weeks earlier than planned. What tool is best described here?
Answer
  • Resource leveling
  • Duration compression
  • Crashing
  • Fast tracking

Question 102

Question
Which of the following is most true?
Answer
  • Lag is the maximum amount of time a task can be delayed without delaying the early start of its successor.
  • Lag may be determined by making a forward pass
  • Lag is delay in start time, caused by delay in finish of predecessor activity.
  • Lag is the maximum amount of time a task can be delayed without delaying the project.

Question 103

Question
As project manager you should dedicate a primary focus to:
Answer
  • Managing all changes immediately as they surface.
  • Formally documenting all changes.
  • Communicating authorized changes to senior management and key stakeholders.
  • Preventing unnecessary changes

Question 104

Question
The behavioral responsibilities of a project manager may also include dealing with:
Answer
  • Regulatory Personnel
  • The legal environment
  • Environmental Issues
  • All of the above

Question 105

Question
The major purpose of project status reports is to:
Answer
  • Organize and summarize the information so that all stakeholders are informed
  • Inform upper management of the project problems
  • Inform the client about the changes that have completed
  • Provide information to management and client

Question 106

Question
Most project management leadership theories focus on all of the following except :
Answer
  • Personal characteristics of the project manager
  • Personal traits of the subordinates
  • Behavioral styles of the project manager
  • Usefulness of authority and power and leadership

Question 107

Question
Summary budget is arrived at during the______ phase of the project:
Answer
  • Initiation
  • Planning
  • Implementation
  • Execution

Question 108

Question
Historical records during closing are useful to __________ and ____________ for future projects:
Answer
  • Predict trends, highlight problems
  • Analyze successes, shortfalls
  • Analyze strengths, document results
  • Justify results, set standards

Question 109

Question
Your client informs that his company has a problem with the current design specs of your product and how it will interface with the existing systems. If this occurs, it could be a major problem for your project. The client is coming to your office in a week to discuss the problem and to see what your team can do to overcome this setback. All previous meetings were informal with this client, but now he wants a formal meeting. What should you do to prepare for this meeting:
Answer
  • Update the schedules and assume an active role since the client has not given you the specifics of the potential problem
  • Make sure that the team has increased productivity so the client can see how efficient your team is performing
  • Assemble the team and ask them to prepare an agenda for topics to discuss
  • Make sure that each team member has his assignment in preparation for any handouts and needed plans

Question 110

Question
The definitive terms of a contract are written during which of the following contract phases?
Answer
  • Contract phase
  • Post award phase
  • Award phase
  • Requirement phase

Question 111

Question
A document that formally recognizes the existence of a project is a :
Answer
  • Gantt Chart
  • WBS
  • Project Charter
  • Scope statement

Question 112

Question
Some organizations are now using 6 Sigma for quality control compared to the usual:
Answer
  • 2 sigma
  • 3 sigma
  • 4 sigma
  • 5 sigma

Question 113

Question
Reducing the impact of a risk event by reducing the possibility of its occurrence is:
Answer
  • Risk avoidance
  • Risk acceptance
  • Risk mitigation
  • Contingency planning

Question 114

Question
In which of the following project management process groups are the most time and money typically spent?
Answer
  • Initiating
  • Planning
  • Executing
  • Controlling

Question 115

Question
A supplier has withdrawn from your project. A new supplier has been added. His labor forces are due to arrive at the job site tomorrow. You should:
Answer
  • Meet with the supplier along with his team and establish yourself as the authority in charge.
  • Bring your team in for introductions and establish a communications exchange
  • Bring out the communication management plan
  • Bring out the project plan.

Question 116

Question
A supplier has withdrawn from your project. A new supplier has been added. His labor forces are due to arrive at the job site tomorrow. You should:
Answer
  • Meet with the supplier along with his team and establish yourself as the authority in charge.
  • Bring your team in for introductions and establish a communications exchange
  • Bring out the communication management plan
  • Bring out the project plan.

Question 117

Question
A new project manager is about to begin creating the project's scope of work. One stakeholder wants to add many items to the scope of work. Another stakeholder only wants to describe the functional requirements. The project is important for the project manager's company but a seller will do the work. Which of the following would you advise the project manager to do?
Answer
  • The scope of work should be general to allow the seller to make its own decisions.
  • The scope of work should be general but the management must allow clarifications later.
  • The scope of work should be detailed to allow clarifications later.
  • The scope of work should be as detailed as necessary for the type of project.

Question 118

Question
After the kickoff meeting, two team members engage in a casual conversation about the project objectives and deliverables. It is clear they heard different messages during the meeting. One member is so adamant that the other member gives up arguing the point. After talking to the project manager, the second member confirms that the first member is mistaken. At this point, what is the BEST course of action?
Answer
  • The second team member should send the other team member an e-mail describing what he discovered.
  • At the next project meeting, the team member should ask the mistaken team member to describe his interpretation so the project manager can get everyone on the same page.
  • The project manager should send out an e-mail to the team restating the project objectives and deliverables
  • At the next project meeting, the project manager should spend time reviewing a documented scope statement with the goal of identifying this and other false assumptions.

Question 119

Question
During project execution, a project team delivers a project deliverable to the customer. However, the customer neither acknowledges the deliverable nor says if it is acceptable, although an approval is required. What is the BEST thing to do?
Answer
  • Continue with the project
  • Document the situation
  • Contact management for help
  • Call a meeting of the team

Question 120

Question
You are managing a six-month project and have held bi-weekly meetings with your project sponsors. After five-and-a-half months of work, the project is on schedule and budget, but the sponsors are not satisfied with the deliverables. This situation will delay the project completion by one month. The MOST important process that could have prevented this situation is:
Answer
  • Risk monitoring and control.
  • Schedule control
  • Regular walkthroughs and sign-offs
  • Scope change control

Question 121

Question
When you are closing out a project, what must you do?
Answer
  • Provide project feedback to the team
  • Obtain sign off from the customer
  • Review project documentation for completeness
  • Update the project plans

Question 122

Question
Financial controls that need to be considered for project plan development do not include:
Answer
  • Time reporting
  • Standard contract provisions
  • Process audits
  • Accounting codes

Question 123

Question
A project manager has been working on a project for six months with the same team yet the team still shows a lack of support for the project. The best thing for the project manager to do would be to?
Answer
  • Re-evaluate the effectiveness of the reward system the project manager has put in place
  • Talk to each team member's boss
  • Re-plan the project
  • Tell the team he needs its support

Question 124

Question
A project has several teams. Team C has repeatedly missed several deadlines in the past causing Team D to have to crash the critical path several times. As the project leader for Team D, what should you do?
Answer
  • Meet with management alone
  • Meet with the project manager alone
  • Meet with the project manager and management
  • Meet with the project manager and the team C leader

Question 125

Question
The current update to the schedule performance report shows no schedule variance. Based upon the reporting, you have told the client that the project is on time. However, your team members know that a major milestone has just been missed and that the project will not meet its startup date. This is an indication of poor?
Answer
  • Communication management planning
  • Scope management planning
  • Team trust
  • Schedule planning

Question 126

Question
A project manager is assigned a project with a team that has already been selected. The first thing the project manager should find out about the team is?
Answer
  • What is each team member's favorite color
  • Each team member's objectives for working on the project
  • A list of each team member's tasks
  • Each team member's role in the project plan

Question 127

Question
An advisor to a new project manager tells the project manager to create lessons learned document at the end of a project. A lessons learned document includes?
Answer
  • Any variances and the causes of the variances
  • Reports from the customer
  • Reports from management
  • A list of all the plans

Question 128

Question
Abdullah, a project manager in XYZ Company is managing a project on IT and is looking for historical data on the usage of the previous software and applications in the company; he will get it in.
Answer
  • Newspaper Archives
  • Organizational Process Assets
  • Management Information System
  • Enterprise Environmental Factors

Question 129

Question
The project is completed and the final deliverable given to the customer but the customer refuses to take any action to give final acceptance on the project. The project manager should?
Answer
  • Repeatedly ask for final acceptance
  • Ask the team for assistance
  • Document the situation
  • Do nothing because there is nothing that can be done

Question 130

Question
What do knowledge, skills, tools and techniques stand for when applied to the activities of a project, if it also entails effective management of a process.
Answer
  • Human Resource Management
  • Project Management
  • Financial Management
  • Project Management Process

Question 131

Question
The Precedence Diagramming Method :
Answer
  • has finish-to-start task relationships and provides the flexibility of lead and lag time to the activities;
  • has the activity on the arrow
  • is also known as Arrow Diagramming Method
  • is used to make precedence diagrams

Question 132

Question
Gantt charts are great for:
Answer
  • Showing tasks relationships
  • Tracking actual vs planned
  • Optimum Resource utilization
  • b and c

Question 133

Question
Ultimate responsibility for quality management in the project rests with the?
Answer
  • Project engineer
  • Purchasing agent
  • Quality manager
  • Team members

Question 134

Question
Design of experiments?
Answer
  • identifies which factors may influence specific variables of a process or product
  • identifies which variables don't have any influence on quality
  • determines what a quality outcome is
  • is a method for research and development

Question 135

Question
You are a project manager for a major information systems project. Someone from the quality department comes to see you about beginning a quality audit of your project. The team, already under pressure to complete the project as soon as possible, takes objection to the audit. You should explain to the team that the purpose of a quality audit is?
Answer
  • part of an ISO 9000 investigation
  • to check if the customer is following its quality process
  • to identify lessons learned that can improve performance on the project
  • to check the accuracy of the costs submitted by the team

Question 136

Question
You manage a project whose team members have diverse skills and expertise. You want to encourage your staff to pool its knowledge on project issues to make the best decisions possible. The most appropriate management style to use is:
Answer
  • Laissez-faire
  • Democratic
  • Autocratic
  • Directive

Question 137

Question
The types of power that have substantial influence on both subordinates and upper management are:
Answer
  • Formal & expert
  • Reward & penalty
  • Expert & referent
  • Formal & referent

Question 138

Question
Your preferred resource is not available at the time needed. What is the best thing to do?
Answer
  • Negotiate with management to get the resource
  • Assess your alternatives
  • Begin the task early
  • Use reserves to increase resources assigned to those tasks

Question 139

Question
An important piece of hardware will be late. What is the first thing to do?
Answer
  • Discuss with team
  • Use schedule reserves
  • Use alternate vendor
  • Go to customer or management

Question 140

Question
A project has experienced significant delays due to equipment problems, staff attrition, and slow client reviews. The project is 40% complete and has used 60% of the available calendar time. What is the FIRST thing you should do?
Answer
  • Re-baseline the schedule to reflect the new date
  • Analyze the critical path activities for potential to fast track or crash the schedule
  • Document the lack of progress and associated issues to management
  • Identify tasks that have required more time than planned

Question 141

Question
functional manager wants to make a change to the time associated with a task, but there is not enough reserve to accommodate the change. Who should authorize the change?
Answer
  • Senior management
  • The functional manager
  • The project manager
  • The team member performing the work

Question 142

Question
During the course of a project you have motivated team members, managed conflict, performed personnel administrative functions and negotiated for more resources. These are examples of:
Answer
  • General Project Management
  • Project Human Resource Management
  • Project Execution
  • A Projectized organization

Question 143

Question
You have been promoted to Manager, Continuous Process Improvement. Your new position:
Answer
  • Is a project because the work will be performed by people
  • Is not a project because Continuous Process Improvement will continue indefinitely
  • Is a project because it is constrained by limited resources
  • Is a project because improvements must be planned, executed, and controlled

Question 144

Question
Which of the following is not a Project Management knowledge area?
Answer
  • Project Quality Management
  • Project Procurement Management
  • Project Configuration Management
  • Project Risk Management

Question 145

Question
The state of being totally answerable for the satisfactory completion of a specific assignment is called:
Answer
  • Authority
  • Accountability
  • Responsibility
  • Fiduciary

Question 146

Question
You are responsible for the communication controls for the Genesis series of satellites. Your current assignment is:
Answer
  • Project management
  • Functional management
  • Facility management
  • Program management

Question 147

Question
Work packages are used to :
Answer
  • Represent units of work at a level where work is performed.
  • Distinguish one package from all others assigned to a single functional group.
  • Limit work to be performed to relatively short periods of time.
  • All of the above.

Question 148

Question
Network planning methods(PERT/CPM/PDM):
Answer
  • Are usually too complicated for practical use on most projects
  • Require highly trained specialists for effective use
  • Always require computer support to be practical
  • Are based on flow charts and they allow observation of what happens to the project schedule when changes occur to a task's start and stop dates

Question 149

Question
Earned value can be described as:
Answer
  • The value of the equipment that has been installed as of the current date
  • The sum of the labor costs that have been incurred on the project date
  • A method of measuring project performance
  • A method of measuring the amount of money that has been spent to date

Question 150

Question
A role of the change control board (CCB) is to:
Answer
  • issue change requests
  • represent top management interests in initiating innovation
  • review the impact of change requests on project costs, schedule, and specifications
  • identify new areas of project work

Question 151

Question
Quality control is:
Answer
  • identifying which quality standards are relevant to the project and determining how to satisfy them
  • monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance
  • evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards
  • taking action to increase the effectiveness and efficiency of the project so as to provide added benefits to both the performing organization and the project customer

Question 152

Question
Cost of quality is a concept that includes:
Answer
  • the cost necessary for ensuring conformance to requirements
  • the life cycle cost of the project
  • all research and development costs related to the project
  • only the cost of the quality control function

Question 153

Question
The pillars) of quality is (are) :
Answer
  • Quality is free
  • Doing it right the first time
  • Zero defects
  • B and C

Question 154

Question
Quality assurance is:
Answer
  • top management's intention regarding quality
  • functions determining implementation of the quality policy
  • actions to provide confidence of satisfying quality requirements
  • responsibilities and processes which implement quality management

Question 155

Question
The zero defects concept:
Answer
  • is a performance standard for management
  • is a motivational technique that promotes "doing it right the first time"
  • is used by management to communicate to all employees that everyone should do things right the first time
  • A and C

Question 156

Question
When appointed, a project manager has the inherent forms of legitimate power conveyed to him. The three forms of legitimate power are:
Answer
  • absolute, direct, and indict
  • direction, coordination, and liaison
  • formal, informal, and persuasive
  • formal, reward, and penalty

Question 157

Question
The five types of conflict resolution are listed below and represent, in general order of importance, the methods a project manager should use to manage conflict. The one used most often by project managers to resolve conflict is:
Answer
  • confrontation
  • compromise
  • smoothing
  • forcing

Question 158

Question
The process of getting a group of diverse individuals to work effectively together as a team is the definition of
Answer
  • leadership
  • project management
  • the project manager's responsibilities
  • team building

Question 159

Question
Which contract type should be used by the owner on a high risk project?
Answer
  • Cost plus percentage of cost
  • Cost plus incentive fee
  • Lump sum
  • Fixed price plus incentive fee

Question 160

Question
The technique used under the Quantitative Risk Analysis that helps to determine which risks have the most potential impact on the project is called
Answer
  • Sensitivity Analysis
  • Expected Monetary value Analysis
  • Modeling and Simulation
  • Expert Judgment

Question 161

Question
Project risk is characterized by three factors:
Answer
  • Severity of impact, duration of impact and cost of impact
  • Identification, type of risk category and probability of impact
  • Risk event, risk probability and the amount at stake
  • Occurrence, frequency and cost

Question 162

Question
Name the ethical code you'll be required to adhere to as a PMP:
Answer
  • PMI Policy of Ethics
  • PMI Code of Ethical Conduct
  • PMI Code of Professional Ethics & Standards
  • PMI Code of Ethics and Professional Conduct

Question 163

Question
Which is not another term for contract?
Answer
  • Agreement
  • Purchase Order
  • Proposal
  • Memorandum of Understanding

Question 164

Question
Which of the following situations describes a violation of the Project Management Institute Code of Ethics and Professional Conduct?
Answer
  • Accepting a gift that is within the customary guidelines of the country or province you are currently working in.
  • Use of confidential information to advance your position or influence a critical decision.
  • Complying with laws and regulations of the state or province in which project management services are provided
  • Disclosing information to a customer about a situation that may have an appearance of impropriety.

Question 165

Question
You are working in a country where it is customary to exchange gifts between contractor and customer. Your company code of conduct clearly states that you cannot accept gifts from any client. Failure to accept the gift from this client may result in termination of the contract. The action to take in this case would be:
Answer
  • Provide the customer with a copy of your company code of conduct and refuse the gifts
  • Exchange gifts with the customer and keep the exchange confidential
  • Report the matter to your project sponsor and /or your legal office for assistance.
  • Ask the project sponsor or project executive to exchange gifts.

Question 166

Question
An example of a conflict of interest would be:
Answer
  • As a public official you make a decision about a contract award that will benefit you personally
  • You and a functional manager disagree with a task cost estimate
  • Your sponsor decides to cancel your project because it no longer supports the company strategy
  • Your personality conflicts with that of a key member of your project team.

Question 167

Question
The strategies under the tool of Strategies for negative Risks or Threats and which typically deal with threats or risks that may have negative impacts on project objectives if they occur includes all except:
Answer
  • Avoid
  • Mitigate
  • Transfer
  • Accept

Question 168

Question
Project Managers can contribute to their organization's knowledge base and to the profession of project management most effectively by:
Answer
  • Developing and implementing a project review and lessons learned process
  • Establishing strict guidelines for protecting intellectual property
  • Promote the use of ad hoc project management
  • Ensuring that all project plans are developed before the project team is formed

Question 169

Question
For a festival, you give your government client a leather brief case which is against the law. You are in violation of the responsibility to:
Answer
  • Complete your work within the budget
  • Comply with regulations.
  • Provide accurate information.
  • Save company costs.

Question 170

Question
You have just changed jobs and discovered that your new employer routinely violates OSHA/EPA and affirmative action requirements on projects. You should first:
Answer
  • Do nothing. It's not your problem
  • Start by asking management if they are aware that regulations are being violated
  • Talk to the corporate legal department
  • Inform the appropriate government agencies about the violations

Question 171

Question
During your assignment as project manager, you add a new member to your project team. This new team member was recently hired from a competitor and offers to share a substantial amount of proprietary information from his previous company. This information could put you and your team in a very strong position for future business. You are aware of a non-compete clause in the new hire's condition of employment. You should:
Answer
  • Accept the information and agree to keep it confidential between you and the new hire.
  • Review the condition of employment with the new hire and advise him to reconsider the offer.
  • Review the information and only accept only what may have a direct impact on the project's financial status.
  • Ignore the offer to share and move forward with the project

Question 172

Question
Before reporting a perceived violation of an established rule or policy the project manager should:
Answer
  • Determine the risks associated with the violation
  • Ensure there is a reasonably clear and factual basis for reporting the violation
  • Ignore the violation until it actually affects the project results
  • Convene a committee to review the violation and determine the appropriate response

Question 173

Question
A response to a negative risk event is known as a:
Answer
  • Work Item
  • Work Package
  • Workaround
  • Work breakdown structure

Question 174

Question
Qualitative Risk Analysis will be performed under :
Answer
  • Initiation Process Group
  • Planning Process Group
  • Executing Process Group
  • Monitoring and Controlling Process Group

Question 175

Question
Acquire Project team process will be performed under:
Answer
  • Initiating Process Group
  • Planning Process Group
  • Executing Process Group
  • Monitoring and Controlling Process Group

Question 176

Question
The objectives of Project Risk Management includes
Answer
  • To increase the likelihood and impact of positive events
  • To decrease the likelihood and impact of negative events
  • Only A
  • Both A & B

Question 177

Question
In a group of 4 members, 1 member has been added. How many communication channels are there now :
Answer
  • 5
  • 3
  • 10
  • 20

Question 178

Question
Which of the following statements is correct?
Answer
  • There are only some core processes and some facilitating processes in the PMBOK
  • PMI is not responsible for producing the PMBOK.
  • PMBOK will be changed every year in December
  • PMBOK has 10 process groups and 47 processes

Question 179

Question
Which of the following is not an input to Develop Project Charter:
Answer
  • Contract
  • Project Statement of Work
  • Enterprise Environmental Factors
  • Project Management Information System

Question 180

Question
Which of the following is a technique used to Create WBS:
Answer
  • Organizational Process Assets
  • Decomposition
  • WBS Dictionary
  • Configuration Management System

Question 181

Question
Which of the following is not an input to Define Activities process:
Answer
  • WBS Dictionary
  • Organizational Process Assets
  • Project Scope Statement
  • Schedule Network Templates

Question 182

Question
Which of the following is not an output of Estimate Activity Resources:
Answer
  • Activity Resource Requirements
  • Resource Breakdown Structure
  • Resource Categories and Types
  • Resource Management Plan

Question 183

Question
Which of the following is a tool used in Estimate Activity Durations:
Answer
  • Analogous Estimating
  • Work Breakdown Structure Templates
  • Critical Path Method
  • Schedule Network Templates

Question 184

Question
Crashing, and Fast tracking are techniques used in the following process:
Answer
  • Schedule Development
  • Activity Definition
  • Create WBS
  • Resource Allocation

Question 185

Question
Which is not a technique used for Estimate Costs process:
Answer
  • Analogous Estimating
  • Bottom-up Estimating
  • Parametric Estimating
  • Resource Leveling

Question 186

Question
Which is not a tool used in Quality Planning process :
Answer
  • Cost-Benefit Analysis
  • Benchmarking
  • Design of Experiments
  • Process Analysis

Question 187

Question
What are three tools used in Control Quality process:
Answer
  • Benchmarking, Cost of Quality (COQ) and Cause and Effect Diagram
  • Cost of Quality (COQ), Cause and Effect Diagram and Control Charts
  • Control Charts, Flowcharting and Process Analysis
  • Pareto Chart, Control Charts and Cause and Effect Diagram

Question 188

Question
Which of the following Human Resource process generates Roles & Responsibilities:
Answer
  • Plan Human Resource Management
  • Acquire Project Team
  • Develop Project Team
  • Manage Project Team

Question 189

Question
Co-Location is a techniques which means:
Answer
  • Placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team.
  • Placing many or all of the most active project team members in the same physical location to reduce the cost of the project
  • Performing a complete project at a single location
  • Performing a project at various locations

Question 190

Question
Manage Stakeholders is a part which of the following knowledge area:
Answer
  • Human Resource Management
  • Project Integration Management
  • Project Scope Management
  • Project Stakeholder Management

Question 191

Question
Which of the following is not correct about Communications Management Plan document:
Answer
  • It contains Stakeholder communication requirements
  • It contains the details of Person responsible for communicating the information
  • It contains Frequency of the communication, such as weekly
  • It contains total cost of communication

Question 192

Question
Which is not a tool used for Plan Risk Responses process:
Answer
  • Risk Audits
  • Avoidance
  • Transfer
  • Mitigate

Question 193

Question
Advertising is a technique used in which of the following process:
Answer
  • Select Sellers
  • Request Seller Responses
  • Contract Administration
  • Contract Closure

Question 194

Question
Which of the following definition is not correct:
Answer
  • Plan Human Resource Management - Identifying and documenting project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.
  • Acquire Project Team - Obtaining the human resources needed to complete the project
  • Develop Project Team - Improving the competencies and interaction of team members to enhance project performance
  • Team Building - Forming a team from scratch for a new project

Question 195

Question
Which of the following definition is not correct:
Answer
  • Contract Closure - completing and settling each contract, including the resolution of any open items, and closing each contract.
  • Plan Purchases and Acquisitions - selecting a buyer to purchase any product or service.
  • Select Sellers - reviewing offers, choosing from among potential sellers, and negotiating a written contract with a seller.
  • Request Seller Responses - obtaining information, quotations, bids, offers, or proposals, as appropriate

Question 196

Question
Which of the following is not correct:
Answer
  • PMO - Program Management Office
  • RBS - Resource Breakdown Structure
  • RAM - Resource Assignment Matrix
  • RFP - Request for Proposal

Question 197

Question
Which of the following is not correct :
Answer
  • Cost of Quality (COQ): Determining the costs incurred to ensure quality
  • Crashing: A specific type of project schedule compression technique performed by taking action to decrease the total project schedule duration.
  • Total Quality Management: A common approach to implementing a quality improvement program within an organization
  • Simulation: prototyping of a project to check if proposed design will work or not.

Question 198

Question
Most schedule simulations are based on some form of which of the following?
Answer
  • Delphi
  • PERT
  • CPM
  • Monte Carlo Analysis

Question 199

Question
What is critical path?
Answer
  • The shortest path through the network, which represents the longest amount of time in which a project can be completed.
  • The path with zero float.
  • The longest path through the network, which represents the shortest amount of time in which a project can be completed.
  • The path with the most activities with the longest durations.

Question 200

Question
In the communication process, "noise" is the word used to describe factors and forces inhibiting the exchange of information between two or more parties. Noise includes all of the following but __________
Answer
  • Culture
  • Behavior
  • Traditional way of doing things
  • Loud talking
Show full summary Hide full summary

Similar

06 PROJECT TIME MANAGEMENT
miguelabascal
Respiratory System
bridget.watts97
To Kill a Mockingbird Key Themes and Quotes
Matthew T
Creative Writing
amberbob27
TOEFL Practice
aliking
GCSE AQA Biology 2 Enzymes, Digestion & Enzyme Uses
Lilac Potato
Matters of Life and Death - Edexcel GCSE Religious Studies Unit 3
nicolalennon12
History- Religion and medicine
gemma.bell
Function and Structure of DNA
Elena Cade
GCSE REVISION TIMETABLE
Sonia Christopher
NSI / PSCOD/ ASSD
Yuvraj Sunar