  1. 1Which of the following statements is correct about "Independent Testing"?

    a. Using dependent testers is not effective at finding defects.
    b. Testing independence means that the person who tests the software is different from the person who develops it.
    c. No independent testers means that the testers are working from outside the organization.
    d. One of the benefits of independent testing is that the testers recognize different kinds of failures.
    e. One of the drawbacks of independent testing is that developers may lose the sense of responsibility for quality.
    1. Aa, b & c are correct; d & e are false
    2. Ba & b are correct; c, d & e are false
    3. Cb, d & e are correct; a & c are false
    4. Db & e are correct; a, c & d are false
  2. 2Which of the following is considered one of the tasks of the test manager?
    1. AReviewing requirements to find defects
    2. BAnalysis and execution of test cases
    3. CTest environment implementation decision
  3. 3Which of the following is considered as one of the tasks of the test manager?
    1. AGathering metrics and choosing tools needed for testing
    2. BWriting user stories and acceptance criteria
    3. CDesign test cases and configure test conditions
  4. 4Which of the following is considered as one of the tasks of the tester?
    1. ATest environment setup
    2. BWriting test policy and test strategy
    3. CInitiating the analysis, design, implementation and execution of tests
  5. 5Which of the following statements is correct about "Test planning"?

    a. Test planning is a continuous activity
    b. Feedback from the development activities is used to recognize risks in the test plan
    c. Planning may be documented in separated test plans for different test levels and types
    d. Test plan outlines test activities for development and maintenance projects
    1. Aa, d & c are correct; b is false
    2. Ba, b & c are correct; d is false
    3. Ca & c are correct; b & d are false
    4. Da is correct; b, c & d are false
  6. 6Which of the following is considered as a test planning activity?
    1. ADefining the overall approach of development
    2. BBudgeting the projects and defining code standards
    3. CChoose the programming language that will be used in development
    4. DDetermine the scope, objectives and risks of testing
  7. 7Scheduling of test analysis, design, implementation and execution is a... that it is performed by the...
    1. ATest Planning activity / Test Leader
    2. BTest Execution activity / Test Leader
    3. CTest Planning activity / Tester
    4. DTest Execution activity / Tester
  8. 8Choose the correct definition of "Test strategy"?
    1. AA measure of the proportion of executable statements exercised by the testers
    2. BProvides a generalized description of the test process
    3. CDocumentation of test activities in session-based testing
  9. 9"Risk-Based" testing is an example of.... test strategy.
    1. AMethodical
    2. BAnalytical
    3. CProcess-compliant
    4. DDirected
  10. 10"Reliability growth model" is an example of... test strategy
    1. AModel-based
    2. BMethodical
    3. CDirected
    4. DAnalytical

Informationen

Beschreibung
Quiz am Chapter 5 - CTFL ISTQB, erstellt von America LH am 07/06/2022.
Sprache
English
Aufrufe
190
Schlagwörter
ctflistqbtesting
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck