PERT Chart for Landscaping a Garden
Start
Mark Utilities
Dig holes
Plant trees
Plant flowers
Install Edging
Finish
Purchase Trees
Purchase Edging
Purchase Flowers
Time: 1 day
Time: 3 days
Time: 7 days
Time: 2 days
Time: 5 days
Time: 6 days
Time: 8 days
Time: 4 days
Critical Path Time: 22 days