Quantification and costing of construction works
Preparing Pricing documents
- tender documents generally
- BQ's
- Sch of Works
- Sch of rates
- Provisional sums
Methods of measurement
- SMM
- CESSMM
- 4 types of rules
- Measurement
- Sets out measured works
- Definition rules
- sets out meanings used in CESMM 3
- Coverage rules
- explains items included but not stated indescription
- Additional description rules
- additional descriptions
- Measurement
- Structure
- list of principle quants.
- preamble
- DW sch.
- work items
- summary
- 4 types of rules
- RICS code of Measuring Practice 6th ed.
- GEA
- gross external area
- the area of the building measured externally at each floor level
- gross external area
- GIA
- gross internal Area
- area of building measured to internal face of perimeter walls
- Ex. open sided balconies, fire esp., canopies, ext walls, fuel stores
- area of building measured to internal face of perimeter walls
- gross internal Area
- NIA
- Net Internal Area
- usable area within a building measured to the internal face of perimeter wall at each floor
- ex. internal structural walls & columns, spaces with headroom less 1.5m, corridors & circulation , perm lift lobbies, WC, cln cub, plant rm
- usable area within a building measured to the internal face of perimeter wall at each floor
- Net Internal Area
- definitions to permit accurate & consistent measurement
- GEA
- difference between SMM and CESMM
- SMM7 doc for measurement
- more details as for BQs
- e.g. excavation is separate items in SMM but classed as one in CESMM
- suitable for building projects
- more details as for BQs
- CESMM
- based on Ice Conditions of Contract
- SMM7 doc for measurement
Analysis of Price
- Tender Sums
- Guranteed/Agreed Maximum Price
- Target Cost - Pain-gain mech
- L&E
- Preliminaries
- Dayworks
Valuation of Works
- Interim Valuations
- Valuing Change
- Principles
- add/omit are valued by quantifying the change of scope + using rates/prices 4 identical /similar works as basis of valuation
- effects of prelims/risk allowances/design frees/OH&P should be considered
- works not similar = rates from other works in the contract used & used as a basis 2 form a new rate/price with adj 4 diff.
- star rate
- when not possible 2 produce a * state - a fair rate/price is calc by 2 reflect changed factors
- last resort = works valued on time taken and resources used 2 complete - dayworks
- JCT
- SBC XQ/Q/AQ
- XQ/Q
- change = alteration/mod of design quant. or qual.
- priced docs used 4 pricing vals (CSA/wk sch)
- contractor holds risk of properly quant scope.
- Value change?
- emp. & MC agree rate
- where agreement not met = QS carry out valuation using valuation rules
- change = alteration/mod of design quant. or qual.
- AQ
- Value Change?
- QS re-measure works carried out by contractor and adjust BQ
- Value Change?
- XQ/Q
- IFC
- Value change
- same as Q?XQ
- Value change
- D&B
- emp. & MC endeavour 2 agree valuation
- fail 2 agree = EA value in accordance with V Rules
- MW
- if fail 2 agree = Ca value on fair and reasonable basis based on work sch. + inc L&E
- MPC
- Early warning - both parties notify other if change.
- Emp request quote - deals with change + adj of prelims & design + EOT & L&E
- value of change agreed b4 instruction
- SBC XQ/Q/AQ
- NEC
- NEC A (act sch)
- VARIATION: Alterations/ modifications 2 design/qual/quant of the contract works 2 site access or working cond.
- different variations that could arise
- change 2 spec.
- discrepancy between contract doc
- discrepancy with stat requirements
- errors & omissions
- deficiency in emp requirements
- Instructions must be in writing - QS cannot make add 2 the contract sum for AIs that r not written
- Oral instrutions
- MC has 7 days 2 write 2 CA asking 4 the AI 2 b confirmed
- if the CA does not respond in a further 7 days it is taken as being an AI
- MC objecting 2 variations
- they can make reasonable obj in writing 4 variations relating 2 those described in 5.1.2 (work cond)
- CA can issue a compliance notice if the MC does comply with instruction
- if there is no action by the MC within 7 days, others can b emp. 2 carry out that wrk
- Principles
- L&E
- What is it?
- reimbuses the MC for direct L&E incurred in carrying out add wrk or from an emp breach
- Clauses in JCT SBC
- 4.23 to 4.26
- Procedure of claiming L&E
- 1. as soon as reg wrk affected, MC notifes CA in writing ,
- 2. MC 2 submit further info 2 CA if req.
- 3. submit further info 2 CA/QS 2 help them ascertain the amount of L&E
- Relevant Matters
- events than entitle MC 2 L&E, along with deferment of possession of site
- Relevant matters
- 5 in total
- 1. Variations
- 2. Instructions
- 3. Approx Qnts not properly described/forcast
- 4. suspension by emp
- 5. any impediment, prevention or default by MC
- 5 in total
- L&E should be an assessment if ACTUAL loss
- what is not permissible - accelerations and claim preparation
- Common heads of claims
- prolongation (xtr site OH e.g. prelims)
- Prelims thickeningm(extra supervision during period of delay)
- Disruption (underemployment of plant / laabour)
- Inc in labour/ mat cost during the period of delay
- head office OH
- Loss of profit (commonly combined with Head office OH
- Finance chanrges
- Acceleration costs
- not permissible in JCT contract
- claim prep costs
- not permissible in JCT contracts
- Use the HUDSON FORMULA
- Head office OHP/ 100 X Contract sum/ contract period X period of delay
- Global Claim
- Global claim is where there is no attempt 2 separate out all the diff causes & their effects.
- it lists a whole load of causes 4 delay/ L&E & gives the overall effect
- due 2 difficulties proving/disproving them, MC is likely 2 end up with something e.g. EOT or L&E
- Can MC claim if variations omits part of the works?
- the claim would be for loss of profit
- MC have 2 prove that no valid reason 4 emp to omit wrks - esp if the wrks then performed by another contractor
- MC right 2 b able 2 complete the wrk he was contracted 2 carry out, & realise the profit & therefore for omissions, careful wording the variation
- there cannot b fundamental changes 2 the charac 4 the wrk or else the contract may b seen 2 b breached
- What is it?
- Final Account
- Reporting on cost
- intems included
- Ex summary
- preliminaries
- instructed variations
- anticipated variations
- Claims
- total certified payments
- Purpose
- report against budgeted values & act as a working cost check on the project budget
- give client understanding of savings/add monies required
- report on contract progress against pre-contract predictions
- intems included
- Tender report
- list of tenders recieved
- initial tender rtn costs
- any quals identified
- post-tender adjustments
- revised tender sums
- issues to be resolved
- comparison of tender return
- recommendation
- comparison with PTE
- Correcting errors in tender
- JCT Practice note 6
- 2 alternative
- Alternative 1
- cont. given details of errors
- opportunity to confirm or withrdraw
- Confirm
- confirm tender sum in report
- withdraw
- approach the next lowest tenderer
- Confirm
- opportunity to confirm or withrdraw
- cont. given details of errors
- Alternative 2
- confirm or amend
- genuine errors
- Amend and now not lowest
- engage with lowest
- confirm or amend
- JCT Practice note 6
- Post contract financial reporting
Informationen
- Beschreibung
- T022 & T074 Mindmap am Quantification and costing of construction works, erstellt von alison_patey0437 am 25/04/2013.
- Erstellt von
- alison_patey0437
- Aufrufe
- 1.788
- Tags
- Bewertung