PERT Charts
Folien in diesem Satz (11)
-
- Program Evaluation Review Technique
- Also known as the Critical Path Method
- PERT is a planning and control tool which can be used to define and control tasks necessary to complete a project.
- Can be graphically represented in a network diagram
-
1. Identifying activities and milestones
- Activities are the tasks of the project.
- Milestones are the events that mark the beginning or end of one or more of the activities.

-
2. Identify the sequence of activites
- For some activities this may be obvious, and can be completed as part of step one.
- Other tasks may require some analysis to determine the appropriate order in which they should be performed
-
3. Construct a Network diagram
- A visual representation of the sequence of successive and parallel activites
- Arrowed lines represent activites
- Circles or "bubbles" represent milestones

-
4. Estimate times for activites
- This involves estimating three times for each activity:
- Optimistic time: How long it would take to complete the task in the best case scenario
- Pessimistic time: How long it would take to complete the task in the worst case scenario
- Most likely time: The highest probability time that the activity could take
- This times are used to calculate the expected time using the following equation:
- \[\text{ Expected time = } \frac{\text{(Optimistic time + (4 x Most likely time) + Pessimistic time)}}{6}\]
- Usually times are calculated in weeks, but other units can be used if it is more appropriate for the project in question.
-
5.1 Calculate start and finish times
- The following times for each activity should be calculated:
- Earliest Start Time
- Earliest Finish Time
- Latest Start Time
- Latest Finish Time
- Earliest Start and Finish Times: Determined by working forward through the network and determining the earliest time at which an activity can start and finish considering its predecessor activities
- Latest Start and Finish Times: Latest times that an activity can start and finish without delaying the project. LS and LF are found by working backward through the network
-
5.2 Determine the Critical Path
- The Critical Path is determined by adding the time for the activities in each sequence, in order to determine the longest path
- Slack time: The amount of time non-critical path activity can be delayed for without delaying the overall project
- The difference in the latest and earliest finish of each activity is that activity's slack.
- The critical path then is the path through the network in which none of the activities have slack.
-
5.3 Calculate Variance in Completion Time
- The variance in each activity can be calculated by \(Variance = (\frac{Pessimistic - Optimistic}{6})^2\)
- The variance in the project completion time can be calculated by summing the variances in the completion times of the activities in the critical path.
- Given this variance, one can calculate the probability that the project will be completed by a certain date assuming a normal probability distribution for the critical path.
- The normal distribution assumption holds if the number of activities in the path is large enough for the central limit theorem to be applied.
-
6. Updating chart as project progresses
- Estimated times can be replaced with actual times.
- In cases where there are delays, additional resources may be needed to stay on schedule and the PERT chart may be modified to reflect the new situation.
-

- Bildunterschrift: Example of Network Diagram: The Critical Path is marked in red. Each activity is assign an expected time. measured in days.
-
- Project activities must be clearly defined, independent and stable in their relationships
- Precedence relationships must be specified and networked together
- Time estimates are subjective and open for manipulation by managers
- There is a risk that too much emphasis might be placed on the critical path