SEGMENT 5 QUIZ: Constructing a Network Chart - SCHEDULE MANAGEMENT

brandon mayo 24 Fragen

Quiz starten

Fragen in diesem Quiz (24)

  1. 11. On an AOA diagram, the arrow between nodes represents:
    1. Aa. An activity.
    2. Bb. A constraint.
    3. Cc. An event.
    4. Dd. The critical path.
  2. 22. What type of contract is the most appropriate for a research and development project?
    1. Aa. Firm fixed price.
    2. Bb. Cost reimbursable.
    3. Cc. Time & materials.
    4. D. d. Fixed price plus incentive.
  3. 33. Events that are a part of activity sequencing for scheduling purposes, but have no duration, are:
    1. ACritical path activities
    2. BMilestones.
    3. CDummy activities
    4. DWork packages
  4. 44. A cost-plus-incentive fee contract provides a target cost of $1.2 million, target fee of $120,000 with a minimum fee of $60,000 and maximum of $200,000. The share ratio is 75/25. What would the fee be if costs are $995,000?
    1. A$51,250
    2. B$153,750.
    3. C$171,250
    4. D$200,000.
  5. 55. A network diagram may include one or more summary activities, known as:
    1. AHangers.
    2. BSubnetworks
    3. CHammocks
    4. DFragnets
  6. 66. How many processes are in the procurement knowledge area
    1. A4
    2. B5
    3. C6
    4. D7
  7. 7What is the point of total assumption for a contract having these parameters?
    Target cost = $297,000 Ceiling price = $387,659
    Target profit = $40,095 Share ratio (over-run) = 80/20
    1. A$360,205
    2. B$708,790.
    3. C$410,324.
    4. D$410,765
  8. 8A cost-plus-incentive fee contract provides a target cost of $1.2 million, target fee of $120,000 with a minimum fee of $60,000 and maximum of $200,000. The share ratio is 75/25. What is the fee if costs are $1.45 million?
    1. A$60,000
    2. B$62,500
    3. C$57,500
    4. D$200,000
  9. 99. When would it be appropriate to incorporate a subnetwork into the project plans?
    1. AYou need to roll up detail costs into a summary activity. The subnetwork becomes the summary.
    2. BThe project is internally repetitious
    3. CYou are using Graphical Evaluation and Review Technique (GERT) for conditional diagramming.
    4. DTo obtain more detailed critical path data.
  10. 1010. PTA refers to:
    1. AAn association concerned with elementary education.
    2. BThe price of a contract above which the contractor assumes full liability.
    3. CThe point of a cost-plus contract above which the contractor assumes full liability.
    4. DThe cost point of a contract above which the contractor assumes full liability.

Informationen

Beschreibung
PMP Project Management Quiz am SEGMENT 5 QUIZ: Constructing a Network Chart - SCHEDULE MANAGEMENT, erstellt von brandon mayo am 09/10/2017.
Sprache
English
Aufrufe
5
Schlagwörter
project managementpmp
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Mehr zu Network Diagrams, Critical Path and PERT

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck