Tyler Warford 77 Fragen Aktualisiert am 14 Okt 2024

Quiz starten

Fragen in diesem Quiz (77)

  1. 1change order is a written order to the contractor signed by the owner and the architect, issued after the contract execution
    1. ARichtig
    2. BFalsch
  2. 2notice window to submit a change order. time to tell the owner that an issue has been discovered.
    1. A48 hrs
    2. B24 hrs
    3. C1 week
    4. D12 hrs
  3. 3a change order signed by the contractor indicates the contractors agreement to contract price sum and contract time.
    1. ARichtig
    2. BFalsch
  4. 4What initiates a change?
    1. Acontractors, owner, or designer request.
    2. Bproposal request
    3. CRFI
    4. DError in Drawings
    5. EError in Specifications
    6. FDiffering site conditions
    7. GLack of product available
    8. HWeather
    9. IWorker strikes (union)
  5. 5Change Process
    1. ARecognition or initiation of a change
    2. Bproper contractual notice
    3. Cdetailed change analysis
    4. Destimate direct costs
    5. Eestimate indirect costs
    6. Foverhead and profit
    7. Gschedule impact & time extension
  6. 6change to work can have significant economic consequences for the contractors and subcontractors. therefore contractors must receive equitable compensation for accomplishing change work.
    1. ARichtig
    2. BFalsch
  7. 7anchoring is when a person relies heavily on the first piece of information received.
    1. ARichtig
    2. BFalsch
  8. 8a change order clause allows a GC to mark up a change order by 5% for the GC to make money. it is a common misconception that GC's make a lot of money on change orders
    1. ARichtig
    2. BFalsch
  9. 9revenue - cost = profit
    1. ARichtig
    2. BFalsch
  10. 10revenue and costs can be offset to balance the books.
    1. ARichtig
    2. BFalsch

Informationen

Beschreibung
Management Construction Quiz am Project Controls - Exam II, erstellt von Tyler Warford am 14/10/2024.
Sprache
English
Aufrufe
76
Verlauf
Erstellt am 14 Okt 2024 · aktualisiert am 14 Okt 2024
Schlagwörter
constructionmanagement
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck