Horizontal and Vertical Alignment Design Layout Design

Layout design covers the following areas:

design speed

other speeds

Speed analysis

stopping sight distance (SSD)

Full overtaking sight distance (FOSD)

Highway capacity

Design Speed The starting point for determining the geometry for a highway is the design speed. This, in turn, is determined by the purpose of the road. Once established, the design speed thereafter determines the other parameters of the road. For example, depending on design speed, decisions have to be made on the following matters:

control access

distance between junctions

length of road with hard shoulder

separation cross traffic

prohibition of certain vehicle types

Typical design speed band boundaries:

145, 120, 100, 85, 70, 60, and 50 km/h.

Typically below 50km/hr the concept of design speed is generally not used as an input to alignment design.

In the UK, the maximum design speeds used are 70mph (120km/hr) for dual carriageways and 60mph (100 km/hr) on single carriageways.

Highways are typically of two categories:

Urban roads - design speed less than 50km/hr

Rural roads - design speed more than 50km/hr

Percentile Speed The percentile speed of a highway is the speed at which or below a given percentage of drivers travel. For example, the 60th %ile speed is the speed at or below which 60% of

the drivers travel. i.e. a speed exceeded by 40% of the drivers.

In the UK, design speeds are usually the 85th percentile speed. For example for a design speed of 120km/h (Design speed of

Motorways), 85% of the drivers are expected to drive at or

below 120 km/h. Only about 15% of the drivers are expected

to exceed this speed (obviously illegally).

jAnalysis of Speed Data When tables of data are collated regarding the speed of vehicles on a road, a graphical representation of the data can then be drawn to analyse it and determine things such as the percentile speeds.

Mean, class intervals and standard deviation can also be calculated using mathematical methods

Sight Distances There are two main design sight distances:

Stopping sight distance (SSD)

Full overtaking sight distance (FOSD)

The SSD is worked out on the assumption that:

The driver eye level is within the range 1.5 - 2.0m above the ground

The driver can see an object 0.25m above the ground

Points to note:

SSD and FOSD are related to design speed and to the horizontal curve

radii.

FOSD only apply to single carriageways. Thus, there is no FOSD for

design speeds which do not allow for single carriageways (e.g. of

120km/h in UK)

Stopping sight distance

There are three components of SSD -

perception distance - distance travelled in the time taken to perceive the hazard

reaction distance - distance travelled in the time taken for the driver to apply the brakes and the brakes to come into effect

braking distance - distance travelled whilst the brakes are applied to bring the vehicle to a stop

Perception and reaction distances will vary from driver to driver depending on a number of things including their health, observation etc. For design purposes, perception time is taken a 2 seconds. For braking, deceleration of 0.25g is normally assumed.

The desirable minimum criteria is:

SSDd = 2 seconds + V/0.25g - where V is the design speed.

For absolute minimum criteria,

SSDa = 2 seconds + V’/0.25g - where V’ is the design speed one

step below V.

Full overtaking sight distance FOSD should be provided on sections specifically designed to permit overtaking.

An overtaking manouver:

Typically takes about 4 – 15 seconds

85% of manoeuvres

99% of manoeuvres

FOSD is considered to be made up of three components:

1. D1 – The distance travelled by the vehicle doing the overtaking

manoeuvre

2. D2 – The distance travelled by the on-coming vehicle from

opposite direction

3. D3 – The safety distance

FOSD = D1 + D2 + D3 where:

1. D3 = D2

/5

2. V = Design speed of road

3. V’’ Speed, two design speed steps lower than V

Assumptions

1. That the overtaking driver starts the manoeuvre two design speed

steps below the design speed (Distance D1).

2. That the overtaking driver then accelerates (normally assumed

uniform acceleration) to the design speed.

3. That the approaching vehicle travels a at the design speed (Distance

D2).

4. That the safety distance D3 = D2/5

With the above assumptions, FOSD = 2.05 × T × V (metres)

Where

T = Time to complete manoeuvre (secs);

V = Design speed (m/s)

Example: For the 85% of the manoeuvres, for a design speed of 100 km/h

(27.78 m/s), FOSD100 = 2.05 × 10 × 27.78

= 569.49 (metres)

Points of caution on FOSD

That the designer does not cause confusion in the driver’s mind as to

whether it is safe to overtake or not,

On sections of road designated for overtaking, sight distances are at

least the FOSD,

That there are no very long straight stretches of road which are boring

to the driver and encourage high speeds,

That where the section is not designated for overtaking, this fact is

apparent to all drivers – e.g. where it is not possible to provide FOSD,

sight distance should be restricted to not very greater than SSD.

Highway Capacity The capacity of a highway is the number of vehicles passing a given section or

road in a given period.

Although a vehicle only occupies a length of road equal to its length, its presence

means that a greater length of road is unavailable to any other vehicle.

In order that the road can be used safely, there must be a gap, called headway

(H), between one vehicle and the next.

Road space (S) utilised by a vehicle of length L is given by the equation:

S = L + H

If all vehicles are travelling at speed V m/s, the time (t) for vehicle A to travel

distance S is given by:

Speed = Distance/time Time (t) = Distance/Speed = S/V sec. = (L + H)/V secs

Layout Design Whether rural or urban, a highway from the designer’s viewpoint is made

up of two parts:

1. The road between junctions,

2. Junctions themselves.

In the entire design process, the designer has to face various challenges:

Areas of bad ground or suitable locations for bridges,

Meet required standards – sight distances, gradients, etc.,

Balance cut and fill areas

Face political constraints

Many more constraints

Alternative carriageway categories:

1. Normal single carriageway – S2

2. Wide single carriageway – WS2

3. Dual 2-lane all purpose carriageway, D2AP

4. Dual 3-lane all purpose carriageway, D3AP

5. Dual 2-lane motorway, D2M

6. Dual 3-lane motorway, D3M

7. Dual 4-lane motorway, D4M

In all these roads, the starting point for determining layout designs is the

forecast traffic flow measured as 24-hour AADT (Annual Average Daily

Traffic) at some time (typically the 15th year) after opening the road.

Information

Description
Degree level Surveying & Highway Design (Horizontal & vertical alignment design) Note on Horizontal and Vertical Alignment Design - Layout Design, created by rhiannonsian on 05/04/2015.
Created by
rhiannonsian
Views
4
Rating

More on Highway Geometric Design

Feedback

What is it about?

What should we add next?