IWA mock test: Individual Working Alone revision questions
Know where you stand before course day. Free 15-question check, every answer explained with its Rule Book rule, and no account for the first 5.
- topics covered, 280 explained questions
- 10
- timed mock questions to build stamina
- 30
- IWA certificate validity (per Seaton Rail)
- 2 years
Quick check
Unlock 110 more free questions
Make a free account to keep going. We save your score by topic, so you can pick up where you left off. Your answers so far are kept.
Already have an account? Sign in
How to prepare
-
See what to fix first Free
-
Build topic confidence Free account
-
15 questionsThe IWA role and competence Safe system of work for yourself, your certificate, your primary sponsor and Sentinel suspension.
-
19 questionsPlanning and the safe work pack Responsible Manager, Planner and person in charge, site familiarity and reviewing the pack.
-
34 questionsWalking alone, obstacles and crossing the line When you may walk on or near the line, authorised routes, the Crossing the Line procedure and positions of safety.
-
13 questionsWork without blocking the line Distances from the running rail, barriers and tape, warning equipment and the 10-second rule.
-
27 questionsWork that needs the line to be blocked What counts as affecting the safety of the line, and agreeing a safe system with a PC, ES or PICOS.
-
51 questionsBlocking a line (handbook 8) Planning, taking, using and handing back a line blockage yourself.
-
40 questionsWorking in possessions and sidings Handbook 9 possessions, work-site marker boards, detonator protection and PICOS rules in sidings.
-
21 questionsSafety-critical communication Giving and receiving safety-critical messages clearly and correctly.
-
25 questionsElectrified lines Working safely on or near electrified lines as an IWA.
-
35 questionsEmergencies, protecting the line and reporting Emergency protection of the line, what to do when something goes wrong and what to report.
-
-
Rail IWA Prep Pass
Walk in ready for the IWA
Start free to find your gaps. The Prep Pass gives you the practice to close them before exam day.
- All 280 questions across 10 topics
- Timed practice tests: 30 questions in 40 minutes
- Mistakes review: practise what you got wrong
- Your progress saved on phone and computer
-
Stop repeating mistakes Prep Pass
-
Strengthen your weakest topic Prep Pass
-
Practise under time pressure Prep Pass
IWA at a glance
The assessment
Course, theory and practical
Questions and time
Not published
Pass mark
Not published
Course length
3 days initial, 2 days recert
Valid for
2 years
Sample IWA questions
1. You are checking whether electrical equipment is isolated before working alone. What does ‘isolated’ mean?
- It is disconnected from one electrical supply and switched off.
- It is disconnected from all electrical supplies in a secure way.
- It is connected to a traction return running rail.
- It is separated from the nearest electrical supply temporarily.
Answer: B. It is disconnected from all electrical supplies in a secure way.
Electrical equipment is isolated when it is securely disconnected from all sources of electricity supply. Disconnection from just one source does not establish isolation.
- It is disconnected from one electrical supply and switched off: There may be other sources of supply.
- It is connected to a traction return running rail: Connection to a traction return rail describes earthing, not isolation.
- It is separated from the nearest electrical supply temporarily: Isolation requires secure disconnection from all sources, not just the nearest.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
2. You are arranging a line blockage and discuss additional protection with the signaller. What is its purpose?
- To warn you when a train is approaching the work location
- To identify where an engineering train can enter a possession
- To prevent a train being incorrectly allowed into the blocked portion of line
- To allow trains to pass through the blockage at reduced speed
Answer: C. To prevent a train being incorrectly allowed into the blocked portion of line
Additional protection is a separate, independent measure intended to prevent a train being incorrectly allowed into the blocked portion of line. It supports the primary protection rather than replacing it.
- To warn you when a train is approaching the work location: Additional protection is not a warning system for approaching trains.
- To identify where an engineering train can enter a possession: An intermediate point identifies where an engineering train can enter or leave a possession.
- To allow trains to pass through the blockage at reduced speed: Additional protection is intended to prevent an incorrect entry, not permit trains through.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
3. You plan to use netting between your work site and an open line where trains travel at 60 mph. How far from the line must the netting be?
- At least 0.9 metres
- At least 1.25 metres
- At least 3 metres
- At least 2 metres
Answer: D. At least 2 metres
At 60 mph, netting must be at least 2 metres from the open line. The minimum distance depends on the type of fence and the speed of trains.
- At least 0.9 metres: 0.9 metres is below the minimum distance.
- At least 1.25 metres: 1.25 metres applies to netting where trains travel at up to 40 mph.
- At least 3 metres: 3 metres is more than the stated minimum.
Source: Network Rail keypoint card: COSS, IWA, PC
4. You are planning to work alone at an unfamiliar location. What should you check about hazards at the site?
- Whether the nearest station has public access
- Whether the work can be completed in daylight
- Whether the location has limited clearances
- Whether the access gate has a company lock
Answer: C. Whether the location has limited clearances
You need to know whether the site has hazards such as limited clearances. This helps you plan a safe system of work for the location.
- Whether the nearest station has public access: Public access to a station does not establish whether the site has limited clearances.
- Whether the work can be completed in daylight: Daylight alone does not establish what hazards are present at the site.
- Whether the access gate has a company lock: The type of access-gate lock does not establish whether the site has limited clearances.
Source: Network Rail keypoint card: COSS, IWA, PC
5. You see a no refuges warning sign before a structure. Where are the positions of safety or refuges for its length?
- On the same side, beyond the sign
- On the opposite side of the railway line
- On both sides, within the structure
- On the same side, at the far end
Answer: B. On the opposite side of the railway line
A no refuges warning sign means there is no position of safety on that side for the length of the structure. Positions of safety or refuges are on the opposite side of the railway line.
- On the same side, beyond the sign: There is no position of safety on that side for the length of the structure.
- On both sides, within the structure: The sign does not indicate positions of safety on both sides.
- On the same side, at the far end: The sign identifies positions of safety or refuges on the opposite side.
Source: GERT8000-HB1 General duties and track safety for track workers (Iss 9, Limited clearance signs
6. Trains are running and you reach a prohibition sign. When may you pass beyond it?
- When walking to a planned work location
- When carrying out a routine inspection
- When you can see the line is clear
- When carrying out emergency protection
Answer: D. When carrying out emergency protection
You must not pass beyond the sign while trains are running unless you are carrying out emergency protection. This restriction applies because you could not safely reach a position of safety or refuge.
- When walking to a planned work location: A planned work location does not provide an exception.
- When carrying out a routine inspection: A routine inspection does not provide an exception.
- When you can see the line is clear: Seeing a clear line does not provide an exception.
Source: GERT8000-HB1 General duties and track safety for track workers (Iss 9, Limited clearance signs
7. Which warning system is operated by trains to warn track workers that a train is approaching?
- Automatic track warning system (ATWS)
- Semi-automatic track warning system (SATWS)
- Train-operated warning system (TOWS)
- Lookout-operated warning system (LOWS)
Answer: C. Train-operated warning system (TOWS)
TOWS is operated by trains and warns track workers of an approaching train. The systems have different methods of operation.
- Automatic track warning system (ATWS): ATWS is an automatic warning system.
- Semi-automatic track warning system (SATWS): SATWS has a warning that is cancelled manually.
- Lookout-operated warning system (LOWS): LOWS is operated by a lookout.
Source: GERT8000-HB1 General duties and track safety for track workers (Iss 9, Definitions
What changes, and when
Handbook 6 Issue 9 renames and changes section 3.2 to remove the ability to carry out patrolling, inspecting or examining duties without any safe system of work.
Handbook 9 Issue 10 removes the RT3199 signature, adds transient work sites and withdraws section 3.6 (equipment warning).
How these questions are made
Written from the official sources
Checked independently
Recertifying your IWA?
Seaton Rail says you can recertify within 8 weeks before or after your certificate expires. You need a logbook with 4 completed entries since your last assessment and 2 line manager reviews, and a workplace assessment follows at 9 to 15 months. Check these with your provider.
Retake rules after a fail are not published. Check the 5 December 2026 changes with your provider, then work on the topics where you score lowest here.
Frequently asked questions
What is the IWA?
IWA stands for Individual Working Alone. An IWA sets up a safe system of work for themselves so they can walk and work on or near the line alone on Network Rail managed infrastructure. An IWA never protects a group; that is the COSS.
How many questions are in the IWA test?
It is not published. No provider page gives a question count, format or time for the theory assessment. Our 30-question, 40-minute mock is our own, not the real length.
What is the IWA pass mark?
It is not published. Providers assess you against Network Rail's competence standard, which is not public. We suggest aiming for 80% or more in practice.
Who can take the IWA course?
You must be 18 or over and need to work alone on or near the line. You must already hold PTS, a Network Rail level 1 or 3 medical and drugs and alcohol certificate, have good English and have a primary sponsor.
How long is the IWA course?
Initial is 3 days at all three providers we checked, and recertification is 2 days. Seaton adds a day when combined with PTS recertification.
How long does an IWA certificate last?
Two years, according to Seaton Rail's course pages, with recertification within 8 weeks before or after expiry. Check with your provider.
How much does the IWA course cost?
Each provider sets its own fee. Examples: OLEC £400 initial and £250 recert; Fusion People £252 initial and £253 recert, each plus a £14 Sentinel fee in a 2024 listing.
Which Rule Book handbooks does the IWA cover?
Providers name Handbooks 6, 8 and 9, plus sidings under the PICOS (Handbook 13). Handbook 6 covers general duties of an IWA, 8 blocking a line and 9 possessions.