Exams · US
Security+ practice questions: Change management and cryptography
Approvals, maintenance windows, backout plans, public and private keys, key exchange.
Updated 12 November 2026 for the SY0-801 objectives
Key points
See all 19 key pointsA change advisory board (CAB) reviews proposed changes and advises on approval according to the organization’s change process.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Assign a change owner, identify stakeholders, and assess security and operational impacts before implementation.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Review test results, obtain required approval, and schedule implementation within an appropriate maintenance window.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Prepare a backout plan to restore the previous state if a change fails, or an approved fail-forward plan to correct it.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Assess changes to allow lists and deny lists for both unintended access and blocked legitimate activity.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Consider service or application restarts, downtime, legacy compatibility, and dependencies when planning a change.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
Update diagrams, policies, and procedures after changes, and use version control to track revisions and support restoration.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
A public key can be shared, while its corresponding private key must be protected; key escrow stores a key for authorized recovery.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.3 Explain the importance of using appropriate cryptographic solutions.
A certificate authority signs certificates that bind identities to public keys, and a certificate signing request supplies information needed to request a certificate.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.3 Explain the importance of using appropriate cryptographic solutions.
A CRL lists revoked certificates, while OCSP provides status information for an individual certificate.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.3 Explain the importance of using appropriate cryptographic solutions.
A wildcard certificate can cover multiple subdomains, while a self-signed certificate requires an independent trust decision because it lacks a trusted third-party signature.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.3 Explain the importance of using appropriate cryptographic solutions.
Symmetric encryption uses a shared secret key, whereas asymmetric encryption uses a public and private key pair.
CompTIA Security+ SY0-801 V8 Certification Exam Objectives, 1.3 Explain the importance of using appropriate cryptographic solutions.
Sample questions
1. Before updating a firewall, an analyst identifies the applications and users that could be affected. Which change management activity is the analyst performing?
- Impact analysis
- Backout planning
- Approval review
- Test validation
Answer: A. Impact analysis
SY0-801 objective 1.2 covers impact analysis, which identifies potential effects of a proposed change. Backout planning instead prepares a way to reverse the change.
- Backout planning: Backout planning prepares for reversing a change.
- Approval review: Approval review determines whether the change may proceed.
- Test validation: Test validation evaluates results from testing the change.
Source: CompTIA Security+ SY0-801 V8 Exam Objectives v2.0, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
2. A server update passes testing, but the team wants to prepare for an unexpected failure in production. What should the team document before deployment?
- The list of stakeholders to notify
- The results of the completed tests
- The steps to restore the prior configuration
- The schedule for the next review meeting
Answer: C. The steps to restore the prior configuration
SY0-801 objective 1.2 covers backout planning, including steps to restore the previous state if a change fails. Test results support the deployment decision but do not provide a recovery procedure.
- The list of stakeholders to notify: A stakeholder list supports communication, not restoration.
- The results of the completed tests: Test results do not describe how to reverse the change.
- The schedule for the next review meeting: A review schedule does not provide a recovery procedure.
Source: CompTIA Security+ SY0-801 V8 Exam Objectives v2.0, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
3. A proposed network change requires review by the change advisory board before deployment. What should the change owner obtain before proceeding?
- A new maintenance window for testing
- An updated list of system dependencies
- A completed postimplementation review
- Approval through the change process
Answer: D. Approval through the change process
SY0-801 objective 1.2 includes the CAB and the approval process. A postimplementation review occurs after deployment and does not replace the required approval.
- A new maintenance window for testing: A new window does not replace the required approval.
- An updated list of system dependencies: A dependency list informs review but is not approval.
- A completed postimplementation review: A postimplementation review follows deployment.
Source: CompTIA Security+ SY0-801 V8 Exam Objectives v2.0, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
4. An approved update will interrupt a service for 20 minutes. The team has a one-hour period reserved for service disruption and recovery. When should the team deploy the update?
- During the busiest operating period
- Immediately after the test results are filed
- After the maintenance window has closed
- During the reserved maintenance window
Answer: D. During the reserved maintenance window
SY0-801 objective 1.2 covers maintenance windows, which provide a scheduled period for work that may disrupt services. Filing test results supports readiness but does not establish an appropriate deployment time.
- During the busiest operating period: The busiest period can increase disruption to users.
- Immediately after the test results are filed: Filing test results does not establish an appropriate deployment time.
- After the maintenance window has closed: Deploying after the window misses the reserved period.
Source: CompTIA Security+ SY0-801 V8 Exam Objectives v2.0, 1.2 Given a scenario, demonstrate the impact of change management processes on security.
5. A hospital plans to upgrade a server library used by several applications, including an older scheduling system. What should the team assess before the upgrade?
- Whether the library's owner has changed departments
- Whether the server's asset tag follows naming policy
- Whether the scheduling system supports the new library
- Whether the scheduling system has a current user guide
Answer: C. Whether the scheduling system supports the new library
SY0-801 objective 1.2 includes legacy applications and dependencies as technical implications of change. The team should assess compatibility because an application may depend on the existing library; a current user guide does not establish compatibility.
- Whether the library's owner has changed departments: The owner's department does not establish application compatibility.
- Whether the server's asset tag follows naming policy: An asset tag does not establish application compatibility.
- Whether the scheduling system has a current user guide: A user guide alone does not establish compatibility with the new library.
Source: CompTIA Security+ SY0-801 V8 Exam Objectives v2.0, 1.2 Given a scenario, demonstrate the impact of change management processes on security.