Exams · US

PSM 1 practice test: Product Backlog, Sprint Backlog and their commitments

The artifacts, the Product Goal, the Sprint Goal and how each artifact is used.

20 questions · 18 key rules

Updated 12 November 2026 for the Scrum Guide November 2020

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Backlogs and goals1. A Product Owner wants estimates for several upcoming items. Who is responsible for sizing them?
    1. The Product Owner, with input from stakeholders
    2. The Scrum Master, with input from the Developers
    3. The Developers who will do the work
    4. The whole Scrum Team, with the Product Owner deciding
    Show answer and explanation

    Answer: C. The Developers who will do the work

    The Developers who will do the work are responsible for sizing. The Product Owner may help them understand and select trade-offs.

    Why the others are wrong

    • The Product Owner, with input from stakeholders: The Product Owner may influence sizing but is not responsible for it.
    • The Scrum Master, with input from the Developers: The Scrum Master is not assigned responsibility for sizing.
    • The whole Scrum Team, with the Product Owner deciding: Sizing is the responsibility of the Developers who will do the work.

    Source: The Scrum Guide (November 2020, Product Backlog

  2. Backlogs and goals2. A team is discussing how to refine its Product Backlog. Which two statements describe refinement? Choose two.
    1. It is an ongoing activity that can add details to items.
    2. It is completed only during Sprint Planning.
    3. It breaks down and further defines items into smaller, more precise items.
    4. It requires every item to have the same attributes.
    Show answer and explanation

    Answer: A. It is an ongoing activity that can add details to items., C. It breaks down and further defines items into smaller, more precise items.

    Refinement is ongoing and makes items smaller and more precise. It can add details such as a description, order, and size.

    Why the others are wrong

    • It is completed only during Sprint Planning: Refinement is ongoing, not limited to Sprint Planning.
    • It requires every item to have the same attributes: Item attributes often vary with the domain of work.

    Source: The Scrum Guide (November 2020, Product Backlog

  3. Backlogs and goals3. A Product Backlog item has been refined. When is it deemed ready for selection in Sprint Planning?
    1. When the Product Owner has assigned it to a Developer
    2. When its size is smaller than every other item
    3. When stakeholders have approved its release date
    4. When the Scrum Team can complete it within one Sprint
    Show answer and explanation

    Answer: D. When the Scrum Team can complete it within one Sprint

    An item is deemed ready for selection when the Scrum Team can get it Done within one Sprint. Refinement usually gives items the transparency needed to reach that point.

    Why the others are wrong

    • When the Product Owner has assigned it to a Developer: Readiness does not require assignment to a Developer.
    • When its size is smaller than every other item: Readiness depends on whether the item can be Done within one Sprint, not its relative size.
    • When stakeholders have approved its release date: Stakeholder approval of a release date is not the stated readiness criterion.

    Source: The Scrum Guide (November 2020, Product Backlog

  4. Backlogs and goals4. Which description best fits the Product Backlog?
    1. A fixed plan of tasks assigned for the current Sprint
    2. An emergent, ordered list of what is needed to improve the product
    3. A record of all completed work released to customers
    4. An unordered list of requests owned by stakeholders
    Show answer and explanation

    Answer: B. An emergent, ordered list of what is needed to improve the product

    The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team.

    Why the others are wrong

    • A fixed plan of tasks assigned for the current Sprint: The Product Backlog is emergent and is not a fixed Sprint task plan.
    • A record of all completed work released to customers: It identifies needed product improvements rather than recording only completed releases.
    • An unordered list of requests owned by stakeholders: The Product Backlog is ordered, not an unordered list.

    Source: The Scrum Guide (November 2020, Product Backlog

  5. Backlogs and goals5. Which three elements make up the Sprint Backlog?
    1. The Product Goal, release plan, and Definition of Done
    2. The Sprint Goal, stakeholder requests, and release schedule
    3. The Sprint Goal, selected Product Backlog items, and delivery plan
    4. The Product Goal, selected requirements, and improvement plan
    Show answer and explanation

    Answer: C. The Sprint Goal, selected Product Backlog items, and delivery plan

    The Sprint Backlog contains the Sprint Goal, the selected Product Backlog items, and an actionable plan for delivering the Increment. Together, they describe why, what, and how for the Sprint.

    Why the others are wrong

    • The Product Goal, release plan, and Definition of Done: The Product Goal, release plan, and Definition of Done are not the three elements of the Sprint Backlog.
    • The Sprint Goal, stakeholder requests, and release schedule: Stakeholder requests and a release schedule are not the specified elements of the Sprint Backlog.
    • The Product Goal, selected requirements, and improvement plan: The Product Goal and an improvement plan do not replace the Sprint Goal and delivery plan.

    Source: The Scrum Guide (November 2020, Sprint Backlog

Sign up free

Other PSM I topics

GoConqr Original. Practice questions written with AI from the Scrum Guide 2020 and the Scrum.org PSM I focus areas, each checked against the source it cites. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with Scrum.org or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?