  1. Scrum Team1. Which accountabilities make up a Scrum Team?
    1. One Scrum Master, one Product Owner, and Developers
    2. One Scrum Master, several Product Owners, and Developers
    3. One Product Owner, one team lead, and Developers
    4. One Scrum Master, one Product Owner, and project managers
    Show answer and explanation

    Answer: A. One Scrum Master, one Product Owner, and Developers

    A Scrum Team consists of one Scrum Master, one Product Owner, and Developers. These are the three accountabilities defined within the team.

    Why the others are wrong

    • One Scrum Master, several Product Owners, and Developers: A Scrum Team has one Product Owner, not several.
    • One Product Owner, one team lead, and Developers: A team lead is not one of the three Scrum accountabilities.
    • One Scrum Master, one Product Owner, and project managers: Developers, not project managers, are one of the three accountabilities.

    Source: The Scrum Guide (November 2020, Scrum Team

  2. Scrum Team2. A large Scrum Team reorganizes into several Scrum Teams focused on the same product. Which two things should the teams share? Choose two.
    1. The same Product Backlog
    2. The same Scrum Master
    3. The same Product Goal
    4. The same Sprint Backlog
    Show answer and explanation

    Answer: A. The same Product Backlog, C. The same Product Goal

    Scrum Teams working on the same product should share the same Product Goal, Product Backlog, and Product Owner. This helps the teams focus on the same product.

    Why the others are wrong

    • The same Scrum Master: Sharing a Scrum Master is not listed as a requirement for these teams.
    • The same Sprint Backlog: Sharing a Sprint Backlog is not listed as a requirement for these teams.

    Source: The Scrum Guide (November 2020, Scrum Team

  3. Scrum Team3. A team produces a useful Increment, but its value is questioned. Who is accountable for creating a valuable, useful Increment every Sprint?
    1. The Developers alone
    2. The entire Scrum Team
    3. The Product Owner alone
    4. The Scrum Master alone
    Show answer and explanation

    Answer: B. The entire Scrum Team

    The entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint. This accountability is shared across the team.

    Why the others are wrong

    • The Developers alone: The accountability belongs to the entire Scrum Team, not only the Developers.
    • The Product Owner alone: The accountability belongs to the entire Scrum Team, not only the Product Owner.
    • The Scrum Master alone: The accountability belongs to the entire Scrum Team, not only the Scrum Master.

    Source: The Scrum Guide (November 2020, Scrum Team

  4. Scrum Team4. A Scrum Team needs a plan for the Sprint. Who is accountable for creating the Sprint Backlog?
    1. The Scrum Master
    2. The Product Owner
    3. The stakeholders
    4. The Developers
    Show answer and explanation

    Answer: D. The Developers

    The Developers are accountable for creating the Sprint Backlog as a plan for the Sprint. This makes the plan a Developer accountability.

    Why the others are wrong

    • The Scrum Master: The Scrum Master is not accountable for creating the Sprint Backlog.
    • The Product Owner: The Product Owner is not accountable for creating the Sprint Backlog.
    • The stakeholders: Stakeholders are not accountable for creating the Sprint Backlog.

    Source: The Scrum Guide (November 2020, Developers

  5. Scrum Team5. A team wants to ensure its work meets its quality standard. What are the Developers accountable for doing?
    1. Creating a separate quality team
    2. Asking stakeholders to set daily quality checks
    3. Adhering to a Definition of Done
    4. Leaving quality decisions until the Sprint ends
    Show answer and explanation

    Answer: C. Adhering to a Definition of Done

    Developers are accountable for instilling quality by adhering to a Definition of Done. Quality is part of their work throughout the Sprint.

    Why the others are wrong

    • Creating a separate quality team: A separate quality team is not the stated Developer accountability.
    • Asking stakeholders to set daily quality checks: Stakeholders setting daily checks is not the stated Developer accountability.
    • Leaving quality decisions until the Sprint ends: Waiting until the Sprint ends does not fulfill the accountability to adhere to a Definition of Done.

    Source: The Scrum Guide (November 2020, Developers

Sign up free

Other PSM I topics

GoConqr Original. Practice questions written with AI from the Scrum Guide 2020 and the Scrum.org PSM I focus areas, each checked against the source it cites. Think a question is wrong? Use "Report" under it.

Independent study resource. Not affiliated with Scrum.org or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?