Lindsey Maycock EIA Year 1 English 35 cards

Cards in this deck (35)

  1. 1What are the 12 stages of EIA?1. Screening
    2. Scoping
    3. Public participation
    4. Describe the development
    5. Establish baseline
    6. Identify key impacts
    6 7. Impact prediction
    8. Evaluate impact significance
    9. Determine mitigation measures
    10. Decision making
    11. Review EIS
    12. Monitor and follow-up
  2. 2What are the possible outcomes of decision making?Accept action
    Accept action with modifications
    Accept alternative version of action
    Action rejection
  3. 3What are the elements of monitoring and follow-up?- before the project for baseline data and after to monitor the impact.
    - Evaluation of conformance with standards
    - Management on actions that arise from monitoring and evaluation
    - Communication to stakeholders about the results
  4. 4What are the levels of ecology?1. Organism
    2. Population
    3. Community
    4. Ecosystem
  5. 5What are the effects of offshore wind during construction, operation and decommission?Vessel noise and disturbance. Prey change, habitat removal. collision with birds and barrier to bird movement
  6. 6What are the two types of cumulative effects?Additive
    Synergistic (effects are more than the sum of their parts)
    Antagonistic - neutralise effect
  7. 7What is the case for the Rochdale envelope?Increased flexibility in caselaw where uncertainties exist such as the exact length of a road. A conceptual boundary is drawn. It avoids salami-slicing
  8. 8What is a potential positive impact for biodiversity of solar energy?Provides shade for animals (full effect is yet to be understood)
  9. 9What is the purpose of an objection of a project from NatureScot?To notify the Scottish Government if a local authority is going against their objections
  10. 10What proportion of Scotland's land cover is peat?One quarter
  11. 11What are the top two layers of peat?Acrotelm - living plant matter
    Catotelm - dead plant matter
  12. 12What is NEPA?National Environmental Policy Act
  13. 13What are the design stages of a project?1. Inception
    2. Feasibility
    3. Proposal outline
    4. Detailed design
    5. Production information
    6. Operations on site
  14. 14What are the five levels of public participation?1. Inform
    2. Consult
    3. Involve
    4. Collaborate
    5. Empower
  15. 15What are the different types of alternatives in SEA?1. Continue with present plans
    2. Obviate plans
    3. Reduce demand of materials
    4. Different location approach
    5. Different types of development (eg. wind instead of coal)
    6. Fiscal measures
    7. Different forms of management
  16. 16What are the three consultation authorities in Scotland?NatureScot
    SEPA
    Historic Environment Scotland (HES)
  17. 17What are some of the factors that determine impact significance?Severity, spatial, reversibility, probability, number of people affected, sensitivity of affected environment, designated sites, capacity levels and sustainability, equity, public opinion, regulation
  18. 18What are the measures used to mitigate bird collision on wind farms?Adjusting height of turbines to a level the birds don't fly at. Having turbines more spaced out
  19. 19What are the challenges of a cumulative impact assessment?Shifting baselines due to past projects, uncertainty of the impact of current projects, not knowing what the future projects will be
  20. 20What are the five models of offshore wind turbines?Monopile, suction monopile, gravity base, jacket, tripet
  21. 21What are the benefits of town and country planning?Reduces conflict between people, communities, developers and the environment. Gives better protection to nature. Development will work in the interest of the community.
  22. 22What decade was EIA implemented to the UK?90s
  23. 23What is the main environmental impact of hydro energy?It disrupts fish migratory patterns, takes a lot of resources to set up
  24. 24What will be needed as part of the national planning frameowrk on a much wider scale in Scotland for renewables to reach their full potential?Grid reinforcements
  25. 25What can be done to avoid offences against NatureScot's advice?Good timing, good working practice, retaining certain areas and structures that are important to wildlife
  26. 26What proportion of global organic carbon stores is held by peat bog?A third
  27. 27What was the US policy act that encouraged the rest of the world to adopt EIA?NEPA
  28. 28What is an environmental outcome report?A more condensed version of EIA that is used to fit within timing of decision making
  29. 29What are the 10 problems of EIA implementation?1. EIA requirements might be avoided (eg. by salami-slicing or for political reasons)
    2. EIA might not ensure environmentally sound projects
    3. EIA might not be carefully integrated into planning
    4. Cumalitive impacts might not be considered
    5. Public participation in EIA might be inadequate
    6. Proposed mitigations might not be implemented
    7. Post project monitoring might not be conducted
    8. Assesment of risk might be absent from EIA
    9. Assesments of social impacts might be absent
    10. Impact assessment might not consider alternatives
  30. 30What is an Environmental Management Plan (EPM)?A site specific plan to ensure all legislation and mitigation measures are complied with and how to manage harm
  31. 31What is the role of public participation in EIA?To ensure public views have been adequately considered and the report is accessible and comprehensive
  32. 32What would guidance or inspiration on what actions to take (such as whether or not to build a new road) fall under: Policy, Plan or Programme?Policy
  33. 33When is Rochdale envelope used?When details of a project haven't been confirmed after a planning application has been submitted
  34. 34What are the 14 IAIA basic principles?1. Purposive 2. Practical 3. Relevant 4. Cost-effective 5. Efficient 6. Participative
    7. Transparent 8. Integrated 9. Systematic 10. Focused 11. Adaptive
    12. Interdisciplinary 13. Rigorous
    14. Credible
  35. 35What are the 10 IAIA operating principles?1. Screening 2. Scoping 3. Examination of alternatives 4. Impact analysis 5. Mitigation and impact management 6. Evaluation of significance 7. Preparation of EIS or report 8. Review of EIS 9. Decision making
    10. Follow-up

Information

Description
Year 1 EIA Flashcards on EIA exam, created by Lindsey Maycock on 19/04/2023.