  1. Engineer to set out edges of SCCP supports

  2. Drill holes using relevant plywood template

  3. Clean holes to allow engineer to survey

  4. HOLD: Engineer to survey holes

  5. If level okay, scabble substrate

  6. If level too high, plane then scabble substrate

  7. Install formwork box

  8. HOLD: Engineer to check substrate levels

  9. HOLD: Engineer to check substrate levels

  10. HOLD: Engineer to check anchor design

  11. If anchor design not okay stop work

  12. HOLD: Check weather forecast

  13. If too windy to lift stop works

  14. Clean substrate surface and all holes

  15. HOLD: Engineer/NNB to inspect substrate

  16. If not okay, perform remedials

  17. Engineer to level shims

  18. Lift support onto shims

  19. Dry place anchors

  20. HOLD: Engineer to check anchor depths

  21. If not okay, engineer to advise remedials

  22. HOLD: Engineer to check support position

  23. If not okay, adjust position

  24. Check if holes contain ponded water

  25. Resin in anchor bolts. Tighten nuts after period advised.

  26. HOLD: Engineer to confirm date of grouting / book lab technician

  27. HOLD: Engineer to advise whether curing tent required

  28. Fixers to erect curing tent

  29. If so, hoover

  30. Grout supports

  31. Deploy thermal blankets if required

  32. Cure grout

  33. Cut off anchor tops

Information

Description
Flowchart on Untitled, created by William Winder on 11/11/2019.
Created by
William Winder
Views
0
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?