Bond Testing

  1. Special Equipment Required

    • Meter and two cables
    • Ohmeter/Milliohmmeter
    • 1.2V nickel-alkaline source
    • Test cables are 60ft and 6ft in length
      • 60ft cable has a single spike probe
      • 6ft cable has a double spike probe
  2. Method One

    • 60ft cable connected to main earth of the aircraft
      • Refer to AMM for location
    • 6FT cable connected to the points specified in the boding test schedule or AMM
    • Meter gives a reading ohms giving an indication of the resistance of the bond
  3. Method Two

    • Test leads in form of duplex spikes/single spikes/crocodile type leads
    • Carry out pre-use check by placing all 4 terminals on a low resistance conductor - meter should indicate zero
    • May be necessary to penetrate conductive coating
    • Current is passed through the resistance
    • Voltage drop across resistance is measured and compared with current flowing
    • If higher reading is obtained
      • Bonding connection should be removed and cleaned
      • Connection refitted and sealed
      • Redo bonding test
      • If required bond value can't be obtained, seek advice from manufacturer
  4. Pre-use Checks

    • Full scale deflection of the meter is obtained when two spikes of the 6ft probe are shortened
    • Meter reads zero when the two spikes of the 6ft probe are shorted by the single spike of the 60ft probe

Information

Description
Aeronautical Engineering (EWIS Mindmaps) Mind Map on Bond Testing, created by Kenzie Evans on 05/09/2017.
Created by
Kenzie Evans
Views
0
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?