SAB2 #31 Perform Integrated Change Control
- Detailed in pp 154 of RMC
Make only the changes that are right for your project but you need to get your changes approved by the change control board
- Evaluate the impact (Always first)
- Identify Options
- Get the change request approved internally
- Get customer buy in if required
Project Management plan
Work performance reports
Change requests
Enterprise environmental factors
Meetings
Expert judgment
Change control tools
After Perform Integrated Change Control, we go back to the Direct and Manage Project Work process to put the approved changes in place.
Approved change requests
Project Management plan updates
Change log (All changes, even the ones that don’t get approved, are written in the change log)
Project document updates
Images and files in the map
Information
- Description
- Mind Map on SAB2 #31 Perform Integrated Change Control, created by luisenrique.vega on 02/08/2014.
- Created by
- luisenrique.vega
- Views
- 31
- Rating
More on Project Execution, Monitoring and Control