  1. Se ha gastado $2,625,000. El proyecto lleva 70% completado. Cual es la nueva predicción del proyecto?
    1. El Proyecto tiene 9 meses, el total del presupuesto es $4,200,000. Se ha gastado $1,650,000. Se tiene un CPI de 0.875.
      1. EAC=BAC/CPI=4200000/0.875=$4,800,000

        Annotations:

        • EAC=Estimate at Completion EAC = BAC/CPI EAC = DT/SPI
        1. ETC=EAC-AC=4800000-1650000=$3,150,000

          Annotations:

          • ETC=Estimate to Complete ETC= EAC - AC ETC= EAC - AT
          1. VAC=BAC-EAC=4200000-4800000=$-600,000

            Annotations:

            • VAC=Variance at Completion VAC=BAC-EAC
            1. DT= 9

              Annotations:

              • DT=Duration Total
              1. BAC=4,200,000

                Annotations:

                • BAC=Budget at Completion
                1. AC= 1,650,000

                  Annotations:

                  • AC= Actual Cost
                  1. CPI= 0.875

                    Annotations:

                    • CPI=Cost Performance index => 1. --- Good <1. --- Bad
                    1. EV=CPI*AC=1650000*0.875=1,443,750
                  2. BAC = 4,200,000

                    Annotations:

                    • BAC=Budget at Completion
                    1. EV=%C*BAC=0.7*4200000=2,940,000

                      Annotations:

                      • EV=Earned Value
                      1. EAC=BAC/CPI= 4,200,000/1.12=3,750,000

                        Annotations:

                        • EAC=Estimation at Complete EAC=BAC/CPI
                        1. AC= 2,625,000

                          Annotations:

                          • AC= Actual Cost
                          1. CPI= EV/AC=2,940,000/2,625,000=1.12

                            Annotations:

                            • CPI= Cost Performance Index CPI= EV/AC => 1  Good < 1 Bad
                            1. VAC=BAC-EAC= 4,200,00-3,750,000= 450,000

                              Annotations:

                              • VAC= Variance at Completion
                              1. Under Budget ?

                                Annotations:

                                • Under Budget Por 450,000
                                1. Over Budget ?
                                  1. ETC= EAC-AC= 3,750,000-2,625,000=1,125,000

                                    Annotations:

                                    • ETC= Estimation to Complete ETC= EAC-AC
                                    Show full summary Hide full summary

                                    Similar

                                    Sociology Key Words
                                    kazoakley
                                    GCSE Biology heart notes
                                    Kamila Woloszyn
                                    Spanish Subjunctive
                                    MrAbels
                                    AQA Physics P1 Quiz
                                    Bella Statham
                                    Biology - the digestive system
                                    Oliviax
                                    Regular Verbs Spanish
                                    Oliver Hall
                                    Flame tests
                                    Joshua Rees
                                    regular preterite tense conjugation -ar verbs
                                    Pamela Dentler
                                    Blood MCQs Physiology PMU 2nd Year
                                    Med Student
                                    Core 1.10 Polymers (Plastics)
                                    T Andrews
                                    Účto Fífa 2/6
                                    Bára Drahošová