By: Eliyahu M. Goldratt in the 1980s.
DBR
- CCR Active
- 3 Buffers
- A shipping buffer
- An assembly buffer
- A CCR buffer
- 3 Buffers
- No CCR is Active
- There's no reason why all the firm orders shouldn't be delivered on time.
- The "buffer" is a liberal estimate of the lead-time
- The “drum”, which is really the master production schedule (MPS).
- Rope: Once a shipping buffer is determined, a material release schedule (MRS) is generated
- There's no reason why all the firm orders shouldn't be delivered on time.
- Strives to achieve the following
- Very reliable due-date performance
- Effective exploitation of the constraint
- As short response time as possiblpossible, within the limitations imposed by the constraint(s).
- The traditional DBR model is designed to regulate the flow of work-in-process (WIP) through a production line at or near the full capacity of the most restricted resource in the manufacturing chain.
- CCR Active
S-DBR
- To apply S-DBR, we begin with the presumption that the company is not currently constrained by any internal resource. In other words, the market is most often the overarching constraint for most companies
- The Control Part of S-DBR
- red-line
- Planned load is the total time (in hours) required of the CCR to complete all work that has been formally released into the system, but which has not yet been processed at the CCR.
- red-line
- Basic Assumption No. 1:
- The market dictates certain requirements that a company must meet. Otherwise, demand for the company's product or service will diminish, and perhaps vanish completely in the future. These requirements imposed by the market sometimes conflict with full exploitation of an internal constraint (CCR).
- Basic Assumption No. 2:
- A small change to the actual processing sequence at an internal constraint does NOT have much impact on overall system performance.
The S-DBR global approach, including the financial, marketing and purchasing approach has been exhaustively tested using the Management Interactive Case Study Simulator (MICSS).
- The purpose of the MICSS is to demonstrate the feasibility of SDBR methodology in a semi-complex environment with uncertain market demand, a high level of "Murphy" in operations, and unreliable vendors.