CL 2 . Contract

Construction Stage

Insurance/warranty

CL 74 . Dispute Resolution

CL 2.1 Priority of contract & errors & discrepancies

1) AOA 2) Letter of confirmation 3) LOA 4) COC 5) APP1, 5,11,12,13 of COC 6)ER 7) Pricing Doc 8) Ref.Design 9)other doc in contract

CL.8 Possesion of site and access

CL 42. Date for line Completion

CL 44. Procedure for Extension of Time

CL 47. Liquidated and Ascertained Damages for Delay

CL 51B Line Completion

CL 49 Testing and Commisioning

CL 53 Defects Liability

CL 57 Variation

CL 60A Advance Payment

CL 60 Provisional Sums

CL 61 Contract Sum

CL 62 Certificates & Payment

CL 73. Procedure for Claims

CL 14. Sub-Contracting

CL 87 Key Dates

CL 47A Sectional Completion

CL 53.6 CMGD

CL 53.1 DLP

CL 62.4 Statements of Final Account & Final Certificates

CL 62.5 Release Retention

CL 62.2 Interim Certificate & Payment

CL 87.3 Cert. of Achievement of Key Event

CL 2B TC warranty & indemnity to E

CL 12 Performance Security

CL 14.3 Sub Contractor's Warranties

12.1 Performance Bond

12.3 Design Guarantee Bond

12.4 Parent Co. Guarantee

CL 74.2 Dispute Adjudication Board (DAB)

CL 74.4 Arbitration

Information

Description
Note on Gist for COC -KVMRT3 - created from Mind Map, created by esa zarina on 19/12/2017.
Created by
esa zarina · Dec 2017
Updated
Dec 19, 2017
Views
5
History
  • Created by esa zarina · Dec 19, 2017
  • Copied to Note by esa zarina · Dec 19, 2017
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?