  1. Slide 1

    • Process: Define Activities
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create an activity list from each work package
  2. Slide 2

    • Process: Sequence Activities
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create a network diagram
  3. Slide 3

    • Process: Plan Procurement Management
    • Knowledge Area: Procurement Management
    • Process Group: Planning
    • What Does It Mean? Create the procurement statement of work, procurement strategy, bid documents, and the procurement management plan
  4. Slide 4

    • Process: Develop Project Management Plan
    • Knowledge Area: Integration Management
    • Process Group: Planning
    • What Does It Mean? Create a project management plan that is bought into, approved, realistic, and formal
  5. Slide 5

    • Process: Collect Requirements
    • Knowledge Area: Scope Management
    • Process Group: Planning
    • What Does It Mean? Finalize and document detailed requirements and determine how they will be managed
  6. Slide 6

    • Process: Direct and Manage Project Work
    • Knowledge Area: Integration Management
    • Process Group: Executing
    • What Does It Mean? Produce work according to the project management plan (also called deliverables); create an issue log to track and record issues that have the potential to impact the project
  7. Slide 7

    • Process: Develop Schedule
    • Knowledge Area: Schedule Management
    • Process Group: Planning
    • What Does It Mean? Create a bought into, approved, realistic, and formal project schedule and schedule baseline
  8. Slide 8

    • Process: Perform Qualitative Risk Analysis
    • Knowledge Area: Risk Management
    • Process Group: Planning
    • What Does It Mean? Analyze the probability and impact of potential risks to determine which risks might warrant a response or further analysis
  9. Slide 9

    • Process: Define Scope
    • Knowledge Area: Scope Management
    • Process Group: Planning
    • What Does It Mean? Create the project scope statement
  10. Slide 10

    • Process: Validate Scope
    • Knowledge Area: Scope Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Meet with the customer to gain formal acceptance of interim deliverables
  11. Slide 11

    • Process: Identify Stakeholders
    • Knowledge Area: Stakeholder Management
    • Process Group: Initiating
    • What Does It Mean? Identify and document information (in the stakeholder register) about the stakeholders on the project
  12. Slide 12

    • Process: Conduct Procurements
    • Knowledge Area: Procurement Management
    • Process Group: Executing
    • What Does It Mean? Select a seller based on the seller responses and obtain a signed contract
  13. Slide 13

    • Process: Monitor and Control Project Work
    • Knowledge Area: Integration Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Measure performance against the project management plan; change requests may be a result of this comparison
  14. Slide 14

    • Process: Perform Integrated Change Control
    • Knowledge Area: Integration Management
    • Process Group: Monitoring and controlling
    • What Does It Mean? Evaluate the impact of change to the project and approve, reject, or defer change requests

Information

Description
Slide Set on Process review, created by Karolina Dubauskas on 06/03/2021.
Created by
Karolina Dubauskas · Mar 2021
Updated
Mar 7, 2021
Views
3
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?