Business Case
Content of the notes (18)
Page 1
Purpose of Business Case Theme
The purpose of the Business Case theme is to establish mechanisms
to judge whether the project is (and remains) desirable, viable and achievable
as a means to support decision making in its (continued) investment.
It is a PRINCE2 principle that a project must have continued business justification.
The business justification is the reason for the project. Without it no project should start. If business justification is valid at the start of a project, but disappears once it is under way, the project should be stopped or changed.
The ongoing and ever-present decision regarding the Business Case is whether the project can (still) be justified. This is based on whether the project is desirable (the cost/benefit/risk balance), viable (the project can deliver the products) and achievable (the products can provide the benefits).
The
Senior User(s) is responsible for specifying the benefits and subsequently
realizing the benefits through the use of the products provided by the project.
The
Executive is responsible for ensuring that those benefits specified by the
Senior User(s) represent value for money, are aligned to corporate objectives,
and are capable of being realized.
Page 2
What is a Business Case?
The Business Case presents the optimum mix of information
used to judge whether the project is (and remains) desirable, viable and
achievable, and therefore worthwhile investing in.
Outputs, outcomes and benefits
A
project’s output is
any of the project’s specialist products (whether tangible or intangible)
An
outcome is the
result of the change derived from using the project’s outputs
A
benefit is
the measurable improvement resulting from an outcome that is perceived as an
advantage by one or more stakeholders.
Page 3
3 questions to explain Output, Outcome and Benefits.
Question to uncover Output: What is the product that will be delivered by the project?
Question to uncover Outcome: What can the users do better with this product?
Question to uncover Benefits: List the measurable improvements of using this product.
Outputs: The
Outputs of a project are the products that the users will use. These are also
known as specialist products and the project is set up to create these
products.
Outcome: You may
have heard the expression “outcome is a result of change.” From a PRINCE2
project point of view, we say that an Outcome is the result of the change
derived from using the project's outputs. Outcomes describe what users can do
better, e.g., faster reporting.
Benefits: PRINCE2
says that Benefits are the measurable improvements, resulting from an outcome
that is perceived as an advantage by one of the stakeholders. Try to see
Benefits as the measurable advantages of using the product. Benefits can be
realized during the project, but most benefits are usually realized after the
project has closed and sometimes a long time after.
Page 4
The PRINCE2 approach to the Business Case
In PRINCE2, the Business Case is developed at
the beginning of the project and maintained throughout
the life of the project, being formally verified by the Project
Board at each key decision point, such as end stage assessments, and confirmed throughout the period that the benefits accrue.
Develop means
getting the right information upon which decisions can be made
Verify means
assessing whether the project is (still) worthwhile
Maintain means
to update the Business Case with actual costs and benefits and current forecasts
for costs and benefits
Confirm means
assessing whether the intended benefits have been (or will be) realized. Confirming
benefits will mostly take place post project.
Page 5
Develop Business Case
In
PRINCE2 the Executive is responsible for the Business Case. It does not
necessarily mean that the Executive writes the Business Case, merely that the
Executive is responsible for ensuring that the Business Case is written and
approved.
Development
of the Business Case may be delegated, for example, to a business analyst or perhaps
even to the Project Manager. In some cases, program management will provide
an approved Business Case as part of the Project Brief.
The
outline Business Case is derived from the project mandate and developed
pre-project in the Starting up a Project process in order to gain approval by
the Project Board in the Directing a Project process to initiate the project.
The
detailed Business Case is derived from the outline Business Case, the Project
Plan (costs, timescale, products) and the Risk Register. Due to the inputs
required to develop a Business Case, its development will be iterative.
Page 6
Develop Business Case - Cont
Page 7
Develop Business Case Cont
Page 8
Verify Business Case
What does verify the Business Case mean?
It means to determine whether the Business Case is
worthwhile.
This verification is done at a number of points in the
project by the Project Board
Project Board
verification points
Verification
Point 1: At the end
of the “Starting Up a Project” (Pre-Project) process.
Verification
Point 2: At the end
of the Initiation Stage
Verification
Point 3: At the
start of each new delivery stage.
At the end of the Starting up a Project process by the Project
Board in order to authorize project initiation based on a reasonable justification
At the end of the Initiating a Project process by the
Project Board in order to authorize the project
As part of any impact assessment by the Project Manager of
any new or revised issues or risks
In tandem with an Exception Plan by the Project Board, in
order to authorize the revised stage and the continuation of the project
At the end of each stage by the Project Manager to determine
whether any of the costs, timescales, risks or benefits need to be updated
At the end of each stage by the Project Board, to authorize
the next stage and the continuation of the project
During the final stage by the Project Manager, to assess the
project’s performance against its requirements and the likelihood that the outcomes
will provide the expected benefits
As part of the benefits review (possibly by corporate or
program management), to determine the success of the project outcomes in
realizing their benefits.
Page 9
Verify Business Case - Cont....
Page 10
Maintain the Business Case
Maintain the Business Case refers to keeping the Business
Case up to date (living document) to reflect what is happening in the project.
It may be done when assessing Risks or Issues, or at the end of a stage. For
example, some of the typical changes can be an increase or reduction in cost,
new information on a risk, etc.
So, when is a good time to update the Business Case during
the project? A good time to update the Business Case is at the end of every
stage, as you will have the true cost of the last stage, and perhaps even the
updated cost of the next stage, along with any information on issues and risks.
Page 11
Confirm the Benefits
Identify the benefits
Select objective
measures that reliably prove the benefits
Collect the baseline
measures (from which the improvements will be quantified)
Decide how, when and
by whom the benefit measures will be collected.
Page 12
The Benefits Review Plan
The purpose of the Benefits Review Plan is to identify the benefits and most importantly, to select how the benefits can be measured. In other words, the Benefits Review Plan is used to plan the assessment of benefits. You can then compare the new results to the current situation, so the current situation becomes the baseline.
So the purpose of the Benefits Review
Plan is to:
Define clearly how to measure the
benefits
Define the activities required to
measure the expected project's benefits
The Benefits Review Plan must include information on the expected timeline for these benefits. The Project Manager creates it in the Initiation Stage. The Senior User is responsible for specifying the benefits and realizing the benefits.
The Senior User represents the users who are asking for a new product so they should be able to describe the expected benefits. These benefit descriptions should show that the project is value for money (worth the investment).The Senior User is then responsible for using the product to achieve the benefits, and they become more accountable to the Corporate or Program Environment. This will also ensure their continued commitment during and after the project.
Page 13
Business Review Plan
1) Created by Project Manager in the Initiation stage
2) Information is provided by the Senior User
3) Project Board approves the Benefits Review Plan
4) Check the realised benefits at the end of each stage
5) Plan the Benefits Review after the project (post project)
6) Check for realised benefits (post project)
Page 14
Business Case
Page 15
Who is Responsible for What
Page 16
Master Business Case Theme In 27 Minutes
https://www.youtube.com/watch?v=ou6MIIIicOQ (Embed)
Page 17
Page 18
Information
- Description
- Certificate Prince 2 (Theme 1 - Business Case) Note on Business Case, created by Salman Khalid on 29/04/2016.
- Created by
- Salman Khalid · Apr 2016
- Updated
- May 2, 2016
- Views
- 14
- Rating