Questions in this quiz (34)

  1. 1How can the success of the project be evaluated? (choose 2 answers)
    1. AImproved KPIs through frequent releases
    2. BIncreased customer satisfaction
    3. CDelivering an Increment every Sprint
    4. DLower production cost
    5. EIncreased velocity
  2. 2The Product Owner is using burn-up charts instead of burn-down charts. What would be your response as the Scrum Master?
    1. AThere's nothing wrong with it.
    2. BBurn-up charts are used in traditional methods and should be replaced by burn-down charts.
  3. 3How should developers deal with non-functional features?
    1. AIncorporate them info every Increment
    2. BIncorporate them before the release
    3. CIncorporate them in the hardening Sprint
    4. DIncorporate them in the integration Sprint
  4. 4When does the adaptation occur in Scrum?
    1. ADuring the Scrum events
    2. BOnly at the Sprint Review
    3. Cat the Daily Scrum
    4. DDuring the Sprint Planning
  5. 5A company has four products. Which two of the following are acceptable ways of forming Scrum teams?
    1. AThere must be one PO for eacht product. It is not required to have one PO for two and more teams.
    2. BThere can be one PO for each product
    3. CThere can be a single PO for all products.
    4. DThere must be a single PO for all products
  6. 6The Product Owner should use user stories to compose the Product Backlog items.
    1. ATrue
    2. BFalse
  7. 7During a Sprint Review, the stakeholders notice that the product development progress is not very clearly visible and lacked transparency. Moreover, they are not able to understand the team’s next steps. Who bears the primary responsibility for this status?
    1. AThe Scrum Team
    2. BThe Scrum Master
    3. CThe Product Owner
    4. DThe Development Team
  8. 8The Product Owner is responsible for preparing the Sprint Goal before the Sprint Planning.
    1. ATrue
    2. BFalse
  9. 9Which options are acceptable when the Product Owner wants to be informed of the progress in the middle of the Sprint? (Choose two answers)
    1. AAttend the Daily Scrums.
    2. BAsk the Scrum Master for daily briefs.
    3. CCheck the task board in the project room (if exists)
    4. DAsk the Development Team for daily reports
    5. EAsk the team leader for daily briefs
  10. 10The Product Owner can delegate some of his/her responsibilities to the Development Team.
    1. ATrue
    2. BFalse

Information

Description
PO questions
Language
English
Views
389
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?