Scope

Huy Anh Vo 26 questions

Take the quiz

Questions in this quiz (26)

  1. 1The term ______ describes a product produced as part of a project.
    1. Avariance
    2. Bscope
    3. Cdeliverable
    4. Dwork package
  2. 2Scope refers to:
    1. Aeach level of work that is outlined in a work breakdown structure.
    2. Bthe end product created as part of a project that is delivered to the client.
    3. Ctasks that are decomposed into smaller tasks in a work breakdown structure.
    4. Dthe work involved in creating the products and the processes used to create them.
  3. 3_____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.
    1. ACollecting requirements
    2. BDefining scope
    3. CControlling scope
    4. DValidating scope
  4. 4_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.
    1. ACreating scope
    2. BDefining scope
    3. CControlling scope
    4. DValidating scope
  5. 5_____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables.
    1. ACreating scope
    2. BDefining scope
    3. CControlling scope
    4. DValidating scope
  6. 6Creating the WBS is a subprocess associated with the _____ process in project scope management.
    1. Aplanning
    2. Bmonitoring and controlling
    3. Cclosing
    4. Dexecuting
  7. 7The ______ documents how project needs will be analyzed, documented, and managed.
    1. Arequirements traceability matrix
    2. Brequirements management plan
    3. CWBS
    4. Dproject scope statement
  8. 8Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.
    1. Avariance
    2. Bbenchmarking
    3. Cprototyping
    4. Ddecomposition
  9. 9A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.
    1. Arequirements traceability matrix
    2. BGantt chart
    3. Cstate transition table
    4. Dentity-attribute-value model
  10. 10A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.
    1. Aproject charter
    2. Bbusiness case
    3. Cproject scope statement
    4. Dwork breakdown structure

Information

Description
Information Technology Quiz on Scope, created by Huy Anh Vo on 18/06/2019.
Language
English
Views
0
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?